4307 S CAMPBELL DR 90066

Certificate Information: 4307 S CAMPBELL DR 90066

Application / Permit
21010-20000-02599
Plan Check / Job No.
B21VN06539
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 30'-10" X 19'-10" ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d); EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 5/5/2022
Issuing Office
Current Status
CofO Issued on 11/29/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/26/2021 APPLICANT
Assigned to Plan Check Engineer 6/10/2021 SELLA BENYAMIN
Corrections Issued 6/15/2021 SELLA BENYAMIN
Quality Review Completed 6/16/2021 STEVEN KIM
Building Plans Picked Up 6/18/2021 APPLICANT
Applicant returned to address corrections 4/1/2022 SELLA BENYAMIN
Applicant returned to address corrections 4/22/2022 SELLA BENYAMIN
Plan Check Approved 5/5/2022 SELLA BENYAMIN
Issued 5/5/2022 APPLICANT
CofO in Progress 11/29/2023 RICHARD STEINBACH
Permit Finaled 11/29/2023 DANIEL ORRANTE
CofO Issued 11/29/2023 DANIEL ORRANTE
Permit Finaled 11/29/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 10/14/2021 DENNIS BRAGIN
Hydrant and Access approval Cleared 1/10/2022 KURT CORRAL
Eng Process Fee Ord 176,300 Cleared 1/18/2022 DENNIS BRAGIN
Sewer availability Cleared 1/18/2022 DENNIS BRAGIN
Low Impact Development Cleared 3/9/2022 CHRIS VONG
Roof/Waste drainage to street Cleared 3/10/2022 DENNIS BRAGIN

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 5/12/2022 Conditional Approval CLAYTON GRAHAM
Excavation/Setback/Form/Re-Bar 5/20/2022 Approved PATRICK QUALEY
Footing/Foundation/Slab 5/20/2022 Approved PATRICK QUALEY
PLUMBING-Rough 6/15/2022 Partial Approval RICHARD STEINBACH
Wood Frame 6/15/2022 Partial Approval RICHARD STEINBACH
Floor/Roof Diaphrgm/Shear Wall 6/17/2022 Partial Approval STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 9/8/2022 Conditional Approval JESUS RODRIGUEZ
BUILDING-Rough-Frame 10/13/2022 Not Ready for Inspection JESUS RODRIGUEZ
ELECTRICAL-Rough 10/13/2022 Corrections Issued JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 10/13/2022 Approved JESUS RODRIGUEZ
Green Building Rough 10/13/2022 Not Ready for Inspection JESUS RODRIGUEZ
HVAC-Final 10/13/2022 Corrections Issued JESUS RODRIGUEZ
HVAC-Rough 10/13/2022 Approved JESUS RODRIGUEZ
PLUMBING-Rough 10/13/2022 Approved JESUS RODRIGUEZ
Verify Sprinkler Sign Off 10/13/2022 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 11/14/2022 Approved JESUS RODRIGUEZ
Drywall Nailing 11/14/2022 Approved JESUS RODRIGUEZ
Green Building Rough 11/14/2022 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 11/14/2022 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 12/8/2022 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 11/14/2023 Corrections Issued JESUS RODRIGUEZ
Final 11/14/2023 Corrections Issued JESUS RODRIGUEZ
Green Building Final 11/14/2023 Approved JESUS RODRIGUEZ
HVAC-Final 11/14/2023 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Final 11/14/2023 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 11/14/2023 SGSOV Not Ready JESUS RODRIGUEZ
Service/Power Release 11/14/2023 Corrections Issued JESUS RODRIGUEZ
Smoke Detectors 11/14/2023 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 11/27/2023 Approved JESUS RODRIGUEZ
Final 11/27/2023 Corrections Issued JESUS RODRIGUEZ
HVAC-Final 11/27/2023 Approved JESUS RODRIGUEZ
PLUMBING-Final 11/27/2023 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 11/27/2023 SGSOV Approved JESUS RODRIGUEZ
Service/Power Release 11/27/2023 Approved JESUS RODRIGUEZ
Final 11/28/2023 Partial Approval JESUS RODRIGUEZ