832 N GENESEE AVE 90046
Certificate Information: 832 N GENESEE AVE 90046
- Application / Permit
- 21010-20000-02719
- Plan Check / Job No.
- B21VN06853
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2 STORY S.F.D 5038 SQFT WITH 410 SQFT GARAGE (37'-0" x 80'-4') W/NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 10/15/2021
- Issuing Office
- Current Status
- CofO Issued on 12/17/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/10/2021 | PETER MOSESIAN |
| Corrections Issued | 6/13/2021 | PETER MOSESIAN |
| Quality Review Completed | 6/17/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 6/24/2021 | APPLICANT |
| Plan Check Approved | 10/13/2021 | PETER MOSESIAN |
| Issued | 10/15/2021 | APPLICANT |
| CofO in Progress | 12/13/2022 | MICHAEL LEWIS |
| Permit Finaled | 12/17/2022 | DEROLD HAUFF |
| CofO Issued | 12/17/2022 | DEROLD HAUFF |
| Permit Finaled | 12/17/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/26/2021 | JEANIE LAM |
| Permit | Cleared | 7/26/2021 | JEANIE LAM |
| Sewer availability | Cleared | 7/26/2021 | JEANIE LAM |
| Trees in Parkway | Cleared | 8/26/2021 | JOHN KIM |
| Hydrant and Access approval | Cleared | 9/2/2021 | KURT CORRAL |
| Low Impact Development | Cleared | 10/5/2021 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 10/7/2021 | JEANIE LAM |
Contact Information
| Contractor | A L K Development; Lic. No.: 1056442-B | 6201 BABCOCK AVENUE NORTH HOLLYWOOD, CA 91606 |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: C38991 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 3/2/2022 | Partial Approval | CHRIS CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 3/7/2022 | Partial Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 3/14/2022 | Approved | ARTHUR SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2022 | Partial Approval | ADAM ESCOTO |
| Floor/Roof Diaphrgm/Shear Wall | 4/13/2022 | Approved | ARTHUR SARGSYAN |
| Deputy Wood Construction | 5/5/2022 | Conditional Approval | ADAM ESCOTO |
| Deputy Wood Construction | 5/10/2022 | Conditional Approval | ADAM ESCOTO |
| Deputy Drilled-In Anchors | 5/16/2022 | Conditional Approval | ADAM ESCOTO |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2022 | Approved | ADAM ESCOTO |
| PLUMBING-Rough | 5/19/2022 | Approved | ADAM ESCOTO |
| ELECTRICAL-Rough | 6/3/2022 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 6/3/2022 | Approved | JOSEPH MCGARRY |
| Shower Pan | 6/3/2022 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 6/7/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Rough | 6/7/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 6/7/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 6/10/2022 | Partial Approval | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 6/16/2022 | Approved | JOSEPH MCGARRY |
| Green Building Rough | 6/16/2022 | Approved | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 6/16/2022 | Approved | JOSEPH MCGARRY |
| Insulation | 6/20/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| Drywall Nailing | 6/28/2022 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Final | 11/17/2022 | Approved | MICHAEL LEWIS |
| HVAC-Final | 11/17/2022 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 11/17/2022 | Approved | MICHAEL LEWIS |
| PLUMBING-Final | 11/17/2022 | Approved | MICHAEL LEWIS |
| Service/Power Release | 11/17/2022 | Partial Inspection | MICHAEL LEWIS |
| Final | 12/2/2022 | Corrections Issued | MICHAEL LEWIS |
| Green Building Final | 12/2/2022 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 12/2/2022 | SGSOV Approved | MICHAEL LEWIS |
| Service/Power Release | 12/2/2022 | Approved | MICHAEL LEWIS |
| Smoke Detectors | 12/2/2022 | Approved | MICHAEL LEWIS |
| Final | 12/13/2022 | OK to Issue CofO | MICHAEL LEWIS |