20644 W HUMMINGBIRD CT 91326

Certificate Information: 20644 W HUMMINGBIRD CT 91326

Application / Permit
21010-20000-02806
Plan Check / Job No.
B21VN07137
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(TRACT 50505_LOT 219) PROPOSE TWO STORY SFD WITH ATTACHED GARAGE _ PER STANDARD PLAN 655_PLAN 4B _ BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D.
Permit Issued
Issued on 7/29/2022
Issuing Office
Current Status
CofO Issued on 8/24/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/9/2021 APPLICANT
Assigned to Plan Check Engineer 7/8/2021 DAWN MC NULTY
Corrections Issued 7/15/2021 DAWN MC NULTY
Quality Review Completed 7/16/2021 STEVEN KIM
Building Plans Picked Up 7/19/2021 APPLICANT
Plan Check Approved 3/14/2022 DAWN MC NULTY
Issued 7/29/2022 APPLICANT
CofO in Progress 8/23/2023 JEFFREY PARD
CofO Issued 8/24/2023 JOHN JANSON
Permit Finaled 8/24/2023 JOHN JANSON

Permit Application Clearance Information

"T" removal Cleared 11/18/2021 LAUREN PADICK
CPC Cleared 11/18/2021 LAUREN PADICK
CPC Cleared 11/18/2021 LAUREN PADICK
CPC Cleared 11/18/2021 LAUREN PADICK
Tract Map conditions Cleared 11/18/2021 LAUREN PADICK
ZA Case Cleared 11/18/2021 LAUREN PADICK
ZA Case Cleared 11/18/2021 LAUREN PADICK
ZI Cleared 11/18/2021 LAUREN PADICK
Low Impact Development Cleared 12/16/2021 AMMAR ELTAWIL
Address approval Cleared 1/10/2022 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 1/10/2022 LEE GUILBEAUX
Permit Cleared 1/10/2022 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 1/10/2022 DAWN MC NULTY
Roof/Waste drainage to street Cleared 1/10/2022 LEE GUILBEAUX
Sewer availability Cleared 1/10/2022 LEE GUILBEAUX
Hydrant and Access approval Cleared 3/1/2022 KURT CORRAL

Contact Information

Architect Swift,, Daniel R; Lic. No.: C32860 4601 WESTOWN PARKWAY SUITE 208      WEST DES MOINES, IA 50266
Contractor Shapell Homes Inc; Lic. No.: 1001034-B 1140 VIRGINIA DR ATTN: TOLL   BROTHERS - TAGGERT/LEGAL    FORT WASHINGTON, PA 19034
Engineer Hattar,, Basil Ibrahim; Lic. No.: GE2734 41837 SONOMA ROAD      PALMDALE, CA 93551
Engineer Wong,, Ramon Roman; Lic. No.: S2345 1800 E. 16TH STREET      SANTA ANA, CA 92701

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/18/2022 Partial Approval HENRY KIM
Footing/Foundation/Slab 12/29/2022 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 1/19/2023 Not Ready for Inspection HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 1/25/2023 Partial Approval HENRY KIM
Sewer 1/31/2023 Corrections Issued HENRY KIM
Sewer 2/1/2023 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 2/8/2023 Corrections Issued HENRY KIM
Underground Mechanical 2/21/2023 Partial Approval HENRY KIM
Deputy Wood Construction 3/7/2023 Conditional Approval HENRY KIM
Deputy Drilled-In Anchors 3/9/2023 Conditional Approval HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 3/13/2023 Corrections Issued HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 3/15/2023 Partial Approval HENRY KIM
Special/Order Compliance 3/15/2023 Partial Inspection JUSTIN HAWLEY
BUILDING-Rough-Frame 4/4/2023 Corrections Issued HENRY KIM
ELECTRICAL-Rough 4/4/2023 Corrections Issued HENRY KIM
Green Building Rough 4/4/2023 Approved HENRY KIM
HVAC-Rough 4/4/2023 Approved HENRY KIM
Interior/Exterior Lathing 4/4/2023 Corrections Issued HENRY KIM
PLUMBING-Rough 4/4/2023 Approved HENRY KIM
Underground Mechanical 4/4/2023 Approved HENRY KIM
Verify Sprinkler Sign Off 4/4/2023 Approved HENRY KIM
BUILDING-Rough-Frame 4/5/2023 Approved HENRY KIM
Interior/Exterior Lathing 4/5/2023 Partial Approval HENRY KIM
Pre-Inspection 4/5/2023 Partial Inspection JUSTIN HAWLEY
Insulation 4/7/2023 Partial Approval HENRY KIM
Drywall Nailing 4/13/2023 Approved HENRY KIM
Interior/Exterior Lathing 5/4/2023 Approved HENRY KIM
Gas Test 5/19/2023 Approved HENRY KIM
Interior/Exterior Lathing 5/24/2023 Not Ready for Inspection HENRY KIM
SGSOV-Seismic Gas S/O Valve 5/24/2023 SGSOV Approved HENRY KIM
ELECTRICAL-Rough 6/15/2023 Approved HENRY KIM
Interior/Exterior Lathing 6/26/2023 Approved HENRY KIM
Service/Power Release 7/7/2023 Approved HENRY KIM
ELECTRICAL-Final 8/7/2023 Not Ready for Inspection HENRY KIM
HVAC-Final 8/7/2023 Not Ready for Inspection HENRY KIM
PLUMBING-Final 8/7/2023 Not Ready for Inspection HENRY KIM
ELECTRICAL-Final 8/16/2023 Approved HENRY KIM
HVAC-Final 8/16/2023 Approved HENRY KIM
PLUMBING-Final 8/16/2023 Approved HENRY KIM
Final 8/18/2023 Corrections Issued HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 8/18/2023 Approved HENRY KIM
Green Building Final 8/18/2023 Approved HENRY KIM
Smoke Detectors 8/18/2023 Approved HENRY KIM
Final 8/22/2023 OK to Issue CofO JEFFREY PARD