9601 N CLYBOURN AVE 91352
Certificate Information: 9601 N CLYBOURN AVE 91352
- Application / Permit
- 21010-20000-02745
- Plan Check / Job No.
- B21VN06979
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED 2-STORY ADU WITH GARAGE BELOW.
- Permit Issued
- Issued on 9/23/2022
- Issuing Office
- Current Status
- CofO Issued on 12/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/8/2021 | JOE VO |
| Corrections Issued | 7/11/2021 | JOE VO |
| Quality Review Completed | 7/21/2021 | MICHAEL PEREZ |
| Applicant returned to address corrections | 12/6/2021 | JOE VO |
| Applicant returned to address corrections | 7/26/2022 | JOE VO |
| Plan Check Approved | 8/31/2022 | JOE VO |
| Issued | 9/23/2022 | APPLICANT |
| CofO in Progress | 11/12/2025 | DAVID ANDERSON |
| Permit Finaled | 12/17/2025 | RUBEN SALAS |
| CofO Issued | 12/17/2025 | RUBEN SALAS |
| Permit Finaled | 12/17/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Specific Plan | Cleared | 9/29/2021 | PEGGY MALONE-BROWN |
| Address approval | Cleared | 10/29/2021 | CARLOS AGUILERA |
| Permit | Cleared | 10/29/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 11/2/2021 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 3/4/2022 | DWAYNE LAURENT |
| Low Impact Development | Cleared | 4/21/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 5/5/2022 | JOHN LIN |
| Grading Pre-Inspection | Cleared | 5/27/2022 | KIRK LINKLATER |
| Sewer availability | Cleared | 8/10/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ebrahimi,, Amirhosin; Lic. No.: C92049 | 8619 RESEDA BLVD UNIT 304B NORTHRIDGE, CA 91324 |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/19/2023 | Not Ready for Inspection | DAVID ANDERSON |
| METHANE-Barrier | 9/19/2023 | Corrections Issued | DAVID ANDERSON |
| METHANE-Subgrade | 9/19/2023 | Corrections Issued | DAVID ANDERSON |
| Gas Test | 10/13/2023 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 10/13/2023 | Partial Approval | DAVID ANDERSON |
| Wood Frame | 10/13/2023 | Partial Approval | DAVID ANDERSON |
| Insulation | 10/16/2023 | Conditional Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2023 | Partial Approval | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2023 | Approved | DAVID ANDERSON |
| Deputy Wood Construction | 12/15/2023 | Conditional Approval | ROBERT GOLD |
| BUILDING-Rough-Frame | 1/16/2024 | Corrections Issued | DAVID ANDERSON |
| ELECTRICAL-Rough | 1/16/2024 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/16/2024 | Approved | DAVID ANDERSON |
| Green Building Rough | 1/16/2024 | Not Ready for Inspection | DAVID ANDERSON |
| HVAC-Rough | 1/16/2024 | Corrections Issued | DAVID ANDERSON |
| METHANE-Rough | 1/16/2024 | Corrections Issued | DAVID ANDERSON |
| PLUMBING-Rough | 1/16/2024 | Approved | DAVID ANDERSON |
| Verify Sprinkler Sign Off | 1/16/2024 | Corrections Issued | DAVID ANDERSON |
| Wood Frame | 1/16/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Special/Order Compliance | 1/18/2024 | Corrections Issued | DAVID ANDERSON |
| BUILDING-Rough-Frame | 1/30/2024 | Approved | DAVID ANDERSON |
| Green Building Rough | 1/30/2024 | Approved | DAVID ANDERSON |
| HVAC-Rough | 1/30/2024 | Approved | DAVID ANDERSON |
| METHANE-Rough | 1/30/2024 | Approved | DAVID ANDERSON |
| Verify Sprinkler Sign Off | 1/30/2024 | Approved | DAVID ANDERSON |
| Wood Frame | 1/30/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Underground Mechanical | 4/12/2024 | Partial Approval | DAVID ANDERSON |
| Underground Mechanical | 5/6/2024 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 6/13/2024 | Partial Approval | DAVID ANDERSON |
| Insulation | 6/26/2024 | Approved | DAVID ANDERSON |
| Drywall Nailing | 7/15/2024 | Approved | DAVID ANDERSON |
| Shower Pan | 8/28/2024 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 9/5/2024 | Approved | DAVID ANDERSON |
| Final | 6/27/2025 | Corrections Issued | DAVID ANDERSON |
| Footing/Foundation/Slab | 6/27/2025 | Approved | DAVID ANDERSON |
| Green Building Final | 6/27/2025 | Approved | DAVID ANDERSON |
| METHANE-Barrier | 6/27/2025 | Approved | DAVID ANDERSON |
| METHANE-Subgrade | 6/27/2025 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 6/27/2025 | SGSOV Approved | DAVID ANDERSON |
| Service/Power Release | 6/27/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Smoke Detectors | 6/27/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Final | 10/28/2025 | OK to Issue CofO | DAVID ANDERSON |
| Service/Power Release | 10/28/2025 | Approved | DAVID ANDERSON |
| Smoke Detectors | 10/28/2025 | Approved | DAVID ANDERSON |