2403 S CLYDE AVE 1-13 90016
Certificate Information: 2403 S CLYDE AVE 1-13 90016
- Application / Permit
- 21010-20000-02715
- Plan Check / Job No.
- B21VN06850
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- NEW 79'7" X 33' THREE STORY 13 UNITS APARTMENTS SPRINKLERED NFPA-13 (TYPE VB CONSTRUCTION ) ( TOC, TIER 3 ( INCREASE TO TIER 4 - 100% AFFORDABLE HOUSING TO INCLUDE 2 EXTREMELLY LOW INCOME UNITS, 2 VERY LOW INCOME UNITS AND 9 LOW INCOME UNITS) PER ADM-2021-3055-TOC, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 9/29/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/13/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/2/2021 | APPLICANT |
| Disabled Access Plans Picked Up | 6/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/1/2021 | RARES BODEA |
| Corrections Issued | 7/5/2021 | RARES BODEA |
| Quality Review Completed | 7/14/2021 | STEVEN KIM |
| Building Plans Picked Up | 7/15/2021 | APPLICANT |
| Green Plans Picked Up | 7/15/2021 | APPLICANT |
| Applicant returned to address corrections | 11/16/2022 | RARES BODEA |
| Applicant returned to address corrections | 6/9/2023 | RARES BODEA |
| Plan Check Approved | 7/17/2023 | RARES BODEA |
| Issued | 9/29/2023 | APPLICANT |
| CofO in Progress | 4/13/2026 | RAFAEL CORTES |
| Permit Finaled | 4/13/2026 | ERNESTO CORRAL |
| CofO Issued | 4/13/2026 | ERNESTO CORRAL |
| Permit Finaled | 4/13/2026 | ERNESTO CORRAL |
Permit Application Clearance Information
| Address approval | Cleared | 8/25/2021 | RENZ SORIANO |
| Highway dedication | Cleared | 8/25/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 8/26/2021 | RENZ SORIANO |
| Permit | Cleared | 9/10/2021 | RENZ SORIANO |
| Hydrant and Access approval | Cleared | 10/18/2021 | KURT CORRAL |
| Fire Marshall Fire Life Safety | Cleared | 1/27/2022 | RONILO MULAWIN |
| Frnt yard landscape/Water mgmt | Cleared | 4/5/2022 | LAUREN PADICK |
| Opn space landscape/Water mgmt | Cleared | 4/5/2022 | LAUREN PADICK |
| Building over 3-story or 36-ft | Cleared | 5/5/2022 | CALOSHA APPROVED |
| Low Impact Development | Cleared | 7/22/2022 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 8/2/2022 | STEVE MELGAR |
| DCP conditions approval | Cleared | 8/15/2022 | JAMES MCCARTHY |
| Density Bonus 12.22.A.31 | Cleared | 8/15/2022 | JAMES MCCARTHY |
| Density Bonus 12.22.A.31 | Cleared | 8/15/2022 | JAMES MCCARTHY |
| Density Bonus 12.22.A.31 | Cleared | 8/15/2022 | JAMES MCCARTHY |
| Sewer availability | Cleared | 8/19/2022 | STEVE MELGAR |
| DAS Clearance | Cleared | 9/6/2022 | RARES BODEA |
| Green Code | Cleared | 9/15/2022 | MICHAEL AYERS |
| Miscellaneous | Cleared | 11/3/2022 | STEVEN WECHSLER |
| Hold | Cleared | 7/23/2024 | MARIA VENDIVIL |
Contact Information
| Contractor | M General Construction The; Lic. No.: 1055278-B | 116 N WILLOW AVENUE COMPTON, CA 90221 |
| Engineer | Parvini,, Mehdi; Lic. No.: C63186 | 1226 SOUZA DRIVE EL DORADO HILLS, CA 95762 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Methane Barrier | 9/23/2024 | Conditional Approval | RAFAEL CORTES |
| Special/Order Compliance | 10/15/2024 | Partial Inspection | RAFAEL ESPINOZA |
