4301 N VALLEY MEADOW ROAD 91436
Certificate Information: 4301 N VALLEY MEADOW ROAD 91436
- Application / Permit
- 21010-20000-02823
- Plan Check / Job No.
- B21VN07200
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 83' X 89'7" 2-STORY SFD WITH ATTACHED THREE CAR GARAGE, NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 4/14/2022
- Issuing Office
- Current Status
- CofO Issued on 3/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2021 | RARES BODEA |
| Corrections Issued | 6/26/2021 | RARES BODEA |
| Quality Review Completed | 7/2/2021 | STEVEN KIM |
| Building Plans Picked Up | 7/7/2021 | APPLICANT |
| Applicant returned to address corrections | 10/28/2021 | RARES BODEA |
| Applicant returned to address corrections | 11/1/2021 | RARES BODEA |
| Applicant returned to address corrections | 11/17/2021 | RARES BODEA |
| Applicant returned to address corrections | 11/18/2021 | RARES BODEA |
| Plan Check Approved | 11/23/2021 | RARES BODEA |
| Issued | 4/14/2022 | APPLICANT |
| CofO in Progress | 1/24/2025 | JOHN COLEMAN |
| CofO Issued | 3/10/2025 | JOHN JANSON |
| Permit Finaled | 3/10/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 7/14/2021 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 7/14/2021 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 7/14/2021 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 7/14/2021 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 7/14/2021 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 7/14/2021 | CARLOS AGUILERA |
| Permit | Cleared | 7/14/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/19/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/19/2021 | CARLOS AGUILERA |
| Trees in Parkway | Cleared | 8/11/2021 | JOHN KIM |
| Distance to fire station | Cleared | 9/25/2021 | ROBERT DUFF |
| Hydrant and Access approval | Cleared | 9/25/2021 | ROBERT DUFF |
| Low Impact Development | Cleared | 10/1/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 10/7/2021 | CARLOS AGUILERA |
| GPI Written Notices | Cleared | 11/23/2021 | RARES BODEA |
| Grading Pre-Inspection | Cleared | 11/23/2021 | RARES BODEA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lin,, Chi Hsin; Lic. No.: GE2921 | 1722 CEDAR STREET APT G ALHAMBRA, CA 91801 |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
| Geologist | Kruger,, Mark Otto; Lic. No.: EG2345 | 10120 NATIONAL BLVD LOS ANGELES, CA 90034 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/26/2022 | Approved | DAVID SANDOVAL |
| Piling/Pier/Caisson | 12/8/2022 | Approved | VINCENT HANLEY |
| Deputy Reinf. Concrete | 12/9/2022 | Approved | VINCENT HANLEY |
| Deputy Reinf. Concrete | 12/29/2022 | Approved | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 12/29/2022 | Partial Approval | VINCENT HANLEY |
| Deputy Reinf. Concrete | 12/30/2022 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 12/30/2022 | Partial Approval | VINCENT HANLEY |
| Deputy Reinf. Concrete | 1/24/2023 | Approved | VINCENT HANLEY |
| Deputy Reinf. Concrete | 1/25/2023 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 1/26/2023 | Partial Approval | VINCENT HANLEY |
| Deputy Reinf. Concrete | 1/27/2023 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 1/31/2023 | Partial Approval | VINCENT HANLEY |
| Deputy Other (see comments) | 5/17/2023 | Approved | VINCENT HANLEY |
| Deputy Reinf. Concrete | 5/25/2023 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 5/30/2023 | Approved | VINCENT HANLEY |
| Deputy Reinf. Concrete | 5/31/2023 | Approved | VINCENT HANLEY |
| Deputy Reinf. Concrete | 6/8/2023 | Partial Approval | VINCENT HANLEY |
| Deputy Reinf. Concrete | 6/20/2023 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2023 | Partial Approval | VINCENT HANLEY |
| Deputy Wood Construction | 10/12/2023 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/10/2023 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2023 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 11/21/2023 | Approved | VINCENT HANLEY |
| HVAC-Rough | 11/22/2023 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 12/8/2023 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 12/19/2023 | Approved | VINCENT HANLEY |
| Deputy Reinf. Concrete | 1/4/2024 | Conditional Approval | VINCENT HANLEY |
| BUILDING-Rough-Frame | 1/10/2024 | Approved | VINCENT HANLEY |
| Green Building Rough | 1/10/2024 | Approved | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 1/10/2024 | Approved | VINCENT HANLEY |
| Insulation | 1/18/2024 | Approved | VINCENT HANLEY |
| Drywall Nailing | 1/30/2024 | Approved | MORRIS JACKSON |
| Shower Pan | 1/30/2024 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 2/12/2024 | Approved | VINCENT HANLEY |
| Gas Test | 3/22/2024 | Approved | VINCENT HANLEY |
| Underground Mechanical | 3/22/2024 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Final | 11/4/2024 | Conditional Approval | THOMAS FINNILA |
| HVAC-Final | 11/7/2024 | Approved | MORRIS JACKSON |
| PLUMBING-Final | 11/19/2024 | Approved | MORRIS JACKSON |
| ELECTRICAL-Final | 1/9/2025 | Approved | THOMAS FINNILA |
| Service/Power Release | 1/9/2025 | Approved | THOMAS FINNILA |
| Final | 1/24/2025 | OK to Issue CofO | JOHN COLEMAN |
| Green Building Final | 1/24/2025 | Approved | JOHN COLEMAN |
| SGSOV-Seismic Gas S/O Valve | 1/24/2025 | SGSOV Approved | JOHN COLEMAN |
| Smoke Detectors | 1/24/2025 | Approved | JOHN COLEMAN |
| Special/Order Compliance | 2/13/2025 | Corrections Issued | JOHN COLEMAN |