21115 W BASSETT ST 91303

Certificate Information: 21115 W BASSETT ST 91303

Application / Permit
21010-20000-02619
Plan Check / Job No.
B21VN06589
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 43' X 33' 9" IRR.-SHAPE 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK DONE PER STRUCTURAL ENGINEERING.
Permit Issued
Issued on 10/25/2022
Issuing Office
Current Status
CofO Issued on 10/19/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/25/2021 APPLICANT
Assigned to Plan Check Engineer 7/1/2021 GURUNATH NESARAJAH
Corrections Issued 7/4/2021 GURUNATH NESARAJAH
Quality Review Completed 7/7/2021 OMID HEDAYAT
Building Plans Picked Up 7/13/2021 APPLICANT
Applicant returned to address corrections 10/11/2022 GURUNATH NESARAJAH
Applicant returned to address corrections 10/24/2022 GURUNATH NESARAJAH
Plan Check Approved 10/25/2022 GURUNATH NESARAJAH
Issued 10/25/2022 APPLICANT
CofO in Progress 10/4/2023 ALEXANDER HANDY
Permit Finaled 10/19/2023 JOHN JANSON
CofO Issued 10/19/2023 JOHN JANSON
Permit Finaled 10/19/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 11/19/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 11/19/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 11/19/2021 DAGOVERTO GUERRERO
Hydrant and Access approval Cleared 6/20/2022 CINDY JOSSELYN
Low Impact Development Cleared 8/15/2022 SUNG JOON WON
Roof/Waste drainage to street Cleared 8/16/2022 DAGOVERTO GUERRERO
ZI Cleared 9/22/2022 NATHAN ROMINE

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/28/2022 Corrections Issued STEVEN BACK
PLUMBING-Rough 11/28/2022 Partial Approval ALEXANDER HANDY
Footing/Foundation/Slab 1/17/2023 Approved ALEXANDER HANDY
BUILDING-Rough-Frame 3/24/2023 Not Ready for Inspection ALEXANDER HANDY
ELECTRICAL-Rough 3/24/2023 Approved ALEXANDER HANDY
Green Building Rough 3/24/2023 Not Ready for Inspection ALEXANDER HANDY
HVAC-Rough 3/24/2023 Corrections Issued ALEXANDER HANDY
PLUMBING-Rough 3/24/2023 Corrections Issued ALEXANDER HANDY
Verify Sprinkler Sign Off 3/24/2023 Not Ready for Inspection ALEXANDER HANDY
Deputy Wood Construction 3/28/2023 Conditional Approval STEVEN BACK
BUILDING-Rough-Frame 4/5/2023 Corrections Issued HORACE FULTZ
ELECTRICAL-Rough 4/5/2023 Approved HORACE FULTZ
Interior/Exterior Lathing 4/5/2023 Partial Approval HORACE FULTZ
PLUMBING-Rough 4/5/2023 Corrections Issued HORACE FULTZ
BUILDING-Rough-Frame 4/18/2023 Approved ALEXANDER HANDY
Green Building Rough 4/18/2023 Approved ALEXANDER HANDY
Insulation 4/18/2023 Conditional Approval ALEXANDER HANDY
Interior/Exterior Lathing 4/18/2023 Approved ALEXANDER HANDY
PLUMBING-Rough 4/18/2023 Approved ALEXANDER HANDY
Shower Pan 4/18/2023 Approved ALEXANDER HANDY
Verify Sprinkler Sign Off 4/18/2023 Approved ALEXANDER HANDY
Drywall Nailing 4/26/2023 Approved ALEXANDER HANDY
Insulation 4/26/2023 Approved ALEXANDER HANDY
Final 8/23/2023 Corrections Issued ALEXANDER HANDY
Green Building Final 8/23/2023 Approved ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 8/23/2023 SGSOV Not Ready ALEXANDER HANDY
Service/Power Release 8/23/2023 Not Ready for Inspection ALEXANDER HANDY
Smoke Detectors 8/23/2023 Approved ALEXANDER HANDY
ELECTRICAL-Final 9/29/2023 Approved ALEXANDER HANDY
Final 9/29/2023 OK to Issue CofO ALEXANDER HANDY
HVAC-Final 9/29/2023 Approved ALEXANDER HANDY
PLUMBING-Final 9/29/2023 Approved ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 9/29/2023 SGSOV Approved ALEXANDER HANDY
Service/Power Release 9/29/2023 Approved ALEXANDER HANDY