| Deputy Wood Construction | 1/24/2025 | Approved | STUART CHAPMAN |
| Insulation | 4/3/2025 | Partial Approval | RAFAEL CORTES |
| Drywall Nailing | 4/16/2025 | Partial Approval | RAFAEL CORTES |
| Green Building Rough | 4/16/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Wood Frame | 5/23/2025 | Partial Approval | RAFAEL ESPINOZA |
| Insulation | 6/25/2025 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Green Building Rough | 7/2/2025 | Partial Inspection | EDWIN GREGORYONA |
| METHANE-Rough | 7/2/2025 | Not Ready for Inspection | EDWIN GREGORYONA |
| Verify Sprinkler Sign Off | 7/2/2025 | Partial Inspection | EDWIN GREGORYONA |
| Wood Frame | 7/2/2025 | Partial Inspection | EDWIN GREGORYONA |
| Green Building Rough | 7/10/2025 | Not Ready for Inspection | EDWIN GREGORYONA |
| METHANE-Rough | 7/10/2025 | Not Ready for Inspection | EDWIN GREGORYONA |
| Verify Sprinkler Sign Off | 7/10/2025 | Not Ready for Inspection | EDWIN GREGORYONA |
| Wood Frame | 7/10/2025 | Partial Inspection | EDWIN GREGORYONA |
| Insulation | 7/28/2025 | Approved | EDWIN GREGORYONA |
| Wood Frame | 7/28/2025 | Partial Approval | EDWIN GREGORYONA |
| Drywall Nailing | 8/4/2025 | Partial Approval | EDWIN GREGORYONA |
| Green Building Rough | 8/4/2025 | Approved | EDWIN GREGORYONA |
| Drywall Nailing | 8/7/2025 | Partial Approval | CHRISTOPHER BLACKWOOD |
| Drywall Nailing | 8/11/2025 | Approved | MARTIN TAVITIAN |
| Special/Order Compliance | 10/7/2025 | Approved | EDWIN GREGORYONA |
| Special/Order Compliance | 1/20/2026 | No Access for Inspection | RAFAEL CORTES |
| Special/Order Compliance | 3/16/2026 | Approved | RAFAEL CORTES |
| Final | 4/9/2026 | Not Ready for Inspection | RAFAEL CORTES |
| Footing/Foundation/Slab | 4/9/2026 | Conditional Approval | RAFAEL CORTES |
| Green Building Final | 4/9/2026 | Approved | RAFAEL CORTES |
| METHANE-Barrier | 4/9/2026 | Conditional Approval | RAFAEL CORTES |
| METHANE-Final | 4/9/2026 | Conditional Approval | RAFAEL CORTES |
| METHANE-Rough | 4/9/2026 | Partial Approval | RAFAEL CORTES |
| METHANE-Subgrade | 4/9/2026 | Conditional Approval | RAFAEL CORTES |
| Reinforced Masonry Frame | 4/9/2026 | Conditional Approval | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 4/9/2026 | SGSOV Approved | RAFAEL CORTES |
| Smoke Detectors | 4/9/2026 | Approved | RAFAEL CORTES |
| Structural Steel Frame | 4/9/2026 | Conditional Approval | RAFAEL CORTES |
| Verify Sprinkler Sign Off | 4/9/2026 | Approved | RAFAEL CORTES |
| Wood Frame | 4/9/2026 | Conditional Approval | RAFAEL CORTES |
| Final | 4/13/2026 | OK to Issue CofO | RAFAEL CORTES |
| Footing/Foundation/Slab | 4/13/2026 | Approved | RAFAEL CORTES |
| METHANE-Barrier | 4/13/2026 | Approved | RAFAEL CORTES |
| METHANE-Final | 4/13/2026 | Approved | RAFAEL CORTES |
| METHANE-Rough | 4/13/2026 | Approved | RAFAEL CORTES |
| METHANE-Subgrade | 4/13/2026 | Approved | RAFAEL CORTES |
| Reinforced Masonry Frame | 4/13/2026 | Approved | RAFAEL CORTES |
| Structural Steel Frame | 4/13/2026 | Approved | RAFAEL CORTES |
| Wood Frame | 4/13/2026 | Approved | RAFAEL CORTES |