21119 W SAN JOSE ST 91311
Certificate Information: 21119 W SAN JOSE ST 91311
- Application / Permit
- 21010-20000-02509
- Plan Check / Job No.
- B21VN06282
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 2 STORY 23'6"X 29' ACCESSORY DWELLING UNIT PER ORDINANCE
- Permit Issued
- Issued on 7/17/2022
- Issuing Office
- Current Status
- CofO Issued on 3/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/1/2021 | HERNAN ARREOLA |
| Corrections Issued | 7/4/2021 | HERNAN ARREOLA |
| Quality Review Completed | 7/15/2021 | JASON HEALEY |
| Plan Check Approved | 7/5/2022 | HERNAN ARREOLA |
| Issued | 7/17/2022 | APPLICANT |
| CofO in Progress | 1/7/2023 | SEAN WIRCH |
| Permit Finaled | 3/18/2023 | DANIEL ORRANTE |
| CofO Issued | 3/18/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/18/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Low Impact Development | Cleared | 1/31/2022 | ANTHONY VARGAS |
| Address approval | Cleared | 2/2/2022 | JOSE DUARTE-DIAZ |
| Roof/Waste drainage to street | Cleared | 2/2/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/8/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 2/8/2022 | JOSE DUARTE-DIAZ |
| Hydrant and Access approval | Cleared | 3/19/2022 | DWIGHT SANKEY |
| GPI Written Notices | Cleared | 7/5/2022 | HERNAN ARREOLA |
| Grading Pre-Inspection | Cleared | 7/5/2022 | HERNAN ARREOLA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Isaac,, Raymond; Lic. No.: NA84605 | , |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/28/2022 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 8/15/2022 | Partial Approval | JEFFREY PARD |
| PLUMBING-Rough | 8/17/2022 | Partial Approval | JEFFREY PARD |
| Footing/Foundation/Slab | 8/18/2022 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 8/26/2022 | Partial Approval | JEFFREY PARD |
| Green Building Rough | 8/26/2022 | Not Ready for Inspection | JEFFREY PARD |
| Verify Sprinkler Sign Off | 8/26/2022 | Not Ready for Inspection | JEFFREY PARD |
| Wood Frame | 8/26/2022 | Approved | JEFFREY PARD |
| Sewer | 9/8/2022 | Approved | JEFFREY PARD |
| ELECTRICAL-Rough | 9/28/2022 | Approved | JEFFREY BULL |
| HVAC-Rough | 9/28/2022 | Partial Approval | JEFFREY BULL |
| PLUMBING-Rough | 9/28/2022 | Corrections Issued | JEFFREY BULL |
| Wood Frame | 9/28/2022 | Approved | JEFFREY BULL |
| Insulation | 10/3/2022 | Not Ready for Inspection | JOHN KIDWELL |
| Drywall Nailing | 10/6/2022 | Approved | KRISTEN CAUSEY |
| Green Building Rough | 10/6/2022 | Approved | KRISTEN CAUSEY |
| Insulation | 10/6/2022 | Approved | KRISTEN CAUSEY |
| Shower Pan | 10/19/2022 | Approved | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 10/26/2022 | Approved | JUSTIN HAWLEY |
| Shower Pan | 10/26/2022 | Approved | JUSTIN HAWLEY |
| PLUMBING-Rough | 10/28/2022 | Approved | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 12/28/2022 | Approved | SEAN HAUPT |
| Final | 12/28/2022 | Corrections Issued | SEAN HAUPT |
| Green Building Final | 12/28/2022 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 12/28/2022 | SGSOV Not Ready | SEAN HAUPT |
| Service/Power Release | 12/28/2022 | Not Ready for Inspection | SEAN HAUPT |
| Smoke Detectors | 12/28/2022 | Not Ready for Inspection | SEAN HAUPT |
| Verify Sprinkler Sign Off | 12/28/2022 | Approved | SEAN HAUPT |
| Final | 12/30/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 12/30/2022 | SGSOV Not Ready | DAVID SCANTLIN |
| Service/Power Release | 12/30/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| Smoke Detectors | 12/30/2022 | Approved | DAVID SCANTLIN |
| Final | 1/6/2023 | OK to Issue CofO | SEAN WIRCH |
| SGSOV-Seismic Gas S/O Valve | 1/6/2023 | SGSOV Approved | SEAN WIRCH |
| Service/Power Release | 1/6/2023 | Approved | SEAN WIRCH |