13118 W WILLARD ST 91605
Certificate Information: 13118 W WILLARD ST 91605
- Application / Permit
- 21010-20000-02648
- Plan Check / Job No.
- B21VN06674
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 25' X 24' TWO-STORY DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). WORK PER ENGINEER.
- Permit Issued
- Issued on 11/21/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/1/2021 | ROSENDO MEDINA |
| Corrections Issued | 7/3/2021 | ROSENDO MEDINA |
| Quality Review Completed | 7/14/2021 | STEVEN KIM |
| Applicant returned to address corrections | 9/10/2021 | ROSENDO MEDINA |
| Plan Check Approved | 10/13/2021 | ROSENDO MEDINA |
| Building Plans Picked Up | 10/26/2021 | APPLICANT |
| No Progress | 8/16/2022 | ROSENDO MEDINA |
| Plan Check Approved | 11/1/2022 | ROSENDO MEDINA |
| Issued | 11/21/2022 | APPLICANT |
| CofO in Progress | 10/2/2023 | GREGG CUMMINGS |
| No Progress | 10/2/2023 | GREGG CUMMINGS |
| CofO in Progress | 10/2/2023 | DAVID MATSON |
| CofO in Progress | 3/12/2024 | GREGG CUMMINGS |
| Permit Finaled | 4/10/2024 | RUBEN SALAS |
| CofO Issued | 4/10/2024 | RUBEN SALAS |
| Permit Finaled | 4/10/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/11/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 8/13/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 8/13/2021 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 10/1/2021 | LONDY ALVARADO |
| Hydrant and Access approval | Cleared | 10/2/2021 | MATTHEW CRAIG |
| Roof/Waste drainage to street | Cleared | 10/4/2021 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 9/1/2022 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 9/7/2022 | ANDRES COVARRUBIAS |
| Construction near power lines | Cleared | 10/22/2022 | RIDWAN HARDY |
| Construction near power lines | Cleared | 10/22/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Truong,, Phong; Lic. No.: C70784 | 20439 E CRESTLINE DRIVE WALNUT, CA 91789 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/28/2022 | Partial Approval | GREGG CUMMINGS |
| Footing/Foundation/Slab | 1/18/2023 | Corrections Issued | GREGG CUMMINGS |
| Special/Order Compliance | 1/23/2023 | Conditional Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2023 | Partial Approval | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 2/16/2023 | Corrections Issued | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2023 | Partial Approval | GREGG CUMMINGS |
| HVAC-Rough | 4/10/2023 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 4/10/2023 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Rough | 4/28/2023 | Corrections Issued | GREGG CUMMINGS |
| HVAC-Rough | 4/28/2023 | Corrections Issued | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 5/10/2023 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 5/10/2023 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 5/10/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Deputy Wood Construction | 5/12/2023 | Conditional Approval | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/18/2023 | Partial Approval | GREGG CUMMINGS |
| HVAC-Rough | 5/18/2023 | Partial Approval | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 5/25/2023 | Approved | GREGG CUMMINGS |
| Green Building Rough | 5/25/2023 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 5/25/2023 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 5/25/2023 | Partial Approval | GREGG CUMMINGS |
| Verify Sprinkler Sign Off | 5/25/2023 | Approved | GREGG CUMMINGS |
| Insulation | 6/5/2023 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 6/5/2023 | Approved | GREGG CUMMINGS |
| Shower Pan | 6/5/2023 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 6/7/2023 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 6/7/2023 | Partial Approval | GREGG CUMMINGS |
| ELECTRICAL-Final | 8/7/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Gas Test | 8/7/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Final | 8/7/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Final | 8/7/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Service/Power Release | 8/7/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Final | 9/1/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 9/1/2023 | Corrections Issued | GREGG CUMMINGS |
| HVAC-Final | 9/1/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Final | 9/1/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 9/27/2023 | Corrections Issued | GREGG CUMMINGS |
| Footing/Foundation/Slab | 9/27/2023 | Approved | GREGG CUMMINGS |
| Green Building Final | 9/27/2023 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 9/27/2023 | SGSOV Approved | GREGG CUMMINGS |
| Service/Power Release | 9/27/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 9/27/2023 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 9/29/2023 | Approved | GREGG CUMMINGS |
| Final | 9/29/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Final | 9/29/2023 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 9/29/2023 | Approved | GREGG CUMMINGS |
| Service/Power Release | 9/29/2023 | Approved | GREGG CUMMINGS |
| Final | 10/2/2023 | Corrections Issued | GREGG CUMMINGS |
| Final | 3/11/2024 | OK to Issue CofO | GREGG CUMMINGS |