22348 W PHILIPRIMM ST 91367

Certificate Information: 22348 W PHILIPRIMM ST 91367

Application / Permit
21010-20000-02649
Plan Check / Job No.
B21VN06675
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW TWO STORY IRREGULAR SHAPED 31'-0" X 26' ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) ALL WORK PER ENGINEERING
Permit Issued
Issued on 2/28/2022
Issuing Office
Current Status
CofO Issued on 10/12/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/26/2021 APPLICANT
Assigned to Plan Check Engineer 7/1/2021 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 7/7/2021 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 7/16/2021 OMID HEDAYAT
Building Plans Picked Up 8/10/2021 APPLICANT
Plan Check Approved 2/28/2022 SEWADA ZADOORAN MILAGARDI
Issued 2/28/2022 APPLICANT
CofO in Progress 9/22/2022 TROY SANDERS
Permit Finaled 10/12/2022 JOHN JANSON
CofO Issued 10/12/2022 JOHN JANSON
Permit Finaled 10/12/2022 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 8/19/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 8/23/2021 GABRIEL ROBLES
Sewer availability Cleared 8/23/2021 GABRIEL ROBLES
Construction near power lines Cleared 11/18/2021 RIDWAN HARDY
Low Impact Development Cleared 12/16/2021 ANTHONY VARGAS
Hydrant and Access approval Cleared 1/27/2022 KURT CORRAL
GPI Written Notices Cleared 2/18/2022 SEWADA ZADOORAN MILAGARDI
Grading Pre-Inspection Cleared 2/18/2022 SEWADA ZADOORAN MILAGARDI
Roof/Waste drainage to street Cleared 2/23/2022 AMIR KASHFI

Contact Information

Contractor Owner-Builder       ,
Engineer Papazyan,, Andranik; Lic. No.: C56824 635 W COLORADO ST STE 104      GLENDALE, CA 91204

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/8/2022 Approved TROY SANDERS
Green Building Rough 3/24/2022 Not Ready for Inspection TROY SANDERS
PLUMBING-Rough 3/24/2022 Partial Approval TROY SANDERS
Verify Sprinkler Sign Off 3/24/2022 Not Ready for Inspection TROY SANDERS
Footing/Foundation/Slab 4/6/2022 Approved TROY SANDERS
Wood Frame 5/6/2022 Partial Approval DAVID SCANTLIN
Deputy Wood Construction 6/9/2022 Partial Approval TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 6/10/2022 Partial Approval TROY SANDERS
Green Building Rough 6/10/2022 Not Ready for Inspection TROY SANDERS
Verify Sprinkler Sign Off 6/10/2022 Not Ready for Inspection TROY SANDERS
Underground Mechanical 7/5/2022 Partial Approval TROY SANDERS
PLUMBING-Rough 7/11/2022 Approved TROY SANDERS
ELECTRICAL-Rough 7/15/2022 Approved ROBERT GOLD
Interior/Exterior Lathing 7/20/2022 Partial Approval JESUS PINEDA
BUILDING-Rough-Frame 7/22/2022 Approved TROY SANDERS
Green Building Rough 7/22/2022 Approved TROY SANDERS
HVAC-Rough 7/22/2022 Approved TROY SANDERS
Verify Sprinkler Sign Off 7/22/2022 Approved TROY SANDERS
Drywall Nailing 7/27/2022 No Access for Inspection JESUS PINEDA
Drywall Nailing 8/1/2022 Approved JESUS PINEDA
Insulation 8/1/2022 Approved JESUS PINEDA
Interior/Exterior Lathing 8/8/2022 Not Ready for Inspection JESUS PINEDA
Insulation 8/12/2022 Partial Inspection JESUS PINEDA
Interior/Exterior Lathing 8/12/2022 Approved JESUS PINEDA
PLUMBING-Rough 8/22/2022 Partial Approval TROY SANDERS
Sewer 8/22/2022 Approved TROY SANDERS
ELECTRICAL-Final 9/21/2022 Approved TROY SANDERS
Final 9/21/2022 OK to Issue CofO TROY SANDERS
Green Building Final 9/21/2022 Approved TROY SANDERS
HVAC-Final 9/21/2022 Approved TROY SANDERS
PLUMBING-Final 9/21/2022 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 9/21/2022 SGSOV Approved TROY SANDERS
Service/Power Release 9/21/2022 Approved TROY SANDERS
Smoke Detectors 9/21/2022 Approved TROY SANDERS