11716 W CALIFA ST 91607

Certificate Information: 11716 W CALIFA ST 91607

Application / Permit
21010-20000-02674
Plan Check / Job No.
B21VN06710
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 21'-0" X 56'-4" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 6/23/2022
Issuing Office
Valley
Current Status
CofO Issued on 9/29/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/3/2021 APPLICANT
Assigned to Plan Check Engineer 6/4/2021 ARTIN ZARUKIAN
Corrections Issued 6/5/2021 ARTIN ZARUKIAN
Applicant returned to address corrections 12/1/2021 ARTIN ZARUKIAN
Plan Check Approved 12/7/2021 ARTIN ZARUKIAN
Building Plans Picked Up 6/7/2022 APPLICANT
Issued 6/23/2022 APPLICANT
CofO in Progress 8/3/2023 JOHN HAYES
Permit Finaled 9/29/2023 RUBEN SALAS
CofO Issued 9/29/2023 RUBEN SALAS
Permit Finaled 9/29/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/23/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/24/2021 CARLOS AGUILERA
Sewer availability Cleared 6/24/2021 CARLOS AGUILERA
Hydrant and Access approval Cleared 8/31/2021 JOHN CONNEALLY
Low Impact Development Cleared 11/8/2021 LONDY ALVARADO
Roof/Waste drainage to street Cleared 11/17/2021 CARLOS AGUILERA

Contact Information

Contractor Lopez Francisco Construction; Lic. No.: 761746-B 17437 E TADMORE ST      LA PUENTE, CA 91744
Engineer Perazzelli,, Joseph Ames; Lic. No.: C35270 183 GREENFIELD AVENUE      LOS ANGELES, CA 90049

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/30/2022 Partial Approval JACK KARGODORIAN
Footing/Foundation/Slab 7/13/2022 Partial Approval JOHN HAYES
PLUMBING-Rough 7/19/2022 Partial Approval JOHN HAYES
Footing/Foundation/Slab 7/28/2022 Approved GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 10/14/2022 Corrections Issued CALEB MEISTER
Green Building Rough 10/14/2022 Not Ready for Inspection CALEB MEISTER
Verify Sprinkler Sign Off 10/14/2022 Not Ready for Inspection CALEB MEISTER
Pre-Inspection 10/28/2022 Partial Approval JOHN HAYES
Underground Mechanical 10/28/2022 Partial Approval JOHN HAYES
BUILDING-Rough-Frame 12/12/2022 Not Ready for Inspection RYAN SALAZAR
ELECTRICAL-Rough 12/12/2022 Approved RYAN SALAZAR
Green Building Rough 12/12/2022 Not Ready for Inspection RYAN SALAZAR
HVAC-Rough 12/12/2022 Partial Approval RYAN SALAZAR
PLUMBING-Rough 12/12/2022 Approved RYAN SALAZAR
Verify Sprinkler Sign Off 12/12/2022 Not Ready for Inspection RYAN SALAZAR
BUILDING-Rough-Frame 12/19/2022 Approved JOHN COLEMAN
Green Building Rough 12/19/2022 Approved JOHN COLEMAN
Verify Sprinkler Sign Off 12/19/2022 Approved JOHN COLEMAN
Drywall Nailing 12/23/2022 Approved JOHN HAYES
Interior/Exterior Lathing 12/23/2022 Partial Approval JOHN HAYES
Insulation 1/13/2023 Corrections Issued JOHN HAYES
Insulation 1/27/2023 Approved WILLIAM WREN
Drywall Nailing 2/6/2023 Approved DAVID ANDERSON
Interior/Exterior Lathing 2/6/2023 Approved DAVID ANDERSON
Final 5/5/2023 Corrections Issued JOHN HAYES
Green Building Final 5/5/2023 Approved JOHN HAYES
SGSOV-Seismic Gas S/O Valve 5/5/2023 SGSOV Not Required JOHN HAYES
Service/Power Release 5/5/2023 Not Ready for Inspection JOHN HAYES
Smoke Detectors 5/5/2023 Approved JOHN HAYES
Final 8/2/2023 OK to Issue CofO JOHN HAYES
Service/Power Release 8/2/2023 Approved JOHN HAYES