16019 W TEMECULA ST 90272
Certificate Information: 16019 W TEMECULA ST 90272
- Application / Permit
- 21010-20000-02809
- Plan Check / Job No.
- B21VN07145
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 38' X 65' IRREGULAR SHAPED 2-STORY SFD W/ 2-CAR GARAGE. NFPA 13D FIRE SRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 9/8/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/15/2021 | RAPHAEL ROSAS |
| Corrections Issued | 7/19/2021 | RAPHAEL ROSAS |
| Quality Review Completed | 7/26/2021 | STEVEN KIM |
| Applicant returned to address corrections | 9/2/2021 | RAPHAEL ROSAS |
| Building Plans Picked Up | 9/3/2021 | APPLICANT |
| Applicant returned to address corrections | 4/18/2022 | RAPHAEL ROSAS |
| Plan Check Approved | 7/20/2022 | RAPHAEL ROSAS |
| Issued | 9/8/2022 | APPLICANT |
| CofO in Progress | 2/19/2025 | EVAN COOPER |
| CofO Issued | 2/21/2025 | RICHARD STEINBACH |
| Permit Finaled | 2/21/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 8/13/2021 | SAUL GARCIA |
| Permit | Cleared | 8/13/2021 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 8/17/2021 | SAUL GARCIA |
| Sewer availability | Cleared | 8/17/2021 | SAUL GARCIA |
| Hydrant and Access approval | Cleared | 10/7/2021 | KURT CORRAL |
| Coastal Zone | Cleared | 3/1/2022 | LAUREN PADICK |
| ZI | Cleared | 3/1/2022 | LAUREN PADICK |
| Trees in Parkway | Cleared | 3/23/2022 | RAPHAEL ROSAS |
| Low Impact Development | Cleared | 4/7/2022 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 6/27/2022 | CATHERINE ADROVER |
| GPI Written Notices | Cleared | 7/20/2022 | RAPHAEL ROSAS |
| Grading Pre-Inspection | Cleared | 7/20/2022 | RAPHAEL ROSAS |
Contact Information
| Contractor | Steven Ginter Construction Inc; Lic. No.: 680191-B | 1018 SIERRA PL TORRANCE, CA 90501 |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| MEL KHACHATOURIAN, (213) 796-6439 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/18/2023 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 8/18/2023 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 8/24/2023 | Partial Approval | ARAM AVEDISIAN |
| Deputy Reinf. Concrete | 8/29/2023 | Conditional Approval | EVAN COOPER |
| Footing/Foundation/Slab | 8/30/2023 | Partial Approval | EVAN COOPER |
| Deputy Wood Construction | 9/29/2023 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 9/29/2023 | Partial Approval | EVAN COOPER |
| Wood Frame | 10/27/2023 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2023 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 11/21/2023 | Approved | EVAN COOPER |
| Footing/Foundation/Slab | 11/29/2023 | Approved | EVAN COOPER |
| Deputy Wood Construction | 12/5/2023 | No Access for Inspection | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 12/26/2023 | Partial Approval | EVAN COOPER |
| HVAC-Rough | 12/26/2023 | Approved | EVAN COOPER |
| ELECTRICAL-Rough | 1/3/2024 | Corrections Issued | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 1/8/2024 | Approved | EVAN COOPER |
| ELECTRICAL-Rough | 1/8/2024 | Approved | EVAN COOPER |
| Green Building Rough | 1/8/2024 | Approved | EVAN COOPER |
| Verify Sprinkler Sign Off | 1/8/2024 | Approved | EVAN COOPER |
| Insulation | 1/12/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 1/12/2024 | Approved | JESUS RODRIGUEZ |
| Insulation | 1/22/2024 | Corrections Issued | EVAN COOPER |
| Drywall Nailing | 2/2/2024 | Approved | EVAN COOPER |
| Sewer | 2/9/2024 | Approved | EVAN COOPER |
| Shower Pan | 2/20/2024 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 2/23/2024 | Approved | EVAN COOPER |
| Grounding or Bonding | 3/6/2024 | Partial Approval | EVAN COOPER |
| Gas Test | 5/31/2024 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 10/16/2024 | Approved | EVAN COOPER |
| HVAC-Final | 10/16/2024 | Corrections Issued | EVAN COOPER |
| PLUMBING-Final | 10/16/2024 | Approved | EVAN COOPER |
| Final | 12/4/2024 | Corrections Issued | EVAN COOPER |
| Green Building Final | 12/4/2024 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 12/4/2024 | SGSOV Approved | EVAN COOPER |
| Service/Power Release | 12/4/2024 | Approved | EVAN COOPER |
| Smoke Detectors | 12/4/2024 | Approved | EVAN COOPER |
| Final | 2/19/2025 | OK to Issue CofO | EVAN COOPER |