7724 N LUBAO AVE 91306
Certificate Information: 7724 N LUBAO AVE 91306
- Application / Permit
- 21010-20000-02723
- Plan Check / Job No.
- B21VN06879
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 40' X 30'-8" DETACHED ACCESSORY DWELLING UNIT PER LAMC12.22.A.33(C) AND (D). ALL WORK PER WFPP. "COMPLY WITH DEPARTMENT ORDER EFFECTIVE DATE 5/11/21. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE."
- Permit Issued
- Issued on 10/31/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/10/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/8/2021 | JENNIFER LEE |
| Corrections Issued | 6/9/2021 | JENNIFER LEE |
| Applicant returned to address corrections | 2/14/2022 | JENNIFER LEE |
| Building Plans Picked Up | 2/17/2022 | APPLICANT |
| Applicant returned to address corrections | 10/21/2022 | ANTOAN MISHRIKI |
| Plan Check Approved | 10/31/2022 | PINANK PATEL |
| Issued | 10/31/2022 | APPLICANT |
| CofO in Progress | 3/17/2026 | ALEXANDER HANDY |
| Permit Finaled | 4/10/2026 | JOHN JANSON |
| CofO Issued | 4/10/2026 | JOHN JANSON |
| Permit Finaled | 4/10/2026 | JOHN JANSON |
Permit Application Clearance Information
| Construction near power lines | Cleared | 7/9/2021 | WALTER RAMIREZ |
| Address approval | Cleared | 3/17/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 3/18/2022 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 10/20/2022 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 10/20/2022 | CHRIS CHAHBAZ |
| Sewer availability | Cleared | 10/24/2022 | CHRIS CHAHBAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/13/2022 | Approved | ROBERT SUNSERI |
| Pre-Inspection | 12/28/2022 | Approved | JEFFREY BULL |
| Pre-Inspection | 2/16/2023 | Corrections Issued | ALEXANDER HANDY |
| PLUMBING-Rough | 5/8/2023 | Partial Approval | ALEXANDER HANDY |
| Footing/Foundation/Slab | 5/19/2023 | Corrections Issued | JEFFREY PARD |
| Footing/Foundation/Slab | 5/25/2023 | Corrections Issued | HORACE FULTZ |
| Wood Frame | 8/21/2023 | Partial Approval | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 9/5/2023 | Approved | ALEXANDER HANDY |
| Underground Mechanical | 9/5/2023 | Approved | ALEXANDER HANDY |
| Deputy Wood Construction | 9/7/2023 | Conditional Approval | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 9/20/2023 | Corrections Issued | JEFFREY PARD |
| ELECTRICAL-Rough | 9/20/2023 | Corrections Issued | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2023 | Not Ready for Inspection | JEFFREY PARD |
| Green Building Rough | 9/20/2023 | Not Ready for Inspection | JEFFREY PARD |
| PLUMBING-Rough | 9/20/2023 | Corrections Issued | JEFFREY PARD |
| Verify Sprinkler Sign Off | 9/20/2023 | Not Ready for Inspection | JEFFREY PARD |
| BUILDING-Rough-Frame | 9/29/2023 | Partial Approval | ALEXANDER HANDY |
| ELECTRICAL-Rough | 9/29/2023 | Partial Approval | ALEXANDER HANDY |
| Green Building Rough | 9/29/2023 | Approved | ALEXANDER HANDY |
| HVAC-Rough | 9/29/2023 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 9/29/2023 | Partial Approval | ALEXANDER HANDY |
| PLUMBING-Rough | 9/29/2023 | Approved | ALEXANDER HANDY |
| Insulation | 10/16/2023 | Approved | ALEXANDER HANDY |
| Shower Pan | 10/16/2023 | Approved | ALEXANDER HANDY |
| Drywall Nailing | 10/27/2023 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 1/8/2024 | Approved | ALEXANDER HANDY |
| Shower Pan | 1/8/2024 | Approved | ALEXANDER HANDY |
| Pre-Inspection | 10/15/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| Gas Test | 12/20/2024 | Not Ready for Inspection | SCOTT SOBEL |
| ELECTRICAL-Final | 12/27/2024 | Approved | ALEXANDER HANDY |
| Gas Test | 12/27/2024 | Approved | ALEXANDER HANDY |
| Service/Power Release | 12/27/2024 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 3/24/2025 | Approved | ALEXANDER HANDY |
| Final | 3/24/2025 | Corrections Issued | ALEXANDER HANDY |
| Footing/Foundation/Slab | 3/24/2025 | Approved | ALEXANDER HANDY |
| Green Building Final | 3/24/2025 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 3/24/2025 | SGSOV Approved | ALEXANDER HANDY |
| Smoke Detectors | 3/24/2025 | Approved | ALEXANDER HANDY |
| Final | 3/16/2026 | OK to Issue CofO | ALEXANDER HANDY |
| HVAC-Final | 3/16/2026 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 3/16/2026 | Approved | ALEXANDER HANDY |