7410 S AVALON BLVD 1-49 90003
Certificate Information: 7410 S AVALON BLVD 1-49 90003
- Application / Permit
- 21010-20000-02472
- Plan Check / Job No.
- B21VN06139
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- NEW 91'5" X 97'1" FOUR STORY 49 UNITS APARTMENT WITH RECREATION ROOM AT 1ST FLOOR , FULLY SPRINKLERED NFPA-13 (TYPE VA CONSTRUCTION ) ( TOC, TIER 1 ( INCREASE TO TIER 2 - 100% AFFORDABLE HOUSING TO INCLUDE 5 EXTREMELLY LOW INCOME, 43 LOW INCOME AND 1 MANAGER UNIT) [PER ADM-2021-2246-TOC], ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 8/17/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/8/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/19/2021 | APPLICANT |
| Green Plans Picked Up | 5/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/3/2021 | RARES BODEA |
| Corrections Issued | 6/6/2021 | RARES BODEA |
| Quality Review Completed | 6/10/2021 | STEVEN KIM |
| Building Plans Picked Up | 6/24/2021 | APPLICANT |
| Applicant returned to address corrections | 1/9/2023 | RARES BODEA |
| Applicant returned to address corrections | 8/9/2023 | RARES BODEA |
| Plan Check Approved | 8/9/2023 | RARES BODEA |
| Issued | 8/17/2023 | APPLICANT |
| CofO in Progress | 1/8/2026 | RAFAEL ESPINOZA |
| Permit Finaled | 1/8/2026 | RAFAEL ESPINOZA |
| CofO Issued | 1/8/2026 | RAFAEL ESPINOZA |
| Permit Finaled | 1/8/2026 | RAFAEL ESPINOZA |
Permit Application Clearance Information
| Address approval | Cleared | 7/13/2021 | WALLIE JONG |
| Community Plan Implem. Overlay | Cleared | 7/13/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 7/15/2021 | WALLIE JONG |
| DAS Clearance | Cleared | 7/20/2021 | OLLIE CARTER |
| Hydrant and Access approval | Cleared | 8/26/2021 | MATTHEW CRAIG |
| Sewer availability | Cleared | 12/14/2021 | WALLIE JONG |
| Community Plan Implem. Overlay | Cleared | 12/21/2021 | ADALBERTO VERA |
| Highway dedication | Cleared | 1/27/2022 | WALLIE JONG |
| Certificate of Compliance | Cleared | 5/10/2022 | MIGUEL GAMBOA |
| Miscellaneous | Cleared | 5/10/2022 | MIGUEL GAMBOA |
| Tract Map conditions | Cleared | 5/10/2022 | MIGUEL GAMBOA |
| Frnt yard landscape/Water mgmt | Cleared | 5/16/2022 | MIGUEL GAMBOA |
| Community Plan Implem. Overlay | Cleared | 7/26/2022 | PETE EYRE |
| Community Plan Implem. Overlay | Cleared | 9/28/2022 | RIDWAN HARDY |
| Construction near power lines | Cleared | 9/28/2022 | RIDWAN HARDY |
| Fire Marshall Fire Life Safety | Cleared | 1/17/2023 | VIDAL GARCIA |
| Community Plan Implem. Overlay | Cleared | 1/25/2023 | HELEN JADALI |
| Redevelopment Project Area | Cleared | 1/26/2023 | GRACIELA ACOSTA |
| Redevelopment Project Area | Cleared | 1/26/2023 | GRACIELA ACOSTA |
| Opn space landscape/Water mgmt | Cleared | 3/2/2023 | SPENCER WEJROWSKI |
| Trees in Parkway | Cleared | 4/5/2023 | ADALBERTO VERA |
| DCP conditions approval | Cleared | 6/20/2023 | RARES BODEA |
| Density Bonus 12.22.A.31 | Cleared | 6/20/2023 | NICHOLAS KAWAZOE |
| Density Bonus 12.22.A.31 | Cleared | 6/20/2023 | RARES BODEA |
| Low Impact Development | Cleared | 7/22/2023 | TA ANH |
| Green Code | Cleared | 7/26/2023 | MICHAEL AYERS |
| Permit | Cleared | 7/27/2023 | ADRIAN SANCHEZ |
| Roof/Waste drainage to street | Cleared | 7/27/2023 | ADRIAN SANCHEZ |
| Building over 3-story or 36-ft | Cleared | 8/9/2023 | CALOSHA APPROVED |
Contact Information
| Contractor | S & K Quality Builders Inc; Lic. No.: 1026841-B | 16551 VICTORY BLVD #206 VAN NUYS, CA 91406 |
| Engineer | Gharai,, Armin; Lic. No.: C61464 | 6701 CORIE LN WEST HILLS, CA 91307 |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/18/2023 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 10/20/2023 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 12/15/2023 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 1/9/2024 | Partial Approval | JAMES POWERS |
