8034 N CHERRYSTONE AVE 91402
Certificate Information: 8034 N CHERRYSTONE AVE 91402
- Application / Permit
- 21010-20000-02798
- Plan Check / Job No.
- B21VN07136
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 1-STORY 24'-6" x 20'-0" ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d).
- Permit Issued
- Issued on 8/16/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/24/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/11/2021 | SERGIO MUNIZ |
| Corrections Issued | 6/12/2021 | SERGIO MUNIZ |
| Applicant returned to address corrections | 7/28/2021 | SERGIO MUNIZ |
| Applicant returned to address corrections | 4/9/2022 | SERGIO MUNIZ |
| Applicant returned to address corrections | 7/14/2022 | SERGIO MUNIZ |
| Building Plans Picked Up | 7/19/2022 | APPLICANT |
| Plan Check Approved | 8/1/2022 | SARKIS HARABEDIAN |
| Issued | 8/16/2022 | APPLICANT |
| CofO in Progress | 9/18/2025 | VINCENT HANLEY |
| Permit Finaled | 9/24/2025 | RUBEN SALAS |
| CofO Issued | 9/24/2025 | RUBEN SALAS |
| Permit Finaled | 9/24/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 9/25/2021 | GILBERT URREA |
| Address approval | Cleared | 10/15/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 10/18/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 10/18/2021 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 2/9/2022 | TA ANH |
| Construction near power lines | Cleared | 3/31/2022 | WALTER RAMIREZ |
| Roof/Waste drainage to street | Cleared | 7/6/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ramirez, Cid, Jose Carlos; Lic. No.: C91046 | 5164 N RATON CIR LONG BEACH, CA 90807 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/4/2022 | Corrections Issued | MATTHEW NELSON |
| PLUMBING-Rough | 10/14/2022 | Partial Approval | GREGG CUMMINGS |
| Sewer | 10/14/2022 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 10/21/2022 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 10/21/2022 | Partial Approval | GREGG CUMMINGS |
| Footing/Foundation/Slab | 10/31/2022 | Corrections Issued | WILLIAM WREN |
| BUILDING-Rough-Frame | 11/16/2022 | Corrections Issued | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 11/16/2022 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 11/16/2022 | Approved | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 12/21/2022 | Partial Approval | GREGG CUMMINGS |
| Green Building Rough | 12/21/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Verify Sprinkler Sign Off | 12/21/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 12/29/2022 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 2/16/2023 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 2/16/2023 | Partial Approval | GREGG CUMMINGS |
| PLUMBING-Rough | 2/23/2023 | Approved | MATTHEW NELSON |
| Underground Mechanical | 2/23/2023 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 3/28/2023 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 3/28/2023 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 3/28/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Verify Sprinkler Sign Off | 3/28/2023 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 4/3/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 4/17/2023 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| Insulation | 4/21/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 4/28/2023 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 6/6/2023 | Partial Approval | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 10/4/2023 | Approved | DAVID MATSON |
| Final | 10/4/2023 | Corrections Issued | DAVID MATSON |
| Green Building Final | 10/4/2023 | Approved | DAVID MATSON |
| SGSOV-Seismic Gas S/O Valve | 10/4/2023 | SGSOV Approved | DAVID MATSON |
| Service/Power Release | 10/4/2023 | Not Ready for Inspection | DAVID MATSON |
| Smoke Detectors | 10/4/2023 | Approved | DAVID MATSON |
| Final | 8/9/2024 | No Access for Inspection | GREGG CUMMINGS |
| Service/Power Release | 8/9/2024 | No Access for Inspection | GREGG CUMMINGS |
| Final | 5/20/2025 | Corrections Issued | VINCENT HANLEY |
| Service/Power Release | 5/20/2025 | Corrections Issued | VINCENT HANLEY |
| ELECTRICAL-Final | 9/17/2025 | Approved | VINCENT HANLEY |
| Final | 9/17/2025 | OK to Issue CofO | VINCENT HANLEY |
| HVAC-Final | 9/17/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 9/17/2025 | Approved | VINCENT HANLEY |
| Service/Power Release | 9/17/2025 | Approved | VINCENT HANLEY |