12561 N SADDLE CT 91326

Certificate Information: 12561 N SADDLE CT 91326

Application / Permit
21010-20000-02779
Plan Check / Job No.
B21VN07045
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 1-STORY SFD W/ ATTACHED GARAGE PER LA CITY STD PLAN #654 (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 1/3/2022
Issuing Office
Current Status
CofO Issued on 10/22/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/7/2021 APPLICANT
Assigned to Plan Check Engineer 7/8/2021 NILOOFAR MEHRAIN
Plans on Hold 7/15/2021 RARES BODEA
Hold Released 8/2/2021 NILOOFAR MEHRAIN
Corrections Issued 8/5/2021 NILOOFAR MEHRAIN
Quality Review Completed 8/11/2021 STEVEN KIM
Building Plans Picked Up 8/17/2021 APPLICANT
Plan Check Approved 12/28/2021 NILOOFAR MEHRAIN
Issued 1/3/2022 APPLICANT
CofO in Progress 10/21/2022 JEFFREY PARD
CofO Issued 10/22/2022 MICHAEL SMITH
Permit Finaled 10/22/2022 MICHAEL SMITH

Permit Application Clearance Information

"T" removal Cleared 10/20/2021 DANG NGUYEN
CPC Cleared 10/20/2021 DANG NGUYEN
Specific Plan Cleared 10/20/2021 DANG NGUYEN
Tract Map conditions Cleared 10/20/2021 DANG NGUYEN
Tract Map conditions Cleared 10/20/2021 DANG NGUYEN
ZA Case Cleared 10/20/2021 DANG NGUYEN
ZA Case Cleared 10/20/2021 DANG NGUYEN
ZI Cleared 10/20/2021 DANG NGUYEN
Address approval Cleared 10/21/2021 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 10/21/2021 LEE GUILBEAUX
Permit Cleared 10/21/2021 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 10/21/2021 LEE GUILBEAUX
Sewer availability Cleared 10/21/2021 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 10/21/2021 LEE GUILBEAUX
Hydrant and Access approval Cleared 12/2/2021 ROBERT DUFF
Low Impact Development Cleared 12/16/2021 AMMAR ELTAWIL
GPI Written Notices Cleared 12/28/2021 NILOOFAR MEHRAIN
Grading Pre-Inspection Cleared 12/28/2021 NILOOFAR MEHRAIN

Contact Information

Contractor Shapell Homes Inc; Lic. No.: 1001034-B 1140 VIRGINIA DR ATTN: TOLL   BROTHERS - TAGGERT/LEGAL    FORT WASHINGTON, PA 19034

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/24/2022 Partial Approval HENRY KIM
Footing/Foundation/Slab 3/9/2022 Approved HENRY KIM
Deputy Pre-Stress Concrete 3/10/2022 Conditional Approval HENRY KIM
Sewer 3/23/2022 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 5/5/2022 Partial Approval HENRY KIM
Underground Mechanical 5/9/2022 Approved SEAN WIRCH
Deputy Wood Construction 6/8/2022 Conditional Approval HENRY KIM
Deputy Wood Construction 6/13/2022 Conditional Approval HENRY KIM
ELECTRICAL-Rough 6/23/2022 Not Ready for Inspection HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 6/23/2022 Corrections Issued HENRY KIM
HVAC-Rough 6/23/2022 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 6/27/2022 Partial Approval HENRY KIM
BUILDING-Rough-Frame 6/29/2022 Not Ready for Inspection HENRY KIM
Green Building Rough 6/29/2022 Not Ready for Inspection HENRY KIM
Interior/Exterior Lathing 6/29/2022 Not Ready for Inspection HENRY KIM
PLUMBING-Rough 6/29/2022 Not Ready for Inspection HENRY KIM
Verify Sprinkler Sign Off 6/29/2022 Not Ready for Inspection HENRY KIM
ELECTRICAL-Rough 6/30/2022 Corrections Issued HENRY KIM
HVAC-Rough 6/30/2022 Approved HENRY KIM
Interior/Exterior Lathing 6/30/2022 Corrections Issued HENRY KIM
PLUMBING-Rough 6/30/2022 Corrections Issued HENRY KIM
ELECTRICAL-Rough 7/5/2022 Approved HENRY KIM
Green Building Rough 7/5/2022 Corrections Issued HENRY KIM
Interior/Exterior Lathing 7/5/2022 Not Ready for Inspection HENRY KIM
PLUMBING-Rough 7/5/2022 Approved HENRY KIM
Shower Pan 7/5/2022 Approved HENRY KIM
BUILDING-Rough-Frame 7/7/2022 Approved HENRY KIM
Green Building Rough 7/7/2022 Approved HENRY KIM
Interior/Exterior Lathing 7/7/2022 Partial Approval HENRY KIM
Special/Order Compliance 7/7/2022 Corrections Issued HENRY KIM
Verify Sprinkler Sign Off 7/7/2022 Approved HENRY KIM
Insulation 7/14/2022 Partial Approval HENRY KIM
Drywall Nailing 7/21/2022 Approved HENRY KIM
Interior/Exterior Lathing 7/28/2022 Partial Approval HENRY KIM
Interior/Exterior Lathing 8/1/2022 Not Ready for Inspection SEAN WIRCH
Interior/Exterior Lathing 8/4/2022 Approved HENRY KIM
Drywall Nailing 8/30/2022 Approved HENRY KIM
ELECTRICAL-Rough 8/30/2022 Approved HENRY KIM
Gas Test 8/30/2022 Approved HENRY KIM
Interior/Exterior Lathing 8/30/2022 Partial Approval HENRY KIM
SGSOV-Seismic Gas S/O Valve 9/7/2022 SGSOV Approved JEFFREY PARD
Service/Power Release 9/19/2022 Not Ready for Inspection HENRY KIM
Service/Power Release 9/21/2022 Approved JEFFREY PARD
ELECTRICAL-Final 10/13/2022 Not Ready for Inspection JEFFREY PARD
PLUMBING-Final 10/13/2022 Not Ready for Inspection JEFFREY PARD
ELECTRICAL-Final 10/19/2022 Approved JEFFREY PARD
HVAC-Final 10/19/2022 Approved JEFFREY PARD
PLUMBING-Final 10/19/2022 Approved JEFFREY PARD
Final 10/20/2022 OK to Issue CofO JEFFREY PARD
Green Building Final 10/20/2022 Approved JEFFREY PARD
Smoke Detectors 10/20/2022 Approved JEFFREY PARD