218 W 84TH PL 90003

Certificate Information: 218 W 84TH PL 90003

Application / Permit
21010-20000-02694
Plan Check / Job No.
B21VN06744
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
2-STORY GROUND FLOOR ADDITION TO (E) DETACHED GARAGE TO CREATE A DETACHED ADU PER ORDINANCE (2-STORY)
Permit Issued
Issued on 10/5/2022
Issuing Office
Current Status
CofO Issued on 12/7/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/1/2021 APPLICANT
Assigned to Plan Check Engineer 7/8/2021 CARLOS MONTES
Corrections Issued 7/11/2021 CARLOS MONTES
Quality Review Completed 7/18/2021 PRANITA SHAH
Applicant returned to address corrections 1/6/2022 CARLOS MONTES
Applicant returned to address corrections 8/24/2022 CARLOS MONTES
Plan Check Approved 9/29/2022 CARLOS MONTES
Issued 10/5/2022 APPLICANT
CofO in Progress 12/5/2024 MICHAEL LEWIS
Permit Finaled 12/7/2024 DEROLD HAUFF
CofO Issued 12/7/2024 DEROLD HAUFF
Permit Finaled 12/7/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/19/2021 RENZ SORIANO
Highway dedication Cleared 8/19/2021 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 8/25/2021 RENZ SORIANO
Sewer availability Cleared 8/25/2021 RENZ SORIANO
Low Impact Development Cleared 12/22/2021 MARCO SANCHEZ
Frnt yard landscape/Water mgmt Cleared 1/5/2022 MAXFIELD VERMY
Roof/Waste drainage to street Cleared 1/6/2022 THAN WIN
Tenant Habitability Plan Cleared 2/3/2022 MICHAEL SOTO

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Eddy Alexander; Lic. No.: S6159 17958 LULL ST      RESEDA, CA 91335

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/18/2023 Corrections Issued LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 9/14/2023 Partial Approval MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 5/31/2024 Partial Approval MICHAEL LEWIS
Underground Mechanical 6/21/2024 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 12/4/2024 Approved MICHAEL LEWIS
Drywall Nailing 12/4/2024 Approved MICHAEL LEWIS
Final 12/4/2024 OK to Issue CofO MICHAEL LEWIS
Footing/Foundation/Slab 12/4/2024 Approved MICHAEL LEWIS
Green Building Final 12/4/2024 Approved MICHAEL LEWIS
Green Building Rough 12/4/2024 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 12/4/2024 SGSOV Approved MICHAEL LEWIS
Smoke Detectors 12/4/2024 Approved MICHAEL LEWIS