15620 W WOODVALE ROAD 91436

Certificate Information: 15620 W WOODVALE ROAD 91436

Application / Permit
21010-20000-02750
Plan Check / Job No.
B21VN06998
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORY SFD W/ ATTACHED GARAGE & BASEMENT (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 3/15/2022
Issuing Office
Current Status
CofO Issued on 6/15/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/4/2021 APPLICANT
Assigned to Plan Check Engineer 6/17/2021 NILOOFAR MEHRAIN
Corrections Issued 6/22/2021 NILOOFAR MEHRAIN
Quality Review Completed 6/23/2021 CHON CHIO KUO
Building Plans Picked Up 6/25/2021 APPLICANT
Applicant returned to address corrections 9/16/2021 NILOOFAR MEHRAIN
Applicant returned to address corrections 9/21/2021 NILOOFAR MEHRAIN
Applicant returned to address corrections 12/22/2021 NILOOFAR MEHRAIN
Applicant returned to address corrections 1/20/2022 NILOOFAR MEHRAIN
Plan Check Approved 3/10/2022 NILOOFAR MEHRAIN
Issued 3/15/2022 APPLICANT
CofO in Progress 6/15/2026 SEAN WIRCH
Permit Finaled 6/15/2026 JOHN JANSON
CofO Issued 6/15/2026 JOHN JANSON
Permit Finaled 6/15/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 6/29/2021 GABRIEL ROBLES
BHO/Hillside ordinance Cleared 6/29/2021 GABRIEL ROBLES
BHO/Hillside ordinance Cleared 6/29/2021 GABRIEL ROBLES
BHO/Hillside ordinance Cleared 6/29/2021 GABRIEL ROBLES
BHO/Hillside ordinance Cleared 6/29/2021 GABRIEL ROBLES
BHO/Hillside ordinance Cleared 6/29/2021 GABRIEL ROBLES
Permit Cleared 6/29/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 6/30/2021 GABRIEL ROBLES
Sewer availability Cleared 6/30/2021 GABRIEL ROBLES
Trees in Parkway Cleared 7/28/2021 JOHN KIM
Low Impact Development Cleared 8/9/2021 MICHAEL SCADUTO
Roof/Waste drainage to street Cleared 8/11/2021 GABRIEL ROBLES
Hydrant and Access approval Cleared 9/10/2021 MATTHEW CRAIG
GPI Written Notices Cleared 12/22/2021 NILOOFAR MEHRAIN
Grading Pre-Inspection Cleared 12/22/2021 NILOOFAR MEHRAIN
Excavation more than 5-ft deep Cleared 1/20/2022 CALOSHA APPROVED

Contact Information

Contractor Luxe Development Inc; Lic. No.: 993473-B 329 N WETHERLY DRIVE #205      BEVERLY HILLS, CA 90211
Engineer Pirbadian,, Amir; Lic. No.: C72413 5435 BALBOA BLVD 214      ENCINO, CA 91342

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/14/2022 Approved DAVID SANDOVAL
Deputy Shotcrete 5/13/2022 Conditional Approval DAVID SANDOVAL
Excavation/Setback/Form/Re-Bar 6/22/2022 Approved VINCENT HANLEY
Deputy Reinf. Concrete 6/30/2022 Approved VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 6/30/2022 Partial Approval VINCENT HANLEY
Footing/Foundation/Slab 6/30/2022 Partial Approval VINCENT HANLEY
Deputy Shotcrete 7/8/2022 Approved VINCENT HANLEY
PLUMBING-Rough 7/25/2022 Partial Approval VINCENT HANLEY
Piling/Pier/Caisson 8/29/2022 Corrections Issued DAVID SANDOVAL
Footing/Foundation/Slab 9/2/2022 Partial Approval DAVID SANDOVAL
Piling/Pier/Caisson 9/13/2022 Partial Approval VINCENT HANLEY
Shower Pan 9/30/2022 Approved VINCENT HANLEY
Underground Mechanical 9/30/2022 Partial Approval VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 10/13/2022 Partial Approval VINCENT HANLEY
Footing/Foundation/Slab 10/13/2022 Partial Approval VINCENT HANLEY
Underground Mechanical 10/13/2022 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 10/26/2022 Corrections Issued JEFFREY BULL
Footing/Foundation/Slab 10/26/2022 Approved JEFFREY BULL
Deputy Wood Construction 10/27/2022 Conditional Approval KRISTEN CAUSEY
Floor/Roof Diaphrgm/Shear Wall 10/31/2022 Partial Approval DAVID SANDOVAL
Deputy Wood Construction 11/18/2022 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 11/21/2022 Partial Approval VINCENT HANLEY
Special/Order Compliance 11/21/2022 Approved JON MCHUGH
Footing/Foundation/Slab 12/1/2022 Approved VINCENT HANLEY
PLUMBING-Rough 2/13/2023 Approved VINCENT HANLEY
Sewer 2/13/2023 Approved VINCENT HANLEY
ELECTRICAL-Rough 2/21/2023 Approved VINCENT HANLEY
HVAC-Rough 2/21/2023 Approved VINCENT HANLEY
Shower Pan 2/23/2023 Approved JESUS PINEDA
Interior/Exterior Lathing 3/30/2023 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 5/17/2023 Partial Approval VINCENT HANLEY
Green Building Rough 5/17/2023 Not Ready for Inspection VINCENT HANLEY
Verify Sprinkler Sign Off 5/17/2023 Approved VINCENT HANLEY
Insulation 6/9/2023 Approved VINCENT HANLEY
Interior/Exterior Lathing 6/9/2023 Approved VINCENT HANLEY
Drywall Nailing 6/23/2023 Approved JEFFREY BULL
ELECTRICAL-Final 2/23/2024 Corrections Issued VINCENT HANLEY
HVAC-Final 2/23/2024 Corrections Issued VINCENT HANLEY
Service/Power Release 2/23/2024 Corrections Issued VINCENT HANLEY
Service/Power Release 2/28/2024 Approved VINCENT HANLEY
Gas Test 3/7/2024 Approved VINCENT HANLEY
HVAC-Final 3/7/2024 Approved VINCENT HANLEY
PLUMBING-Final 3/7/2024 Approved VINCENT HANLEY
BUILDING-Rough-Frame 5/9/2024 Approved VINCENT HANLEY
ELECTRICAL-Final 5/9/2024 Approved VINCENT HANLEY
Final 5/9/2024 Corrections Issued VINCENT HANLEY
Green Building Final 5/9/2024 Approved VINCENT HANLEY
Green Building Rough 5/9/2024 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 5/9/2024 SGSOV Approved VINCENT HANLEY
Smoke Detectors 5/9/2024 Approved VINCENT HANLEY
Pre-Inspection 5/10/2024 Approved VINCENT HANLEY
Final 3/24/2026 Corrections Issued SEAN WIRCH
Pre-Inspection 4/21/2026 Partial Inspection SEAN WIRCH
Final 4/30/2026 Partial Inspection SEAN WIRCH
Final 6/16/2026 OK to Issue CofO SEAN WIRCH