10618 N JOHANNA AVE 91040

Certificate Information: 10618 N JOHANNA AVE 91040

Application / Permit
21010-20000-02730
Plan Check / Job No.
B21VN06916
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW IRR. SHAPED 47'-0" x 33'-1" ACCESSORY DWELLING UNIT (800 sf) ADDITION TO (E) DET. STORAGE BLD; [ADU HEIGHT: MAX 16'] PER CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g); NFPA-13D SPRINKLER SYSTEM REQUIRED
Permit Issued
Issued on 11/26/2021
Issuing Office
Current Status
CofO Issued on 5/2/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/3/2021 APPLICANT
Assigned to Plan Check Engineer 6/17/2021 SEAN SHAHMIRI
Corrections Issued 6/19/2021 SEAN SHAHMIRI
Quality Review Completed 6/23/2021 OMID HEDAYAT
Building Plans Picked Up 6/25/2021 APPLICANT
Plan Check Approved 10/15/2021 SEAN SHAHMIRI
Issued 11/26/2021 APPLICANT
CofO in Progress 4/27/2023 DAVID ANDERSON
Permit Finaled 5/2/2023 MICHAEL SMITH
CofO Issued 5/2/2023 MICHAEL SMITH
Permit Finaled 5/2/2023 MICHAEL SMITH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 6/19/2021 SEAN SHAHMIRI
Address approval Cleared 7/12/2021 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 7/12/2021 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 7/12/2021 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 7/12/2021 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 7/12/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 7/13/2021 CARLOS AGUILERA
Sewer availability Cleared 7/13/2021 CARLOS AGUILERA
Specific Plan Cleared 8/9/2021 ANDREW JORGENSEN
Hydrant and Access approval Cleared 10/3/2021 JOHN CONNEALLY
Roof/Waste drainage to street Cleared 10/12/2021 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Baraty,, Patrick; Lic. No.: S5900 1819 SUNSHINE COURT      GLENDALE, CA 91208

Inspector Information

MATTHEW NELSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/3/2021 Approved WILLIAM KUEHN
PLUMBING-Rough 4/26/2022 Not Ready for Inspection MATTHEW NELSON
Wood Frame 4/26/2022 Not Ready for Inspection MATTHEW NELSON
PLUMBING-Rough 4/28/2022 Partial Approval GREGG CUMMINGS
Wood Frame 4/28/2022 Partial Approval GREGG CUMMINGS
Insulation 4/29/2022 Partial Approval WILLIAM WREN
Underground Mechanical 4/29/2022 Partial Approval WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 5/9/2022 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 5/23/2022 Partial Approval MATTHEW NELSON
Deputy Wood Construction 5/26/2022 Conditional Approval WILLIAM WREN
ELECTRICAL-Rough 5/27/2022 Not Ready for Inspection MATTHEW NELSON
HVAC-Rough 5/27/2022 Not Ready for Inspection MATTHEW NELSON
PLUMBING-Rough 5/27/2022 Approved MATTHEW NELSON
BUILDING-Rough-Frame 5/31/2022 Partial Approval MATTHEW NELSON
Green Building Rough 5/31/2022 Approved MATTHEW NELSON
Verify Sprinkler Sign Off 5/31/2022 Not Ready for Inspection MATTHEW NELSON
BUILDING-Rough-Frame 6/2/2022 Conditional Approval WILLIAM WREN
ELECTRICAL-Rough 6/2/2022 Approved WILLIAM WREN
HVAC-Rough 6/2/2022 Corrections Issued WILLIAM WREN
Interior/Exterior Lathing 6/7/2022 Approved MATTHEW NELSON
Insulation 6/9/2022 Approved MATTHEW NELSON
Drywall Nailing 6/21/2022 Approved DAVID ANDERSON
Gas Test 8/29/2022 Corrections Issued DAVID ANDERSON
BUILDING-Rough-Frame 10/17/2022 Not Ready for Inspection DAVID ANDERSON
Final 10/17/2022 Corrections Issued DAVID ANDERSON
Green Building Final 10/17/2022 Not Ready for Inspection DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 10/17/2022 SGSOV Approved DAVID ANDERSON
Smoke Detectors 10/17/2022 Approved DAVID ANDERSON
Verify Sprinkler Sign Off 10/17/2022 Not Ready for Inspection DAVID ANDERSON
BUILDING-Rough-Frame 11/4/2022 Approved DAVID ANDERSON
ELECTRICAL-Final 11/4/2022 Not Ready for Inspection DAVID ANDERSON
Final 11/4/2022 Not Ready for Inspection DAVID ANDERSON
Green Building Final 11/4/2022 Approved DAVID ANDERSON
HVAC-Final 11/4/2022 Approved DAVID ANDERSON
PLUMBING-Final 11/4/2022 Approved DAVID ANDERSON
Verify Sprinkler Sign Off 11/4/2022 Approved DAVID ANDERSON
ELECTRICAL-Rough 11/15/2022 Approved DAVID ANDERSON
ELECTRICAL-Final 11/18/2022 Corrections Issued DAVID ANDERSON
Final 11/18/2022 Not Ready for Inspection DAVID ANDERSON
ELECTRICAL-Final 11/21/2022 Approved DAVID ANDERSON
Final 4/21/2023 Not Ready for Inspection DAVID ANDERSON
Final 4/27/2023 OK to Issue CofO DAVID ANDERSON