11034 N SWEETWATER CT 91311
Certificate Information: 11034 N SWEETWATER CT 91311
- Application / Permit
- 21010-20000-02629
- Plan Check / Job No.
- B21VN06625
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- NEW IRR. SHAPED 51'-6" x 62'-10" REC ROOM W/ 2 ATT. OPEN TRELLIS, AND OPEN DECK; ALL WORK PER ENGINEERING DESIGN
- Permit Issued
- Issued on 1/5/2022
- Issuing Office
- Current Status
- Issued on 1/5/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/22/2021 | SEAN SHAHMIRI |
| Corrections Issued | 7/25/2021 | SEAN SHAHMIRI |
| Quality Review Completed | 8/6/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 8/12/2021 | APPLICANT |
| Applicant returned to address corrections | 11/17/2021 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 12/3/2021 | SEAN SHAHMIRI |
| Plan Check Approved | 12/6/2021 | SEAN SHAHMIRI |
| Issued | 1/5/2022 | APPLICANT |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 8/17/2021 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 8/17/2021 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 8/17/2021 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 8/17/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 8/17/2021 | CARLOS AGUILERA |
| "Q" conditions | Cleared | 8/18/2021 | DANIEL CORONADO |
| CPC | Cleared | 8/18/2021 | DANIEL CORONADO |
| Eng Process Fee Ord 176,300 | Cleared | 8/18/2021 | CARLOS AGUILERA |
| Miscellaneous | Cleared | 8/18/2021 | DANIEL CORONADO |
| Miscellaneous | Cleared | 8/18/2021 | DANIEL CORONADO |
| Miscellaneous | Cleared | 8/18/2021 | DANIEL CORONADO |
| Miscellaneous | Cleared | 8/18/2021 | DANIEL CORONADO |
| Private street | Cleared | 8/18/2021 | DANIEL CORONADO |
| ZA Case | Cleared | 8/18/2021 | DANIEL CORONADO |
| ZA Case | Cleared | 8/18/2021 | DANIEL CORONADO |
| ZA Case | Cleared | 8/18/2021 | DANIEL CORONADO |
| ZI | Cleared | 8/18/2021 | DANIEL CORONADO |
| Hydrant and Access approval | Cleared | 10/2/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 11/1/2021 | CHRIS PARK |
| Roof/Waste drainage to street | Cleared | 11/4/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Kim Chong Gook; Lic. No.: 605392-B | 18319 DONMETZ STREET PORTER RANCH, CA 91326 |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/9/2022 | Approved | JEFFREY PARD |
| Sewer | 3/9/2022 | Approved | JEFFREY PARD |
| Excavation/Setback/Form/Re-Bar | 5/16/2022 | Approved | JEFFREY PARD |
| Footing/Foundation/Slab | 6/7/2022 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 8/4/2022 | Partial Approval | JEFFREY PARD |
| Green Building Rough | 8/4/2022 | Not Ready for Inspection | JEFFREY PARD |
| MERV13>=Rough | 8/4/2022 | Not Ready for Inspection | JEFFREY PARD |
| Verify Sprinkler Sign Off | 8/4/2022 | Not Ready for Inspection | JEFFREY PARD |
| Wood Frame | 8/4/2022 | Approved | JEFFREY PARD |
| ELECTRICAL-Rough | 8/9/2022 | Approved | JEFFREY PARD |
| Gas Test | 8/9/2022 | Approved | JEFFREY PARD |
| HVAC-Rough | 8/9/2022 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 8/9/2022 | Approved | JEFFREY PARD |
| Underground Mechanical | 8/9/2022 | Approved | JEFFREY PARD |
| Insulation | 8/18/2022 | Approved | JEFFREY PARD |
| Interior/Exterior Lathing | 8/18/2022 | Approved | JEFFREY PARD |
| Drywall Nailing | 8/26/2022 | Approved | JEFFREY PARD |
| Green Building Rough | 8/26/2022 | Approved | JEFFREY PARD |
| MERV13>=Rough | 10/26/2022 | Not Ready for Inspection | JOHN KIDWELL |
| ELECTRICAL-Final | 4/18/2023 | Approved | DAVID SCANTLIN |
| HVAC-Final | 4/18/2023 | Approved | DAVID SCANTLIN |
| PLUMBING-Final | 4/18/2023 | Approved | DAVID SCANTLIN |
| Enclosure/Fence | 4/21/2023 | Approved | DAVID SCANTLIN |
| HVAC-Final | 4/21/2023 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 12/18/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| Final | 12/18/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| Green Building Final | 12/18/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| MERV13>=Final | 12/18/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| MERV13>=Rough | 12/18/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 12/18/2025 | SGSOV Not Ready | DAVID SCANTLIN |
| Service/Power Release | 12/18/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| Smoke Detectors | 12/18/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| Verify Sprinkler Sign Off | 12/18/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 2/5/2026 | Not Ready for Inspection | DAVID SCANTLIN |
| Final | 2/5/2026 | Not Ready for Inspection | DAVID SCANTLIN |
| Green Building Final | 2/5/2026 | Not Ready for Inspection | DAVID SCANTLIN |
| MERV13>=Final | 2/5/2026 | Not Ready for Inspection | DAVID SCANTLIN |
| MERV13>=Rough | 2/5/2026 | Not Ready for Inspection | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 2/5/2026 | SGSOV Not Ready | DAVID SCANTLIN |
| Service/Power Release | 2/5/2026 | Not Ready for Inspection | DAVID SCANTLIN |
| Smoke Detectors | 2/5/2026 | Not Ready for Inspection | DAVID SCANTLIN |
| Verify Sprinkler Sign Off | 2/5/2026 | Not Ready for Inspection | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 5/22/2026 | Approved | JACK KARGODORIAN |
| Final | 5/22/2026 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 5/22/2026 | Approved | JACK KARGODORIAN |
| MERV13>=Final | 5/22/2026 | Approved | JACK KARGODORIAN |
| MERV13>=Rough | 5/22/2026 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 5/22/2026 | SGSOV Approved | JACK KARGODORIAN |
| Service/Power Release | 5/22/2026 | Not Required | JACK KARGODORIAN |
| Smoke Detectors | 5/22/2026 | Approved | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 5/22/2026 | Approved | JACK KARGODORIAN |