4234 N ALEMAN DR 91356
Certificate Information: 4234 N ALEMAN DR 91356
- Application / Permit
- 21010-20000-02830
- Plan Check / Job No.
- B21VN07251
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Patio Cover
- Work Description
- NEW (16'-0"x 15'-0") DETACHED POOL CABANA. WORK PER ENGINEER.
- Permit Issued
- Issued on 8/16/2021
- Issuing Office
- Current Status
- CofO Issued on 10/15/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/8/2021 | TROY DEGUZMAN |
| Corrections Issued | 7/11/2021 | TROY DEGUZMAN |
| Quality Review Completed | 7/15/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 7/16/2021 | APPLICANT |
| Plan Check Approved | 8/16/2021 | TROY DEGUZMAN |
| Issued | 8/16/2021 | APPLICANT |
| CofO in Progress | 5/26/2022 | DAVID SANDOVAL |
| CofO Issued | 10/15/2022 | DANIEL ORRANTE |
| Permit Finaled | 10/15/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 7/12/2021 | TROY DEGUZMAN |
| Roof/Waste drainage to street | Cleared | 7/23/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/27/2021 | CARLOS AGUILERA |
| ZA Case | Cleared | 8/4/2021 | DANG NGUYEN |
| ZI | Cleared | 8/4/2021 | DANG NGUYEN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cristescu,, Barbu D; Lic. No.: C72038 | 14401 SYLVAN STREET 209 VAN NUYS, CA 91401 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 10/12/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Footing/Foundation/Slab | 10/12/2021 | Corrections Issued | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 10/12/2021 | SGSOV Not Ready | DAVID SANDOVAL |
| Footing/Foundation/Slab | 10/25/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Footing/Foundation/Slab | 10/28/2021 | Corrections Issued | DAVID SANDOVAL |
| Footing/Foundation/Slab | 11/2/2021 | Approved | DAVID SANDOVAL |
| Masonry Wall/Backfill | 11/30/2021 | Approved | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2022 | Approved | DAVID SANDOVAL |
| Green Building Rough | 2/28/2022 | Approved | DAVID SANDOVAL |
| Verify Sprinkler Sign Off | 2/28/2022 | Approved | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 4/25/2022 | SGSOV Not Ready | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 5/11/2022 | Approved | DAVID SANDOVAL |
| Final | 5/11/2022 | Corrections Issued | DAVID SANDOVAL |
| Green Building Final | 5/11/2022 | Approved | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 5/11/2022 | SGSOV Approved | DAVID SANDOVAL |
| Service/Power Release | 5/11/2022 | Approved | DAVID SANDOVAL |
| Smoke Detectors | 5/11/2022 | Approved | DAVID SANDOVAL |
| Final | 5/24/2022 | OK to Issue CofO | DAVID SANDOVAL |