12561 N SADDLE CT 91326
Certificate Information: 12561 N SADDLE CT 91326
- Application / Permit
- 21010-20000-02779
- Plan Check / Job No.
- B21VN07045
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 1-STORY SFD W/ ATTACHED GARAGE PER LA CITY STD PLAN #654 (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
- Permit Issued
- Issued on 1/3/2022
- Issuing Office
- Current Status
- CofO Issued on 10/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/8/2021 | NILOOFAR MEHRAIN |
| Plans on Hold | 7/15/2021 | RARES BODEA |
| Hold Released | 8/2/2021 | NILOOFAR MEHRAIN |
| Corrections Issued | 8/5/2021 | NILOOFAR MEHRAIN |
| Quality Review Completed | 8/11/2021 | STEVEN KIM |
| Building Plans Picked Up | 8/17/2021 | APPLICANT |
| Plan Check Approved | 12/28/2021 | NILOOFAR MEHRAIN |
| Issued | 1/3/2022 | APPLICANT |
| CofO in Progress | 10/21/2022 | JEFFREY PARD |
| CofO Issued | 10/22/2022 | MICHAEL SMITH |
| Permit Finaled | 10/22/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| "T" removal | Cleared | 10/20/2021 | DANG NGUYEN |
| CPC | Cleared | 10/20/2021 | DANG NGUYEN |
| Specific Plan | Cleared | 10/20/2021 | DANG NGUYEN |
| Tract Map conditions | Cleared | 10/20/2021 | DANG NGUYEN |
| Tract Map conditions | Cleared | 10/20/2021 | DANG NGUYEN |
| ZA Case | Cleared | 10/20/2021 | DANG NGUYEN |
| ZA Case | Cleared | 10/20/2021 | DANG NGUYEN |
| ZI | Cleared | 10/20/2021 | DANG NGUYEN |
| Address approval | Cleared | 10/21/2021 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 10/21/2021 | LEE GUILBEAUX |
| Permit | Cleared | 10/21/2021 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 10/21/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 10/21/2021 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 10/21/2021 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 12/2/2021 | ROBERT DUFF |
| Low Impact Development | Cleared | 12/16/2021 | AMMAR ELTAWIL |
| GPI Written Notices | Cleared | 12/28/2021 | NILOOFAR MEHRAIN |
| Grading Pre-Inspection | Cleared | 12/28/2021 | NILOOFAR MEHRAIN |
Contact Information
| Contractor | Shapell Homes Inc; Lic. No.: 1001034-B | 1140 VIRGINIA DR ATTN: TOLL BROTHERS - TAGGERT/LEGAL FORT WASHINGTON, PA 19034 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/24/2022 | Partial Approval | HENRY KIM |
| Footing/Foundation/Slab | 3/9/2022 | Approved | HENRY KIM |
| Deputy Pre-Stress Concrete | 3/10/2022 | Conditional Approval | HENRY KIM |
| Sewer | 3/23/2022 | Approved | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2022 | Partial Approval | HENRY KIM |
| Underground Mechanical | 5/9/2022 | Approved | SEAN WIRCH |
| Deputy Wood Construction | 6/8/2022 | Conditional Approval | HENRY KIM |
| Deputy Wood Construction | 6/13/2022 | Conditional Approval | HENRY KIM |
| ELECTRICAL-Rough | 6/23/2022 | Not Ready for Inspection | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2022 | Corrections Issued | HENRY KIM |
| HVAC-Rough | 6/23/2022 | Approved | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2022 | Partial Approval | HENRY KIM |
| BUILDING-Rough-Frame | 6/29/2022 | Not Ready for Inspection | HENRY KIM |
| Green Building Rough | 6/29/2022 | Not Ready for Inspection | HENRY KIM |
| Interior/Exterior Lathing | 6/29/2022 | Not Ready for Inspection | HENRY KIM |
| PLUMBING-Rough | 6/29/2022 | Not Ready for Inspection | HENRY KIM |
| Verify Sprinkler Sign Off | 6/29/2022 | Not Ready for Inspection | HENRY KIM |
| ELECTRICAL-Rough | 6/30/2022 | Corrections Issued | HENRY KIM |
| HVAC-Rough | 6/30/2022 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 6/30/2022 | Corrections Issued | HENRY KIM |
| PLUMBING-Rough | 6/30/2022 | Corrections Issued | HENRY KIM |
| ELECTRICAL-Rough | 7/5/2022 | Approved | HENRY KIM |
| Green Building Rough | 7/5/2022 | Corrections Issued | HENRY KIM |
| Interior/Exterior Lathing | 7/5/2022 | Not Ready for Inspection | HENRY KIM |
| PLUMBING-Rough | 7/5/2022 | Approved | HENRY KIM |
| Shower Pan | 7/5/2022 | Approved | HENRY KIM |
| BUILDING-Rough-Frame | 7/7/2022 | Approved | HENRY KIM |
| Green Building Rough | 7/7/2022 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 7/7/2022 | Partial Approval | HENRY KIM |
| Special/Order Compliance | 7/7/2022 | Corrections Issued | HENRY KIM |
| Verify Sprinkler Sign Off | 7/7/2022 | Approved | HENRY KIM |
| Insulation | 7/14/2022 | Partial Approval | HENRY KIM |
| Drywall Nailing | 7/21/2022 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 7/28/2022 | Partial Approval | HENRY KIM |
| Interior/Exterior Lathing | 8/1/2022 | Not Ready for Inspection | SEAN WIRCH |
| Interior/Exterior Lathing | 8/4/2022 | Approved | HENRY KIM |
| Drywall Nailing | 8/30/2022 | Approved | HENRY KIM |
| ELECTRICAL-Rough | 8/30/2022 | Approved | HENRY KIM |
| Gas Test | 8/30/2022 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 8/30/2022 | Partial Approval | HENRY KIM |
| SGSOV-Seismic Gas S/O Valve | 9/7/2022 | SGSOV Approved | JEFFREY PARD |
| Service/Power Release | 9/19/2022 | Not Ready for Inspection | HENRY KIM |
| Service/Power Release | 9/21/2022 | Approved | JEFFREY PARD |
| ELECTRICAL-Final | 10/13/2022 | Not Ready for Inspection | JEFFREY PARD |
| PLUMBING-Final | 10/13/2022 | Not Ready for Inspection | JEFFREY PARD |
| ELECTRICAL-Final | 10/19/2022 | Approved | JEFFREY PARD |
| HVAC-Final | 10/19/2022 | Approved | JEFFREY PARD |
| PLUMBING-Final | 10/19/2022 | Approved | JEFFREY PARD |
| Final | 10/20/2022 | OK to Issue CofO | JEFFREY PARD |
| Green Building Final | 10/20/2022 | Approved | JEFFREY PARD |
| Smoke Detectors | 10/20/2022 | Approved | JEFFREY PARD |