20320 W MARLOW LANE 91326
Certificate Information: 20320 W MARLOW LANE 91326
- Application / Permit
- 21010-20000-02759
- Plan Check / Job No.
- B21VN07006
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSE TWO STORY SFD WITH ATTACHED THREE CAR GARAGE_STANDARD PLAN#653_ PLAN 2B _ BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D.
- Permit Issued
- Issued on 4/5/2022
- Issuing Office
- Current Status
- CofO Issued on 6/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/8/2021 | DAWN MC NULTY |
| Corrections Issued | 7/14/2021 | DAWN MC NULTY |
| Quality Review Completed | 7/16/2021 | STEVEN KIM |
| Building Plans Picked Up | 7/19/2021 | APPLICANT |
| Plan Check Approved | 3/24/2022 | DAWN MC NULTY |
| Issued | 4/5/2022 | APPLICANT |
| CofO in Progress | 6/2/2023 | JEFFREY PARD |
| Permit Finaled | 6/6/2023 | MICHAEL SMITH |
| CofO Issued | 6/6/2023 | MICHAEL SMITH |
| Permit Finaled | 6/6/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| "T" removal | Cleared | 1/11/2022 | LAUREN PADICK |
| CPC | Cleared | 1/11/2022 | LAUREN PADICK |
| Frnt yard landscape/Water mgmt | Cleared | 1/11/2022 | LAUREN PADICK |
| Miscellaneous | Cleared | 1/11/2022 | LAUREN PADICK |
| Miscellaneous | Cleared | 1/11/2022 | LAUREN PADICK |
| Miscellaneous | Cleared | 1/11/2022 | LAUREN PADICK |
| Private street | Cleared | 1/11/2022 | LAUREN PADICK |
| Specific Plan | Cleared | 1/11/2022 | LAUREN PADICK |
| Tract Map conditions | Cleared | 1/11/2022 | LAUREN PADICK |
| ZA Case | Cleared | 1/11/2022 | LAUREN PADICK |
| ZA Case | Cleared | 1/11/2022 | LAUREN PADICK |
| Address approval | Cleared | 1/12/2022 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 1/12/2022 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 1/12/2022 | AMMAR ELTAWIL |
| Permit | Cleared | 1/12/2022 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 1/12/2022 | DAWN MC NULTY |
| Roof/Waste drainage to street | Cleared | 1/12/2022 | LEE GUILBEAUX |
| Sewer availability | Cleared | 1/12/2022 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 3/18/2022 | JOHN CONNEALLY |
Contact Information
| Architect | Niemerski,, Kenneth Chester; Lic. No.: C23971 | 52 DAWNWOOD LADERA RANCH, CA 92694 |
| Contractor | Shapell Homes Inc; Lic. No.: 1001034-B | 250 GIBRALTAR RD ATTN-TAGERT/LEGAL HOSHAM, PA 19044 |
| Engineer | Miller,, Karen Lynn; Lic. No.: GE2257 | 6634 VALJEAN AVENUE VAN NUYS, CA 91406 |
| Engineer | Van, Gaale, Mark Allan; Lic. No.: C58680 | 185 W ORANGEWOOD AVE SUITE 200 ORANGE, CA 92868 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 10/3/2022 | Approved | SEAN WIRCH |
| Footing/Foundation/Slab | 10/18/2022 | Approved | HENRY KIM |
| Deputy Reinf. Concrete | 10/20/2022 | Conditional Approval | HENRY KIM |
| Sewer | 10/25/2022 | Approved | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2022 | Partial Approval | HENRY KIM |
| Deputy Pre-Stress Concrete | 11/8/2022 | Corrections Issued | HENRY KIM |
| Deputy Drilled-In Anchors | 11/17/2022 | Conditional Approval | HENRY KIM |
| Underground Mechanical | 11/17/2022 | Approved | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 11/23/2022 | Approved | JEFFREY PARD |
| ELECTRICAL-Rough | 12/8/2022 | Not Ready for Inspection | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2022 | Not Ready for Inspection | HENRY KIM |
| HVAC-Rough | 12/8/2022 | Not Ready for Inspection | HENRY KIM |
| PLUMBING-Rough | 12/8/2022 | Not Ready for Inspection | HENRY KIM |
| BUILDING-Rough-Frame | 12/9/2022 | Not Ready for Inspection | JEFFREY PARD |
| Green Building Rough | 12/9/2022 | Not Ready for Inspection | JEFFREY PARD |
| Interior/Exterior Lathing | 12/9/2022 | Not Ready for Inspection | JEFFREY PARD |
| Verify Sprinkler Sign Off | 12/9/2022 | Not Ready for Inspection | JEFFREY PARD |
| ELECTRICAL-Rough | 12/13/2022 | Approved | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2022 | Corrections Issued | HENRY KIM |
| HVAC-Rough | 12/13/2022 | Not Ready for Inspection | HENRY KIM |
| PLUMBING-Rough | 12/13/2022 | Not Ready for Inspection | HENRY KIM |
| BUILDING-Rough-Frame | 12/14/2022 | Not Ready for Inspection | HENRY KIM |
| Deputy Wood Construction | 12/14/2022 | Conditional Approval | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2022 | Partial Approval | HENRY KIM |
| Green Building Rough | 12/14/2022 | Not Ready for Inspection | HENRY KIM |
| HVAC-Rough | 12/14/2022 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 12/14/2022 | Not Ready for Inspection | HENRY KIM |
| PLUMBING-Rough | 12/14/2022 | Approved | HENRY KIM |
| Verify Sprinkler Sign Off | 12/14/2022 | Approved | HENRY KIM |
| BUILDING-Rough-Frame | 12/20/2022 | Corrections Issued | HENRY KIM |
| Green Building Rough | 12/20/2022 | Corrections Issued | HENRY KIM |
| Interior/Exterior Lathing | 12/20/2022 | Partial Approval | HENRY KIM |
| Drywall Nailing | 12/27/2022 | Not Ready for Inspection | JEFFREY PARD |
| Green Building Rough | 12/27/2022 | Not Ready for Inspection | JEFFREY PARD |
| Gas Test | 1/25/2023 | Approved | HENRY KIM |
| BUILDING-Rough-Frame | 1/27/2023 | Corrections Issued | HENRY KIM |
| Green Building Rough | 1/27/2023 | Corrections Issued | HENRY KIM |
| Service/Power Release | 2/17/2023 | Not Ready for Inspection | HENRY KIM |
| Service/Power Release | 2/22/2023 | Approved | JEFFREY PARD |
| SGSOV-Seismic Gas S/O Valve | 5/4/2023 | SGSOV Approved | HENRY KIM |
| ELECTRICAL-Final | 5/30/2023 | Approved | JEFFREY PARD |
| HVAC-Final | 5/30/2023 | Approved | JEFFREY PARD |
| PLUMBING-Final | 5/30/2023 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 6/1/2023 | Approved | JEFFREY PARD |
| Drywall Nailing | 6/1/2023 | Approved | JEFFREY PARD |
| Final | 6/1/2023 | OK to Issue CofO | JEFFREY PARD |
| Green Building Final | 6/1/2023 | Approved | JEFFREY PARD |
| Green Building Rough | 6/1/2023 | Approved | JEFFREY PARD |
| Smoke Detectors | 6/1/2023 | Approved | JEFFREY PARD |