18716 W HAYNES ST 91335
Certificate Information: 18716 W HAYNES ST 91335
- Application / Permit
- 21010-20000-02692
- Plan Check / Job No.
- B21VN06743
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- First and second story additions to an (E) detached garage and conversion of second story into an ADU per ordinance 186,481.
- Permit Issued
- Issued on 3/16/2022
- Issuing Office
- Current Status
- CofO Issued on 5/17/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/7/2021 | HELEN NGUYEN |
| Corrections Issued | 6/7/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 7/5/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 11/19/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 11/30/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 12/31/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 2/4/2022 | HELEN NGUYEN |
| Applicant returned to address corrections | 2/15/2022 | HELEN NGUYEN |
| Applicant returned to address corrections | 2/23/2022 | HELEN NGUYEN |
| Applicant returned to address corrections | 2/24/2022 | HELEN NGUYEN |
| Applicant returned to address corrections | 2/28/2022 | HELEN NGUYEN |
| Applicant returned to address corrections | 3/1/2022 | HELEN NGUYEN |
| Plan Check Approved | 3/2/2022 | HELEN NGUYEN |
| Issued | 3/16/2022 | APPLICANT |
| CofO in Progress | 4/27/2023 | JON MCHUGH |
| CofO Issued | 5/17/2023 | JOHN JANSON |
| Permit Finaled | 5/17/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 6/23/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 6/29/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 6/29/2021 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 1/13/2022 | ABDULLAH SADOZAI |
Contact Information
| Architect | Uskert,, Derek Carl; Lic. No.: C32400 | 2660 35TH AVE SAN FRANCISCO, CA 94116 |
| Contractor | Owner-Builder | , |
| Engineer | Acciani,, Mark; Lic. No.: C83929 | PO BOX 1390 RUNNING SPRINGS, CA 92382 |
| Engineer | Shamim,, Mahmoud; Lic. No.: M21579 | 3920 LAKE VISTA CT ENCINO, CA 91316 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/21/2022 | Not Ready for Inspection | JEFFREY BULL |
| Footing/Foundation/Slab | 7/28/2022 | Partial Approval | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 8/12/2022 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 8/12/2022 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 9/16/2022 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2022 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 11/2/2022 | Not Ready for Inspection | SEAN HAUPT |
| ELECTRICAL-Rough | 11/2/2022 | Approved | SEAN HAUPT |
| HVAC-Rough | 11/2/2022 | Not Ready for Inspection | SEAN HAUPT |
| PLUMBING-Rough | 11/2/2022 | Not Ready for Inspection | SEAN HAUPT |
| HVAC-Rough | 11/7/2022 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 11/7/2022 | Not Ready for Inspection | SEAN HAUPT |
| BUILDING-Rough-Frame | 11/28/2022 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 11/28/2022 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 11/28/2022 | Approved | JON MCHUGH |
| Insulation | 12/16/2022 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 12/16/2022 | Approved | SEAN HAUPT |
| Drywall Nailing | 12/29/2022 | Partial Approval | JON MCHUGH |
| Sewer | 12/29/2022 | Approved | JON MCHUGH |
| Gas Test | 1/5/2023 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 1/5/2023 | Approved | JON MCHUGH |
| Drywall Nailing | 3/1/2023 | Approved | SEAN HAUPT |
| Final | 3/1/2023 | Corrections Issued | SEAN HAUPT |
| Green Building Final | 3/1/2023 | Not Ready for Inspection | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 3/1/2023 | SGSOV Not Ready | SEAN HAUPT |
| Smoke Detectors | 3/1/2023 | Approved | SEAN HAUPT |
| Final | 3/28/2023 | Corrections Issued | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 3/28/2023 | SGSOV Not Ready | JON MCHUGH |
| Final | 4/27/2023 | OK to Issue CofO | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 4/27/2023 | SGSOV Approved | JON MCHUGH |