18813 W EDLEEN DR 91356
Certificate Information: 18813 W EDLEEN DR 91356
- Application / Permit
- 21010-20000-02647
- Plan Check / Job No.
- B21VN06673
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 60'9" X 47'9" 2-STORY SFD WITH ATTACHED TWO CAR GARAGE AND HABITABLE BASEMENT, NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 12/8/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/7/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/10/2021 | RARES BODEA |
| Corrections Issued | 6/12/2021 | RARES BODEA |
| Quality Review Completed | 6/28/2021 | STEVEN KIM |
| Building Plans Picked Up | 6/29/2021 | APPLICANT |
| Applicant returned to address corrections | 11/14/2022 | RARES BODEA |
| Plan Check Approved | 12/8/2022 | RARES BODEA |
| Issued | 12/8/2022 | APPLICANT |
| CofO in Progress | 12/8/2025 | JOHN KIDWELL |
| Permit Finaled | 1/7/2026 | MICHAEL PELHAM |
| CofO Issued | 1/7/2026 | MICHAEL PELHAM |
| Permit Finaled | 1/7/2026 | MICHAEL PELHAM |
Permit Application Clearance Information
| Address approval | Cleared | 7/13/2021 | DAGOVERTO GUERRERO |
| BHO/Hillside ordinance | Cleared | 7/13/2021 | DAGOVERTO GUERRERO |
| BHO/Hillside ordinance | Cleared | 7/13/2021 | DAGOVERTO GUERRERO |
| BHO/Hillside ordinance | Cleared | 7/13/2021 | DAGOVERTO GUERRERO |
| BHO/Hillside ordinance | Cleared | 7/13/2021 | DAGOVERTO GUERRERO |
| BHO/Hillside ordinance | Cleared | 7/13/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 7/14/2021 | DAGOVERTO GUERRERO |
| Permit | Cleared | 7/14/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 7/14/2021 | DAGOVERTO GUERRERO |
| ZA Case | Cleared | 3/3/2022 | MIGUEL GAMBOA |
| Low Impact Development | Cleared | 3/11/2022 | SUNG JOON WON |
| Trees in Parkway | Cleared | 3/17/2022 | RARES BODEA |
| Distance to fire station | Cleared | 3/31/2022 | LAURINDA MEADE |
| Hydrant and Access approval | Cleared | 3/31/2022 | LAURINDA MEADE |
| Roof/Waste drainage to street | Cleared | 6/2/2022 | DAGOVERTO GUERRERO |
| GPI Written Notices | Cleared | 11/14/2022 | RARES BODEA |
| Grading Pre-Inspection | Cleared | 11/14/2022 | RARES BODEA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
| Engineer | Lin,, Chi Hsin; Lic. No.: GE2921 | 1722 CEDAR STREET APT G ALHAMBRA, CA 91801 |
| Geologist | Kruger,, Mark Otto; Lic. No.: EG2345 | 10120 NATIONAL BLVD LOS ANGELES, CA 90034 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Grading | 12/19/2022 | Conditional Approval | DAVID SANDOVAL |
| Deputy Steel/Welding | 2/15/2023 | Approved | DAVID SANDOVAL |
| Deputy Steel/Welding | 2/21/2023 | Conditional Approval | DAVID SANDOVAL |
| Piling/Pier/Caisson | 5/25/2023 | Approved | SEAN HAUPT |
| Deputy Reinf. Concrete | 5/26/2023 | Approved | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 6/6/2023 | Not Ready for Inspection | VINCENT HANLEY |
| Footing/Foundation/Slab | 6/7/2023 | Partial Approval | SEAN HAUPT |
| Deputy Reinf. Concrete | 6/26/2023 | Approved | SEAN HAUPT |
| Deputy Steel/Welding | 6/28/2023 | Partial Approval | SEAN HAUPT |
| Footing/Foundation/Slab | 7/11/2023 | Partial Approval | SEAN HAUPT |
| Deputy Reinf. Concrete | 7/17/2023 | Approved | SEAN HAUPT |
| Reinforced Concrete Frame | 7/20/2023 | Partial Approval | JOHN KIDWELL |
| Reinforced Concrete Frame | 7/25/2023 | Not Ready for Inspection | SEAN HAUPT |
| Reinforced Concrete Frame | 7/27/2023 | Partial Approval | SEAN HAUPT |
| Deputy Drilled-In Anchors | 8/30/2023 | Conditional Approval | MORRIS JACKSON |
| Deputy Steel/Welding | 8/30/2023 | Approved | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 8/30/2023 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 8/30/2023 | Approved | SEAN HAUPT |
| Special/Order Compliance | 8/30/2023 | Corrections Issued | SEAN HAUPT |
| Deputy Reinf. Concrete | 8/31/2023 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 9/6/2023 | Approved | MORRIS JACKSON |
| Deputy Wood Construction | 9/7/2023 | Conditional Approval | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/12/2023 | Approved | SEAN HAUPT |
| Deputy Steel/Welding | 9/22/2023 | Partial Approval | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 11/16/2023 | Corrections Issued | SEAN HAUPT |
| ELECTRICAL-Rough | 11/30/2023 | Approved | SEAN HAUPT |
| HVAC-Rough | 11/30/2023 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 12/8/2023 | Approved | SEAN HAUPT |
| Shower Pan | 12/8/2023 | Approved | SEAN HAUPT |
| Special/Order Compliance | 12/8/2023 | Corrections Issued | SEAN HAUPT |
| Sewer | 1/12/2024 | Not Ready for Inspection | JEFFREY PARD |
| Sewer | 1/17/2024 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 1/25/2024 | Corrections Issued | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 1/25/2024 | Approved | SEAN HAUPT |
| Green Building Rough | 1/25/2024 | Not Ready for Inspection | SEAN HAUPT |
| Verify Sprinkler Sign Off | 1/25/2024 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 2/7/2024 | Approved | SEAN HAUPT |
| Green Building Rough | 2/7/2024 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 2/7/2024 | Approved | SEAN HAUPT |
| Insulation | 2/14/2024 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 2/20/2024 | Partial Approval | ALEXANDER HANDY |
| Drywall Nailing | 2/23/2024 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 2/23/2024 | Partial Approval | JOHN KIDWELL |
| Underground Mechanical | 9/26/2024 | Partial Approval | JOHN KIDWELL |
| ELECTRICAL-Final | 11/13/2024 | Approved | JOHN KIDWELL |
| HVAC-Final | 11/13/2024 | Approved | JOHN KIDWELL |
| PLUMBING-Final | 11/13/2024 | Approved | JOHN KIDWELL |
| Service/Power Release | 4/29/2025 | Not Ready for Inspection | JOHN KIDWELL |
| Service/Power Release | 5/2/2025 | Approved | JOHN KIDWELL |
| Final | 12/4/2025 | OK to Issue CofO | JOHN KIDWELL |
| Green Building Final | 12/4/2025 | Approved | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 12/4/2025 | SGSOV Approved | JOHN KIDWELL |
| Smoke Detectors | 12/4/2025 | Approved | JOHN KIDWELL |