4610 N AVENUE 40 90065

Certificate Information: 4610 N AVENUE 40 90065

Application / Permit
21010-20000-02812
Plan Check / Job No.
B21VN07158
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW ONE STORY DETACHED 25' X 20'-10" ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) ALL WORK PER ENGINEERNIG “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
Permit Issued
Issued on 1/12/2022
Issuing Office
Current Status
CofO Issued on 1/10/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/8/2021 APPLICANT
Assigned to Plan Check Engineer 7/8/2021 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 7/15/2021 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 7/21/2021 OMID HEDAYAT
Building Plans Picked Up 7/22/2021 APPLICANT
Applicant returned to address corrections 11/9/2021 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 1/12/2022 KEISHAWN ROWE
Issued 1/12/2022 APPLICANT
CofO in Progress 12/29/2022 CRAIG VAUGHAN
Permit Finaled 1/10/2023 DEROLD HAUFF
CofO Issued 1/10/2023 DEROLD HAUFF
Permit Finaled 1/10/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/30/2021 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 8/2/2021 STEVE MELGAR
Sewer availability Cleared 8/2/2021 STEVE MELGAR
GPI Written Notices Cleared 11/15/2021 SEWADA ZADOORAN MILAGARDI
Grading Pre-Inspection Cleared 11/15/2021 SEWADA ZADOORAN MILAGARDI
Roof/Waste drainage to street Cleared 11/15/2021 STEVE MELGAR
Miscellaneous Cleared 11/16/2021 MIGUEL GAMBOA
Supp. Use District POD/CDO/TDO Cleared 12/27/2021 NASHYA JENSEN

Contact Information

Contractor M D M Custom Remodeling Inc; Lic. No.: 930166-B 5316 BABCOCK AVE      VALLEY VILLAGE, CA 91607
Engineer Keshishian,, Anthony; Lic. No.: C89551 2654 RISA D      GLENDALE, CA 91208

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/26/2022 Approved CRAIG VAUGHAN
PLUMBING-Rough 2/2/2022 Partial Approval CRAIG VAUGHAN
Wood Frame 2/2/2022 Partial Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 2/4/2022 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 2/24/2022 Corrections Issued SCOTT FINNILA
ELECTRICAL-Rough 2/24/2022 Approved SCOTT FINNILA
Green Building Rough 2/24/2022 Approved SCOTT FINNILA
HVAC-Rough 2/24/2022 Approved SCOTT FINNILA
MERV13>=Rough 2/24/2022 Approved SCOTT FINNILA
PLUMBING-Rough 2/24/2022 Approved SCOTT FINNILA
Sewer 2/24/2022 Approved SCOTT FINNILA
Verify Sprinkler Sign Off 2/24/2022 Approved SCOTT FINNILA
Insulation 3/3/2022 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 3/3/2022 Partial Approval CRAIG VAUGHAN
Drywall Nailing 3/14/2022 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 3/14/2022 Approved CRAIG VAUGHAN
Shower Pan 3/14/2022 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 7/19/2022 Approved CRAIG VAUGHAN
Final 7/19/2022 No Access for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 7/19/2022 Approved CRAIG VAUGHAN
Green Building Final 7/19/2022 No Access for Inspection CRAIG VAUGHAN
MERV13>=Final 7/19/2022 No Access for Inspection CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 7/19/2022 SGSOV Not Ready CRAIG VAUGHAN
Service/Power Release 7/19/2022 No Access for Inspection CRAIG VAUGHAN
Smoke Detectors 7/19/2022 No Access for Inspection CRAIG VAUGHAN
Final 11/2/2022 Corrections Issued CRAIG VAUGHAN
Green Building Final 11/2/2022 Approved CRAIG VAUGHAN
MERV13>=Final 11/2/2022 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 11/2/2022 SGSOV Approved CRAIG VAUGHAN
Service/Power Release 11/2/2022 Not Required CRAIG VAUGHAN
Smoke Detectors 11/2/2022 Approved CRAIG VAUGHAN
Final 12/16/2022 Corrections Issued CRAIG VAUGHAN
Gas Test 12/16/2022 Approved CRAIG VAUGHAN
Final 12/28/2022 OK to Issue CofO CRAIG VAUGHAN