| Footing/Foundation/Slab | 1/10/2024 | Not Ready for Inspection | JAMES POWERS |
| Reinforced Concrete Frame | 1/11/2024 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 1/12/2024 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 1/16/2024 | Partial Approval | JAMES POWERS |
| Deputy Steel/Welding | 2/28/2024 | Partial Approval | JAMES POWERS |
| Deputy Steel/Welding | 2/29/2024 | Partial Approval | JAMES POWERS |
| Green Building Rough | 3/12/2024 | Approved | RAFAEL ESPINOZA |
| Structural Steel Frame | 3/12/2024 | Partial Approval | RAFAEL ESPINOZA |
| Verify Sprinkler Sign Off | 3/12/2024 | Partial Inspection | RAFAEL ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2024 | Partial Approval | RAFAEL ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 4/2/2024 | Partial Approval | RAFAEL ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 4/12/2024 | Partial Approval | RAFAEL ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2024 | Partial Approval | RAFAEL ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2024 | Partial Approval | RAFAEL ESPINOZA |
| Verify Sprinkler Sign Off | 6/14/2024 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Verify Sprinkler Sign Off | 7/19/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| Wood Frame | 7/19/2024 | Partial Approval | ALFREDO LOPEZ |
| Drywall Nailing | 7/31/2024 | Partial Approval | ALFREDO LOPEZ |
| Insulation | 7/31/2024 | Partial Approval | ALFREDO LOPEZ |
| Drywall Nailing | 8/19/2024 | Partial Approval | DANIEL VARNUM |
| Drywall Nailing | 8/30/2024 | Not Ready for Inspection | LARRY ARNICK |
| Special/Order Compliance | 8/30/2024 | Not Ready for Inspection | LARRY ARNICK |
| Special/Order Compliance | 9/3/2024 | Partial Approval | DAVID BURKHEAD |
| Special/Order Compliance | 9/9/2024 | Partial Approval | LARRY ARNICK |
| Pre-Inspection | 9/20/2024 | Partial Inspection | RAFAEL ESPINOZA |
| Drywall Nailing | 9/25/2024 | Partial Approval | RAFAEL CORTES |
| Drywall Nailing | 9/27/2024 | Partial Approval | RAFAEL CORTES |
| Insulation | 9/27/2024 | Partial Approval | RAFAEL CORTES |
| Pre-Inspection | 10/1/2024 | Approved | RAFAEL CORTES |
| Verify Sprinkler Sign Off | 10/1/2024 | Not Ready for Inspection | RAFAEL CORTES |
| Wood Frame | 10/1/2024 | Not Ready for Inspection | RAFAEL CORTES |
| Drywall Nailing | 10/7/2024 | Not Ready for Inspection | RAFAEL CORTES |
| Special/Order Compliance | 10/9/2024 | Partial Inspection | RAFAEL ESPINOZA |
| Drywall Nailing | 10/10/2024 | Partial Approval | RAFAEL ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 10/10/2024 | Partial Approval | RAFAEL ESPINOZA |
| Wood Frame | 10/10/2024 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Drywall Nailing | 10/16/2024 | Partial Approval | RAFAEL ESPINOZA |
| Wood Frame | 10/25/2024 | Partial Approval | RAFAEL ESPINOZA |
| Drywall Nailing | 10/30/2024 | Corrections Issued | RAFAEL ESPINOZA |
| Insulation | 11/4/2024 | Partial Approval | RAFAEL ESPINOZA |
| Wood Frame | 11/4/2024 | Partial Approval | RAFAEL ESPINOZA |
| Insulation | 11/6/2024 | Not Ready for Inspection | RAFAEL CORTES |
| Insulation | 11/8/2024 | Partial Approval | RAFAEL ESPINOZA |
| Wood Frame | 11/8/2024 | Partial Approval | RAFAEL ESPINOZA |
| Drywall Nailing | 11/18/2024 | Partial Approval | RAFAEL ESPINOZA |
| Insulation | 11/18/2024 | Partial Approval | RAFAEL ESPINOZA |
| Wood Frame | 11/18/2024 | Partial Approval | RAFAEL ESPINOZA |
| Drywall Nailing | 11/25/2024 | Partial Approval | RAFAEL ESPINOZA |
