550 S WOODRUFF AVE 90024
Certificate Information: 550 S WOODRUFF AVE 90024
- Application / Permit
- 21010-20000-02698
- Plan Check / Job No.
- B21VN06757
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW IRR. SHAPED 50'x80' 2-STORY SINGLE FAMILY DWELLING W/ ATT. 2-CAR GARAGE AND BASEMENT; AUTOMATIC SPRINKLER SYSTEM IS REQUIRED
- Permit Issued
- Issued on 8/4/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/29/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/1/2021 | SEAN SHAHMIRI |
| Corrections Issued | 7/3/2021 | SEAN SHAHMIRI |
| Quality Review Completed | 7/9/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 7/12/2021 | APPLICANT |
| Applicant returned to address corrections | 6/16/2022 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 7/20/2022 | SEAN SHAHMIRI |
| Plan Check Approved | 7/20/2022 | SEAN SHAHMIRI |
| No Progress | 7/20/2022 | SEAN SHAHMIRI |
| Plan Check Approved | 7/21/2022 | SEAN SHAHMIRI |
| Issued | 8/4/2022 | APPLICANT |
| CofO in Progress | 8/25/2025 | DANIEL VERA |
| Permit Finaled | 8/29/2025 | RICHARD STEINBACH |
| CofO Issued | 8/29/2025 | RICHARD STEINBACH |
| Permit Finaled | 8/29/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 10/14/2021 | DINAH GARIN |
| Permit | Cleared | 10/14/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 10/18/2021 | DINAH GARIN |
| Sewer availability | Cleared | 10/18/2021 | DINAH GARIN |
| Trees in Parkway | Cleared | 12/8/2021 | ADALBERTO VERA |
| Hydrant and Access approval | Cleared | 12/9/2021 | MATTHEW CRAIG |
| Specific Plan | Cleared | 1/26/2022 | VALERIA CEJA |
| Low Impact Development | Cleared | 4/7/2022 | NICK RAYGOZA |
| Roof/Waste drainage to street | Cleared | 4/26/2022 | STEVE MELGAR |
Contact Information
| Contractor | Hilliard J Stuart Inc; Lic. No.: 182031-B | 7136 HASKELL AVENUE SUITE 109 VAN NUYS, CA 91406 |
| Engineer | Christiansen,, Scott; Lic. No.: C37989 | 1003 WILSHIRE BLVD 202 SANTA MONICA, CA 90401 |
| Engineer | Rowlands,, James; Lic. No.: GE740 | 10954 SANTA MONICA BLVD LOS ANGELES, CA 90025 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/18/2022 | Partial Inspection | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 11/3/2022 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 11/3/2022 | Corrections Issued | STEPHANIE SWANSON |
| Special/Order Compliance | 11/3/2022 | Partial Approval | ASHLEY THOMPSON |
| Special/Order Compliance | 11/3/2022 | Partial Inspection | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 11/4/2022 | Partial Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 11/4/2022 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 11/4/2022 | Partial Approval | STEPHANIE SWANSON |
| Reinforced Masonry Frame | 12/8/2022 | Partial Approval | STEPHANIE SWANSON |
| Reinforced Concrete Frame | 1/25/2023 | Partial Approval | STEPHANIE SWANSON |
| Structural Steel Frame | 1/25/2023 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 2/1/2023 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 2/3/2023 | Partial Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 4/6/2023 | Partial Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 5/8/2023 | Corrections Issued | BRENDAN LOONEY |
| PLUMBING-Rough | 5/8/2023 | Partial Approval | BRENDAN LOONEY |
| Footing/Foundation/Slab | 5/26/2023 | Partial Approval | BRENDAN LOONEY |
| Footing/Foundation/Slab | 6/8/2023 | Approved | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2023 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2023 | Corrections Issued | STEPHANIE SWANSON |
| Deputy Wood Construction | 10/24/2023 | Conditional Approval | MICHAEL PELHAM |
| Deputy Steel/Welding | 10/25/2023 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 10/26/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| Special/Order Compliance | 10/26/2023 | Partial Inspection | MICHAEL PELHAM |
| ELECTRICAL-Rough | 1/26/2024 | Approved | BRENDAN LOONEY |
| Underground Mechanical | 1/26/2024 | Not Ready for Inspection | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 2/1/2024 | Partial Inspection | STEPHANIE SWANSON |
| HVAC-Rough | 2/1/2024 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 2/8/2024 | Partial Approval | STEPHANIE SWANSON |
| Gas Test | 2/12/2024 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 2/12/2024 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 2/15/2024 | Corrections Issued | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 3/15/2024 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Rough | 3/15/2024 | Approved | STEPHANIE SWANSON |
| Verify Sprinkler Sign Off | 3/15/2024 | Approved | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2024 | Approved | STEPHANIE SWANSON |
| HVAC-Rough | 5/7/2024 | Approved | STEPHANIE SWANSON |
| Insulation | 5/7/2024 | Corrections Issued | STEPHANIE SWANSON |
| Insulation | 5/14/2024 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 5/24/2024 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 7/2/2024 | Not Ready for Inspection | SEAN HAUPT |
| Shower Pan | 7/2/2024 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 7/9/2024 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 7/9/2024 | Conditional Approval | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 7/12/2024 | Approved | CHRISTOPHER WILSON |
| Gas Test | 11/15/2024 | Approved | STEPHANIE SWANSON |
| Underground Mechanical | 1/9/2025 | Not Ready for Inspection | BOBBY KEY |
| Underground Mechanical | 1/21/2025 | Partial Approval | BOBBY KEY |
| ELECTRICAL-Final | 2/4/2025 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Final | 2/7/2025 | Approved | STEPHANIE SWANSON |
| Service/Power Release | 2/7/2025 | Approved | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 2/11/2025 | Partial Approval | BOBBY KEY |
| ELECTRICAL-Final | 3/10/2025 | Approved | DANIEL VERA |
| PLUMBING-Final | 3/10/2025 | Not Ready for Inspection | DANIEL VERA |
| HVAC-Final | 4/9/2025 | Approved | STEPHANIE SWANSON |
| PLUMBING-Final | 4/9/2025 | Approved | STEPHANIE SWANSON |
| Final | 5/16/2025 | Corrections Issued | DANIEL VERA |
| SGSOV-Seismic Gas S/O Valve | 5/16/2025 | SGSOV Not Ready | DANIEL VERA |
| BUILDING-Rough-Frame | 7/15/2025 | Approved | DANIEL VERA |
| Final | 7/15/2025 | Not Ready for Inspection | DANIEL VERA |
| Green Building Final | 7/15/2025 | Approved | DANIEL VERA |
| SGSOV-Seismic Gas S/O Valve | 7/15/2025 | SGSOV Not Ready | DANIEL VERA |
| Smoke Detectors | 7/15/2025 | Approved | DANIEL VERA |
| Final | 8/22/2025 | OK to Issue CofO | DANIEL VERA |
| SGSOV-Seismic Gas S/O Valve | 8/22/2025 | SGSOV Approved | DANIEL VERA |