735 N ILIFF ST 90272
Certificate Information: 735 N ILIFF ST 90272
- Application / Permit
- 21010-20000-02609
- Plan Check / Job No.
- B21VN06560
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 72'-8" X 38' (2)-STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 12/15/2021
- Issuing Office
- Current Status
- CofO Issued on 10/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/17/2021 | SELLA BENYAMIN |
| Corrections Issued | 6/22/2021 | SELLA BENYAMIN |
| Quality Review Completed | 6/24/2021 | STEVEN KIM |
| Building Plans Picked Up | 6/29/2021 | APPLICANT |
| Applicant returned to address corrections | 11/19/2021 | SELLA BENYAMIN |
| Plan Check Approved | 12/14/2021 | SELLA BENYAMIN |
| Issued | 12/15/2021 | APPLICANT |
| CofO in Progress | 9/28/2022 | KEVIN SARGSYAN |
| Permit Finaled | 10/20/2022 | DANIEL ORRANTE |
| CofO Issued | 10/20/2022 | DANIEL ORRANTE |
| Permit Finaled | 10/20/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 9/6/2021 | ROBERT DUFF |
| Low Impact Development | Cleared | 9/8/2021 | YVAINNE GALSIM |
| Permit | Cleared | 9/9/2021 | ANTHONY MAINEZ |
| Roof/Waste drainage to street | Cleared | 9/9/2021 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/14/2021 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 9/14/2021 | ANTHONY MAINEZ |
| Trees in Parkway | Cleared | 11/10/2021 | ADALBERTO VERA |
| GPI Written Notices | Cleared | 11/19/2021 | SELLA BENYAMIN |
| Grading Pre-Inspection | Cleared | 11/19/2021 | SELLA BENYAMIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Wang,, Hongyu; Lic. No.: C72679 | 8887 W FALMINGO RD STE 101 LAS VEGAS, NV 89147 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/31/2022 | Partial Inspection | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 2/23/2022 | Corrections Issued | ANDREW NAVE |
| Footing/Foundation/Slab | 2/23/2022 | Not Ready for Inspection | ANDREW NAVE |
| PLUMBING-Rough | 2/23/2022 | Partial Approval | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 3/14/2022 | Partial Inspection | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 3/21/2022 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 4/4/2022 | Not Ready for Inspection | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 4/5/2022 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2022 | Corrections Issued | ANDREW NAVE |
| Deputy Wood Construction | 5/10/2022 | Approved | JOHN KIDWELL |
| ELECTRICAL-Rough | 5/20/2022 | Approved | JOHN KIDWELL |
| HVAC-Rough | 5/20/2022 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 5/20/2022 | Approved | JOHN KIDWELL |
| PLUMBING-Rough | 5/20/2022 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 5/25/2022 | Approved | JOHN KIDWELL |
| Green Building Rough | 5/25/2022 | Approved | JOHN KIDWELL |
| Verify Rec and Parks Fee Memo | 5/25/2022 | Approved | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 5/25/2022 | Approved | JOHN KIDWELL |
| Drywall Nailing | 6/3/2022 | Approved | JUAN VALENZUELA |
| Insulation | 6/3/2022 | Approved | JUAN VALENZUELA |
| Shower Pan | 6/3/2022 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 6/7/2022 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Final | 9/7/2022 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Final | 9/7/2022 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Final | 9/7/2022 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Final | 9/9/2022 | Approved | KEVIN SARGSYAN |
| HVAC-Final | 9/9/2022 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Final | 9/9/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| HVAC-Final | 9/12/2022 | Approved | KEVIN SARGSYAN |
| PLUMBING-Final | 9/13/2022 | Corrections Issued | KEVIN SARGSYAN |
| Gas Test | 9/14/2022 | Approved | KEVIN SARGSYAN |
| PLUMBING-Final | 9/15/2022 | Approved | BRENDAN LOONEY |
| Final | 9/22/2022 | Corrections Issued | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 9/22/2022 | Approved | KEVIN SARGSYAN |
| Green Building Final | 9/22/2022 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 9/22/2022 | SGSOV Approved | KEVIN SARGSYAN |
| Service/Power Release | 9/22/2022 | Approved | KEVIN SARGSYAN |
| Smoke Detectors | 9/22/2022 | Approved | KEVIN SARGSYAN |
| Final | 9/27/2022 | OK to Issue CofO | KEVIN SARGSYAN |