550 S WOODRUFF AVE 90024

Certificate Information: 550 S WOODRUFF AVE 90024

Application / Permit
21010-20000-02698
Plan Check / Job No.
B21VN06757
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW IRR. SHAPED 50'x80' 2-STORY SINGLE FAMILY DWELLING W/ ATT. 2-CAR GARAGE AND BASEMENT; AUTOMATIC SPRINKLER SYSTEM IS REQUIRED
Permit Issued
Issued on 8/4/2022
Issuing Office
Valley
Current Status
CofO Issued on 8/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/1/2021 APPLICANT
Assigned to Plan Check Engineer 7/1/2021 SEAN SHAHMIRI
Corrections Issued 7/3/2021 SEAN SHAHMIRI
Quality Review Completed 7/9/2021 OMID HEDAYAT
Building Plans Picked Up 7/12/2021 APPLICANT
Applicant returned to address corrections 6/16/2022 SEAN SHAHMIRI
Applicant returned to address corrections 7/20/2022 SEAN SHAHMIRI
Plan Check Approved 7/20/2022 SEAN SHAHMIRI
No Progress 7/20/2022 SEAN SHAHMIRI
Plan Check Approved 7/21/2022 SEAN SHAHMIRI
Issued 8/4/2022 APPLICANT
CofO in Progress 8/25/2025 DANIEL VERA
Permit Finaled 8/29/2025 RICHARD STEINBACH
CofO Issued 8/29/2025 RICHARD STEINBACH
Permit Finaled 8/29/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 10/14/2021 DINAH GARIN
Permit Cleared 10/14/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 10/18/2021 DINAH GARIN
Sewer availability Cleared 10/18/2021 DINAH GARIN
Trees in Parkway Cleared 12/8/2021 ADALBERTO VERA
Hydrant and Access approval Cleared 12/9/2021 MATTHEW CRAIG
Specific Plan Cleared 1/26/2022 VALERIA CEJA
Low Impact Development Cleared 4/7/2022 NICK RAYGOZA
Roof/Waste drainage to street Cleared 4/26/2022 STEVE MELGAR

Contact Information

Contractor Hilliard J Stuart Inc; Lic. No.: 182031-B 7136 HASKELL AVENUE SUITE 109      VAN NUYS, CA 91406
Engineer Christiansen,, Scott; Lic. No.: C37989 1003 WILSHIRE BLVD 202      SANTA MONICA, CA 90401
Engineer Rowlands,, James; Lic. No.: GE740 10954 SANTA MONICA BLVD      LOS ANGELES, CA 90025

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/18/2022 Partial Inspection STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 11/3/2022 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 11/3/2022 Corrections Issued STEPHANIE SWANSON
Special/Order Compliance 11/3/2022 Partial Approval ASHLEY THOMPSON
Special/Order Compliance 11/3/2022 Partial Inspection MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 11/4/2022 Partial Approval STEPHANIE SWANSON
Footing/Foundation/Slab 11/4/2022 Partial Approval STEPHANIE SWANSON
PLUMBING-Rough 11/4/2022 Partial Approval STEPHANIE SWANSON
Reinforced Masonry Frame 12/8/2022 Partial Approval STEPHANIE SWANSON
Reinforced Concrete Frame 1/25/2023 Partial Approval STEPHANIE SWANSON
Structural Steel Frame 1/25/2023 Partial Approval STEPHANIE SWANSON
PLUMBING-Rough 2/1/2023 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 2/3/2023 Partial Approval STEPHANIE SWANSON
Footing/Foundation/Slab 4/6/2023 Partial Approval STEPHANIE SWANSON
Footing/Foundation/Slab 5/8/2023 Corrections Issued BRENDAN LOONEY
PLUMBING-Rough 5/8/2023 Partial Approval BRENDAN LOONEY
Footing/Foundation/Slab 5/26/2023 Partial Approval BRENDAN LOONEY
Footing/Foundation/Slab 6/8/2023 Approved STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 10/16/2023 Corrections Issued STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 10/20/2023 Corrections Issued STEPHANIE SWANSON
Deputy Wood Construction 10/24/2023 Conditional Approval MICHAEL PELHAM
Deputy Steel/Welding 10/25/2023 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 10/26/2023 Not Ready for Inspection STEPHANIE SWANSON
Special/Order Compliance 10/26/2023 Partial Inspection MICHAEL PELHAM
ELECTRICAL-Rough 1/26/2024 Approved BRENDAN LOONEY
Underground Mechanical 1/26/2024 Not Ready for Inspection BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 2/1/2024 Partial Inspection STEPHANIE SWANSON
HVAC-Rough 2/1/2024 Corrections Issued STEPHANIE SWANSON
HVAC-Rough 2/8/2024 Partial Approval STEPHANIE SWANSON
Gas Test 2/12/2024 Partial Approval STEPHANIE SWANSON
PLUMBING-Rough 2/12/2024 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 2/15/2024 Corrections Issued STEPHANIE SWANSON
BUILDING-Rough-Frame 3/15/2024 Corrections Issued STEPHANIE SWANSON
Green Building Rough 3/15/2024 Approved STEPHANIE SWANSON
Verify Sprinkler Sign Off 3/15/2024 Approved STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 4/29/2024 Approved STEPHANIE SWANSON
HVAC-Rough 5/7/2024 Approved STEPHANIE SWANSON
Insulation 5/7/2024 Corrections Issued STEPHANIE SWANSON
Insulation 5/14/2024 Approved STEPHANIE SWANSON
Drywall Nailing 5/24/2024 Approved SEAN HAUPT
Interior/Exterior Lathing 7/2/2024 Not Ready for Inspection SEAN HAUPT
Shower Pan 7/2/2024 Approved SEAN HAUPT
Interior/Exterior Lathing 7/9/2024 Partial Approval STEPHANIE SWANSON
PLUMBING-Rough 7/9/2024 Conditional Approval STEPHANIE SWANSON
Interior/Exterior Lathing 7/12/2024 Approved CHRISTOPHER WILSON
Gas Test 11/15/2024 Approved STEPHANIE SWANSON
Underground Mechanical 1/9/2025 Not Ready for Inspection BOBBY KEY
Underground Mechanical 1/21/2025 Partial Approval BOBBY KEY
ELECTRICAL-Final 2/4/2025 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Final 2/7/2025 Approved STEPHANIE SWANSON
Service/Power Release 2/7/2025 Approved STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 2/11/2025 Partial Approval BOBBY KEY
ELECTRICAL-Final 3/10/2025 Approved DANIEL VERA
PLUMBING-Final 3/10/2025 Not Ready for Inspection DANIEL VERA
HVAC-Final 4/9/2025 Approved STEPHANIE SWANSON
PLUMBING-Final 4/9/2025 Approved STEPHANIE SWANSON
Final 5/16/2025 Corrections Issued DANIEL VERA
SGSOV-Seismic Gas S/O Valve 5/16/2025 SGSOV Not Ready DANIEL VERA
BUILDING-Rough-Frame 7/15/2025 Approved DANIEL VERA
Final 7/15/2025 Not Ready for Inspection DANIEL VERA
Green Building Final 7/15/2025 Approved DANIEL VERA
SGSOV-Seismic Gas S/O Valve 7/15/2025 SGSOV Not Ready DANIEL VERA
Smoke Detectors 7/15/2025 Approved DANIEL VERA
Final 8/22/2025 OK to Issue CofO DANIEL VERA
SGSOV-Seismic Gas S/O Valve 8/22/2025 SGSOV Approved DANIEL VERA