22307 W GIFFORD ST 91303

Certificate Information: 22307 W GIFFORD ST 91303

Application / Permit
21010-20000-02688
Plan Check / Job No.
B21VN06742
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Proposed a new 1-story detached accessory dwelling unit.
Permit Issued
Issued on 4/10/2022
Issuing Office
Current Status
CofO Issued on 3/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/30/2021 APPLICANT
Assigned to Plan Check Engineer 6/1/2021 JOE VO
Corrections Issued 6/1/2021 JOE VO
Applicant returned to address corrections 1/19/2022 JOE VO
Plan Check Approved 1/27/2022 JOE VO
Issued 4/10/2022 APPLICANT
CofO in Progress 2/6/2023 KRISTEN BEVERIDGE
CofO in Progress 2/6/2023 KRISTEN BEVERIDGE
Permit Finaled 3/15/2023 JOHN JANSON
CofO Issued 3/15/2023 JOHN JANSON
Permit Finaled 3/15/2023 JOHN JANSON

Permit Application Clearance Information

Construction near power lines Cleared 12/2/2021 RIDWAN HARDY
Address approval Cleared 1/19/2022 JOHN LIN
Roof/Waste drainage to street Cleared 1/26/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 1/27/2022 CARLOS AGUILERA
Sewer availability Cleared 1/27/2022 CARLOS AGUILERA

Contact Information

Contractor Sunrise Home Improvement; Lic. No.: 1031197-B 11222 SCHMIDT ROAD      EL MONTE, CA 91733
Engineer Wu,, Harold Ping-Hung; Lic. No.: NA35693       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/22/2022 Partial Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 5/9/2022 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 6/2/2022 Approved CHRIS CHRISTENSEN
Sewer 6/24/2022 Approved JESUS PINEDA
PLUMBING-Rough 7/7/2022 Corrections Issued DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 7/11/2022 Partial Approval CHRIS CHRISTENSEN
PLUMBING-Rough 7/11/2022 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 7/14/2022 Approved CHRIS CHRISTENSEN
Green Building Rough 7/14/2022 Approved CHRIS CHRISTENSEN
Rough-Elec/Plmb/HVAC 7/14/2022 Approved CHRIS CHRISTENSEN
Verify Sprinkler Sign Off 7/14/2022 Approved CHRIS CHRISTENSEN
Insulation 7/29/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Interior/Exterior Lathing 7/29/2022 Corrections Issued CHRIS CHRISTENSEN
Insulation 8/1/2022 Not Ready for Inspection JESUS PINEDA
Interior/Exterior Lathing 8/1/2022 Partial Approval JESUS PINEDA
Insulation 8/15/2022 Corrections Issued CHRIS CHRISTENSEN
Drywall Nailing 8/25/2022 Corrections Issued JESUS PINEDA
Interior/Exterior Lathing 8/25/2022 Approved JESUS PINEDA
Drywall Nailing 9/1/2022 Approved MORRIS JACKSON
Insulation 9/1/2022 Approved MORRIS JACKSON
ELECTRICAL-Final 12/23/2022 Not Ready for Inspection KRISTEN CAUSEY
Service/Power Release 12/23/2022 Not Ready for Inspection KRISTEN CAUSEY
Final 1/31/2023 Corrections Issued KRISTEN CAUSEY
Green Building Final 1/31/2023 Approved KRISTEN CAUSEY
SGSOV-Seismic Gas S/O Valve 1/31/2023 SGSOV Not Ready KRISTEN CAUSEY
Service/Power Release 1/31/2023 Not Ready for Inspection KRISTEN CAUSEY
Smoke Detectors 1/31/2023 Approved KRISTEN CAUSEY
ELECTRICAL-Final 2/3/2023 Approved KRISTEN CAUSEY
Final 2/3/2023 OK to Issue CofO KRISTEN CAUSEY
HVAC-Final 2/3/2023 Approved KRISTEN CAUSEY
PLUMBING-Final 2/3/2023 Approved KRISTEN CAUSEY
SGSOV-Seismic Gas S/O Valve 2/3/2023 SGSOV Approved KRISTEN CAUSEY
Service/Power Release 2/3/2023 Approved KRISTEN CAUSEY