23270 W GONZALES DR 91367

Certificate Information: 23270 W GONZALES DR 91367

Application / Permit
21010-20000-02706
Plan Check / Job No.
B21VN06804
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Accessory Living Quarters
Work Description
NEW DETACHED (21'-4" x 16'-4") ACCESSORY LIVING QUARTER WITH NFPA-13D FIRE SPRINKLER THROUGHOUT. WORK PER ENGINEER.
Permit Issued
Issued on 10/15/2021
Issuing Office
Current Status
CofO Issued on 11/4/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/1/2021 APPLICANT
Assigned to Plan Check Engineer 6/3/2021 TROY DEGUZMAN
Corrections Issued 6/6/2021 TROY DEGUZMAN
Building Plans Picked Up 6/8/2021 APPLICANT
Plan Check Approved 10/15/2021 TROY DEGUZMAN
Issued 10/15/2021 APPLICANT
CofO in Progress 11/3/2022 TROY SANDERS
Permit Finaled 11/4/2022 JOHN JANSON
CofO Issued 11/4/2022 JOHN JANSON
Permit Finaled 11/4/2022 JOHN JANSON

Permit Application Clearance Information

GPI Written Notices Cleared 6/4/2021 TROY DEGUZMAN
Grading Pre-Inspection Cleared 6/4/2021 TROY DEGUZMAN
Green Code Cleared 6/4/2021 TROY DEGUZMAN
Eng Process Fee Ord 176,300 Cleared 6/9/2021 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 6/9/2021 CARLOS AGUILERA
Sewer availability Cleared 6/9/2021 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Khansa,, Eyass Wafik; Lic. No.: C91758 2252 JOSIE AVE      LONG BEACH, CA 90815

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/10/2021 Partial Approval DAVID SCANTLIN
Excavation/Setback/Form/Re-Bar 12/20/2021 Approved TROY SANDERS
Footing/Foundation/Slab 12/20/2021 Approved TROY SANDERS
Deputy Wood Construction 3/15/2022 Partial Approval TROY SANDERS
BUILDING-Rough-Frame 3/17/2022 Partial Approval TROY SANDERS
Green Building Rough 3/17/2022 Not Ready for Inspection TROY SANDERS
MERV13>=Rough 3/17/2022 Approved TROY SANDERS
Verify Sprinkler Sign Off 3/17/2022 Not Ready for Inspection TROY SANDERS
ELECTRICAL-Rough 3/25/2022 Approved TROY SANDERS
HVAC-Rough 3/25/2022 Approved TROY SANDERS
PLUMBING-Rough 4/4/2022 Approved JEFFREY PARD
BUILDING-Rough-Frame 4/8/2022 Not Ready for Inspection TROY SANDERS
Green Building Rough 4/8/2022 Not Ready for Inspection TROY SANDERS
Verify Sprinkler Sign Off 4/8/2022 Not Ready for Inspection TROY SANDERS
Interior/Exterior Lathing 4/18/2022 Not Ready for Inspection TROY SANDERS
BUILDING-Rough-Frame 4/21/2022 Approved TROY SANDERS
Green Building Rough 4/21/2022 Approved TROY SANDERS
Insulation 4/21/2022 Approved TROY SANDERS
Verify Sprinkler Sign Off 4/21/2022 Approved TROY SANDERS
Drywall Nailing 4/29/2022 Approved MORRIS JACKSON
Shower Pan 5/9/2022 Approved TROY SANDERS
Interior/Exterior Lathing 5/12/2022 Partial Approval TROY SANDERS
ELECTRICAL-Final 10/7/2022 Approved DAVID SCANTLIN
PLUMBING-Final 10/7/2022 Approved DAVID SCANTLIN
HVAC-Final 10/28/2022 Approved TROY SANDERS
Final 11/3/2022 OK to Issue CofO TROY SANDERS
Green Building Final 11/3/2022 Approved TROY SANDERS
MERV13>=Final 11/3/2022 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 11/3/2022 SGSOV Approved TROY SANDERS
Service/Power Release 11/3/2022 Approved TROY SANDERS
Smoke Detectors 11/3/2022 Approved TROY SANDERS