4234 N ALEMAN DR 91356

Certificate Information: 4234 N ALEMAN DR 91356

Application / Permit
21010-20000-02830
Plan Check / Job No.
B21VN07251
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Patio Cover
Work Description
NEW (16'-0"x 15'-0") DETACHED POOL CABANA. WORK PER ENGINEER.
Permit Issued
Issued on 8/16/2021
Issuing Office
Current Status
CofO Issued on 10/15/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/9/2021 APPLICANT
Assigned to Plan Check Engineer 7/8/2021 TROY DEGUZMAN
Corrections Issued 7/11/2021 TROY DEGUZMAN
Quality Review Completed 7/15/2021 OMID HEDAYAT
Building Plans Picked Up 7/16/2021 APPLICANT
Plan Check Approved 8/16/2021 TROY DEGUZMAN
Issued 8/16/2021 APPLICANT
CofO in Progress 5/26/2022 DAVID SANDOVAL
CofO Issued 10/15/2022 DANIEL ORRANTE
Permit Finaled 10/15/2022 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 7/12/2021 TROY DEGUZMAN
Roof/Waste drainage to street Cleared 7/23/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 7/27/2021 CARLOS AGUILERA
ZA Case Cleared 8/4/2021 DANG NGUYEN
ZI Cleared 8/4/2021 DANG NGUYEN

Contact Information

Contractor Owner-Builder       ,
Engineer Cristescu,, Barbu D; Lic. No.: C72038 14401 SYLVAN STREET 209      VAN NUYS, CA 91401
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 10/12/2021 Not Ready for Inspection DAVID SANDOVAL
Footing/Foundation/Slab 10/12/2021 Corrections Issued DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 10/12/2021 SGSOV Not Ready DAVID SANDOVAL
Footing/Foundation/Slab 10/25/2021 Not Ready for Inspection DAVID SANDOVAL
Footing/Foundation/Slab 10/28/2021 Corrections Issued DAVID SANDOVAL
Footing/Foundation/Slab 11/2/2021 Approved DAVID SANDOVAL
Masonry Wall/Backfill 11/30/2021 Approved DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 2/28/2022 Approved DAVID SANDOVAL
Green Building Rough 2/28/2022 Approved DAVID SANDOVAL
Verify Sprinkler Sign Off 2/28/2022 Approved DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 4/25/2022 SGSOV Not Ready DAVID SANDOVAL
BUILDING-Rough-Frame 5/11/2022 Approved DAVID SANDOVAL
Final 5/11/2022 Corrections Issued DAVID SANDOVAL
Green Building Final 5/11/2022 Approved DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 5/11/2022 SGSOV Approved DAVID SANDOVAL
Service/Power Release 5/11/2022 Approved DAVID SANDOVAL
Smoke Detectors 5/11/2022 Approved DAVID SANDOVAL
Final 5/24/2022 OK to Issue CofO DAVID SANDOVAL