15447 W SEPTO ST 91345
Certificate Information: 15447 W SEPTO ST 91345
- Application / Permit
- 21010-20000-02707
- Plan Check / Job No.
- B21VN06806
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 26'-0" x 42'-3" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d).
- Permit Issued
- Issued on 4/11/2022
- Issuing Office
- Current Status
- CofO Issued on 2/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/1/2021 | SARKIS HARABEDIAN |
| Corrections Issued | 7/3/2021 | SARKIS HARABEDIAN |
| Quality Review Completed | 7/9/2021 | STEVEN KIM |
| Plan Check Approved | 4/11/2022 | SARKIS HARABEDIAN |
| Issued | 4/11/2022 | APPLICANT |
| Building Plans Picked Up | 4/13/2022 | APPLICANT |
| CofO in Progress | 2/3/2023 | JOHN COLEMAN |
| Permit Finaled | 2/4/2023 | MICHAEL SMITH |
| CofO Issued | 2/4/2023 | MICHAEL SMITH |
| Permit Finaled | 2/4/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 8/17/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 8/18/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 8/18/2021 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 1/15/2022 | GILBERT URREA |
| Low Impact Development | Cleared | 1/26/2022 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 3/8/2022 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 3/18/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nazarians,, Harmick Edward; Lic. No.: C91232 | 9825 OSO AVE CHATSWORTH, CA 91311 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/25/2022 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 5/5/2022 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 5/5/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| MERV13>=Rough | 5/5/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 5/5/2022 | Partial Approval | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 5/5/2022 | Approved | JENNIFER RABUCHIN |
| Insulation | 5/10/2022 | Partial Approval | DEANDRE HOFFMAN |
| BUILDING-Rough-Frame | 5/12/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2022 | Partial Approval | JENNIFER RABUCHIN |
| Deputy Wood Construction | 6/6/2022 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 6/10/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2022 | Partial Approval | JENNIFER RABUCHIN |
| Gas Test | 6/10/2022 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 6/10/2022 | Partial Approval | JENNIFER RABUCHIN |
| Sewer | 6/10/2022 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 6/10/2022 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 7/15/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 7/15/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Service/Power Release | 7/15/2022 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 8/11/2022 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 8/11/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 8/11/2022 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Rough | 8/11/2022 | Approved | JENNIFER RABUCHIN |
| MERV13>=Rough | 8/11/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 8/11/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Rough-Elec/Plmb/HVAC | 8/11/2022 | Partial Approval | JENNIFER RABUCHIN |
| Service/Power Release | 8/11/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Insulation | 8/25/2022 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 8/25/2022 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 9/7/2022 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 9/7/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 9/7/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Pre-Inspection | 9/7/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 9/19/2022 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 9/19/2022 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 9/19/2022 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 9/26/2022 | Approved | DEANDRE HOFFMAN |
| Final | 1/19/2023 | Corrections Issued | JOHN COLEMAN |
| Green Building Final | 1/19/2023 | Approved | JOHN COLEMAN |
| MERV13>=Final | 1/19/2023 | Approved | JOHN COLEMAN |
| SGSOV-Seismic Gas S/O Valve | 1/19/2023 | SGSOV Approved | JOHN COLEMAN |
| Service/Power Release | 1/19/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Smoke Detectors | 1/19/2023 | Approved | JOHN COLEMAN |
| Final | 1/26/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Service/Power Release | 1/26/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Final | 2/3/2023 | OK to Issue CofO | JOHN COLEMAN |
| Service/Power Release | 2/3/2023 | Approved | JOHN COLEMAN |