| Drywall Nailing | 12/6/2024 | Partial Approval | RAFAEL ESPINOZA |
| Insulation | 12/6/2024 | Partial Approval | RAFAEL ESPINOZA |
| Drywall Nailing | 12/12/2024 | Partial Approval | RAFAEL ESPINOZA |
| Wood Frame | 12/12/2024 | Partial Approval | RAFAEL ESPINOZA |
| Insulation | 12/17/2024 | Partial Approval | RAFAEL ESPINOZA |
| Insulation | 12/20/2024 | Partial Approval | RAFAEL ESPINOZA |
| Wood Frame | 12/20/2024 | Partial Approval | RAFAEL ESPINOZA |
| Drywall Nailing | 1/6/2025 | Partial Approval | LARRY ARNICK |
| Wood Frame | 1/6/2025 | Partial Approval | LARRY ARNICK |
| Drywall Nailing | 1/13/2025 | Partial Approval | RAFAEL CORTES |
| Insulation | 1/13/2025 | Partial Approval | RAFAEL CORTES |
| Drywall Nailing | 1/23/2025 | Partial Approval | RAFAEL ESPINOZA |
| Insulation | 1/23/2025 | Partial Approval | RAFAEL ESPINOZA |
| Drywall Nailing | 2/7/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Drywall Nailing | 2/11/2025 | Partial Approval | RAFAEL ESPINOZA |
| Wood Frame | 2/14/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Wood Frame | 2/21/2025 | Partial Approval | RAFAEL ESPINOZA |
| Drywall Nailing | 2/26/2025 | Partial Approval | RAFAEL CORTES |
| Drywall Nailing | 3/4/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Light Gage Steel Frame | 3/4/2025 | Partial Approval | RAFAEL CORTES |
| Drywall Nailing | 3/7/2025 | Partial Approval | RAFAEL ESPINOZA |
| Light Gage Steel Frame | 3/7/2025 | Partial Approval | RAFAEL ESPINOZA |
| Wood Frame | 3/7/2025 | Partial Approval | RAFAEL ESPINOZA |
| Drywall Nailing | 3/12/2025 | Partial Approval | RAFAEL ESPINOZA |
| Light Gage Steel Frame | 3/14/2025 | Partial Approval | RAFAEL ESPINOZA |
| Drywall Nailing | 3/20/2025 | Partial Approval | RAFAEL ESPINOZA |
| Interior/Exterior Lathing | 3/20/2025 | Partial Approval | RAFAEL ESPINOZA |
| Drywall Nailing | 4/4/2025 | Partial Approval | RAFAEL ESPINOZA |
| Light Gage Steel Frame | 4/4/2025 | Partial Approval | RAFAEL ESPINOZA |
| Interior/Exterior Lathing | 4/18/2025 | Partial Approval | RAFAEL ESPINOZA |
| Light Gage Steel Frame | 4/18/2025 | Partial Approval | RAFAEL ESPINOZA |
| Drywall Nailing | 4/23/2025 | Partial Approval | RAFAEL ESPINOZA |
| Interior/Exterior Lathing | 4/23/2025 | Partial Approval | RAFAEL ESPINOZA |
| Interior/Exterior Lathing | 5/1/2025 | Partial Approval | RAFAEL ESPINOZA |
| Interior/Exterior Lathing | 6/3/2025 | Partial Approval | RAFAEL ESPINOZA |
| Pre-Inspection | 6/25/2025 | Partial Inspection | RAFAEL ESPINOZA |
| Drywall Nailing | 6/27/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Special/Order Compliance | 6/30/2025 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 10/6/2025 | Approved | RAFAEL ESPINOZA |
| Final | 10/6/2025 | Corrections Issued | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 10/6/2025 | Approved | RAFAEL ESPINOZA |
| Reinforced Masonry Frame | 10/6/2025 | Approved | RAFAEL ESPINOZA |
| SGSOV-Seismic Gas S/O Valve | 10/6/2025 | SGSOV Not Ready | RAFAEL ESPINOZA |
| Smoke Detectors | 10/6/2025 | Approved | RAFAEL ESPINOZA |
| Structural Steel Frame | 10/6/2025 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Verify Sprinkler Sign Off | 10/6/2025 | Approved | RAFAEL ESPINOZA |
| Wood Frame | 10/6/2025 | Approved | RAFAEL ESPINOZA |
| Final | 10/22/2025 | Partial Inspection | RAFAEL ESPINOZA |
| Green Building Final | 10/22/2025 | Approved | RAFAEL ESPINOZA |
| SGSOV-Seismic Gas S/O Valve | 10/22/2025 | SGSOV Approved | RAFAEL ESPINOZA |
| Structural Steel Frame | 10/22/2025 | Approved | RAFAEL ESPINOZA |
| Final | 1/6/2026 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Final | 1/8/2026 | OK to Issue CofO | RAFAEL ESPINOZA |