20314 W MARLOW LANE 91326

Certificate Information: 20314 W MARLOW LANE 91326

Application / Permit
21010-20000-02758
Plan Check / Job No.
B21VN07006
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSE TWO STORY SFD WITH ATTACHED THREE CAR GARAGE_STANDARD PLAN#653_ PLAN 1C _ BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D.
Permit Issued
Issued on 4/5/2022
Issuing Office
Current Status
CofO Issued on 6/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/4/2021 APPLICANT
Assigned to Plan Check Engineer 7/8/2021 DAWN MC NULTY
Corrections Issued 7/14/2021 DAWN MC NULTY
Quality Review Completed 7/16/2021 STEVEN KIM
Building Plans Picked Up 7/19/2021 APPLICANT
Plan Check Approved 3/24/2022 DAWN MC NULTY
Issued 4/5/2022 APPLICANT
CofO in Progress 6/6/2023 JEFFREY PARD
Permit Finaled 6/6/2023 MICHAEL SMITH
CofO Issued 6/6/2023 MICHAEL SMITH
Permit Finaled 6/6/2023 MICHAEL SMITH

Permit Application Clearance Information

"T" removal Cleared 1/11/2022 LAUREN PADICK
CPC Cleared 1/11/2022 LAUREN PADICK
Frnt yard landscape/Water mgmt Cleared 1/11/2022 LAUREN PADICK
Miscellaneous Cleared 1/11/2022 LAUREN PADICK
Miscellaneous Cleared 1/11/2022 LAUREN PADICK
Miscellaneous Cleared 1/11/2022 LAUREN PADICK
Private street Cleared 1/11/2022 LAUREN PADICK
Specific Plan Cleared 1/11/2022 LAUREN PADICK
Tract Map conditions Cleared 1/11/2022 LAUREN PADICK
ZA Case Cleared 1/11/2022 LAUREN PADICK
ZA Case Cleared 1/11/2022 LAUREN PADICK
Address approval Cleared 1/12/2022 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 1/12/2022 LEE GUILBEAUX
Low Impact Development Cleared 1/12/2022 AMMAR ELTAWIL
Permit Cleared 1/12/2022 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 1/12/2022 DAWN MC NULTY
Roof/Waste drainage to street Cleared 1/12/2022 LEE GUILBEAUX
Sewer availability Cleared 1/12/2022 LEE GUILBEAUX
Hydrant and Access approval Cleared 3/18/2022 JOHN CONNEALLY

Contact Information

Architect Niemerski,, Kenneth Chester; Lic. No.: C23971 52 DAWNWOOD      LADERA RANCH, CA 92694
Contractor Shapell Homes Inc; Lic. No.: 1001034-B 250 GIBRALTAR RD   ATTN-TAGERT/LEGAL    HOSHAM, PA 19044
Engineer Miller,, Karen Lynn; Lic. No.: GE2257 6634 VALJEAN AVENUE      VAN NUYS, CA 91406
Engineer Van, Gaale, Mark Allan; Lic. No.: C58680 185 W ORANGEWOOD AVE SUITE 200      ORANGE, CA 92868

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/11/2022 Partial Approval JEFFREY PARD
Deputy Pre-Stress Concrete 10/25/2022 Conditional Approval HENRY KIM
Footing/Foundation/Slab 10/26/2022 Approved HENRY KIM
Sewer 11/4/2022 Approved HENRY KIM
Deputy Pre-Stress Concrete 11/8/2022 Corrections Issued HENRY KIM
Underground Mechanical 11/17/2022 Not Ready for Inspection HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 11/23/2022 Approved JEFFREY PARD
Underground Mechanical 11/29/2022 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 12/15/2022 Corrections Issued HENRY KIM
Deputy Drilled-In Anchors 12/27/2022 Approved JEFFREY PARD
Deputy Wood Construction 1/6/2023 Approved JEFFREY PARD
ELECTRICAL-Rough 1/6/2023 Approved HENRY KIM
HVAC-Rough 1/6/2023 Corrections Issued HENRY KIM
PLUMBING-Rough 1/6/2023 Corrections Issued HENRY KIM
HVAC-Rough 1/10/2023 Corrections Issued HENRY KIM
PLUMBING-Rough 1/10/2023 Not Ready for Inspection HENRY KIM
PLUMBING-Rough 1/11/2023 Approved HENRY KIM
Pre-Inspection 1/11/2023 Partial Inspection JUSTIN HAWLEY
Deputy Pre-Stress Concrete 1/13/2023 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 1/13/2023 Partial Approval HENRY KIM
HVAC-Rough 1/13/2023 Approved HENRY KIM
BUILDING-Rough-Frame 1/18/2023 Approved HENRY KIM
Green Building Rough 1/18/2023 Approved HENRY KIM
Interior/Exterior Lathing 1/18/2023 Partial Approval HENRY KIM
Verify Sprinkler Sign Off 1/18/2023 Approved HENRY KIM
Drywall Nailing 1/31/2023 Approved HENRY KIM
Interior/Exterior Lathing 1/31/2023 Approved HENRY KIM
Service/Power Release 3/13/2023 Approved HENRY KIM
Deputy Other (see comments) 3/21/2023 Conditional Approval HENRY KIM
Gas Test 3/30/2023 Approved HENRY KIM
SGSOV-Seismic Gas S/O Valve 5/5/2023 SGSOV Approved HENRY KIM
Final 6/1/2023 OK to Issue CofO JEFFREY PARD
Green Building Final 6/1/2023 Approved JEFFREY PARD
Smoke Detectors 6/1/2023 Approved JEFFREY PARD