7410 S AVALON BLVD 1-49 90003

Certificate Information: 7410 S AVALON BLVD 1-49 90003

Application / Permit
21010-20000-02472
Plan Check / Job No.
B21VN06139
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 91'5" X 97'1" FOUR STORY 49 UNITS APARTMENT WITH RECREATION ROOM AT 1ST FLOOR , FULLY SPRINKLERED NFPA-13 (TYPE VA CONSTRUCTION ) ( TOC, TIER 1 ( INCREASE TO TIER 2 - 100% AFFORDABLE HOUSING TO INCLUDE 5 EXTREMELLY LOW INCOME, 43 LOW INCOME AND 1 MANAGER UNIT) [PER ADM-2021-2246-TOC], ALL WORK PER ENGINEERING
Permit Issued
Issued on 8/17/2023
Issuing Office
Metro
Current Status
CofO Issued on 1/8/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/19/2021 APPLICANT
Green Plans Picked Up 5/27/2021 APPLICANT
Assigned to Plan Check Engineer 6/3/2021 RARES BODEA
Corrections Issued 6/6/2021 RARES BODEA
Quality Review Completed 6/10/2021 STEVEN KIM
Building Plans Picked Up 6/24/2021 APPLICANT
Applicant returned to address corrections 1/9/2023 RARES BODEA
Applicant returned to address corrections 8/9/2023 RARES BODEA
Plan Check Approved 8/9/2023 RARES BODEA
Issued 8/17/2023 APPLICANT
CofO in Progress 1/8/2026 RAFAEL ESPINOZA
Permit Finaled 1/8/2026 RAFAEL ESPINOZA
CofO Issued 1/8/2026 RAFAEL ESPINOZA
Permit Finaled 1/8/2026 RAFAEL ESPINOZA

Permit Application Clearance Information

Address approval Cleared 7/13/2021 WALLIE JONG
Community Plan Implem. Overlay Cleared 7/13/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 7/15/2021 WALLIE JONG
DAS Clearance Cleared 7/20/2021 OLLIE CARTER
Hydrant and Access approval Cleared 8/26/2021 MATTHEW CRAIG
Sewer availability Cleared 12/14/2021 WALLIE JONG
Community Plan Implem. Overlay Cleared 12/21/2021 ADALBERTO VERA
Highway dedication Cleared 1/27/2022 WALLIE JONG
Certificate of Compliance Cleared 5/10/2022 MIGUEL GAMBOA
Miscellaneous Cleared 5/10/2022 MIGUEL GAMBOA
Tract Map conditions Cleared 5/10/2022 MIGUEL GAMBOA
Frnt yard landscape/Water mgmt Cleared 5/16/2022 MIGUEL GAMBOA
Community Plan Implem. Overlay Cleared 7/26/2022 PETE EYRE
Community Plan Implem. Overlay Cleared 9/28/2022 RIDWAN HARDY
Construction near power lines Cleared 9/28/2022 RIDWAN HARDY
Fire Marshall Fire Life Safety Cleared 1/17/2023 VIDAL GARCIA
Community Plan Implem. Overlay Cleared 1/25/2023 HELEN JADALI
Redevelopment Project Area Cleared 1/26/2023 GRACIELA ACOSTA
Redevelopment Project Area Cleared 1/26/2023 GRACIELA ACOSTA
Opn space landscape/Water mgmt Cleared 3/2/2023 SPENCER WEJROWSKI
Trees in Parkway Cleared 4/5/2023 ADALBERTO VERA
DCP conditions approval Cleared 6/20/2023 RARES BODEA
Density Bonus 12.22.A.31 Cleared 6/20/2023 NICHOLAS KAWAZOE
Density Bonus 12.22.A.31 Cleared 6/20/2023 RARES BODEA
Low Impact Development Cleared 7/22/2023 TA ANH
Green Code Cleared 7/26/2023 MICHAEL AYERS
Permit Cleared 7/27/2023 ADRIAN SANCHEZ
Roof/Waste drainage to street Cleared 7/27/2023 ADRIAN SANCHEZ
Building over 3-story or 36-ft Cleared 8/9/2023 CALOSHA APPROVED

Contact Information

Contractor S & K Quality Builders Inc; Lic. No.: 1026841-B 16551 VICTORY BLVD #206      VAN NUYS, CA 91406
Engineer Gharai,, Armin; Lic. No.: C61464 6701 CORIE LN      WEST HILLS, CA 91307
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/18/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/20/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/15/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/9/2024 Partial Approval JAMES POWERS
Footing/Foundation/Slab 1/10/2024 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 1/11/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/12/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/16/2024 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/28/2024 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/29/2024 Partial Approval JAMES POWERS
Green Building Rough 3/12/2024 Approved RAFAEL ESPINOZA
Structural Steel Frame 3/12/2024 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 3/12/2024 Partial Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 3/21/2024 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 4/2/2024 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 4/12/2024 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 4/29/2024 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 6/14/2024 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 6/14/2024 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 7/19/2024 Not Ready for Inspection ALFREDO LOPEZ
Wood Frame 7/19/2024 Partial Approval ALFREDO LOPEZ
Drywall Nailing 7/31/2024 Partial Approval ALFREDO LOPEZ
Insulation 7/31/2024 Partial Approval ALFREDO LOPEZ
Drywall Nailing 8/19/2024 Partial Approval DANIEL VARNUM
Drywall Nailing 8/30/2024 Not Ready for Inspection LARRY ARNICK
Special/Order Compliance 8/30/2024 Not Ready for Inspection LARRY ARNICK
Special/Order Compliance 9/3/2024 Partial Approval DAVID BURKHEAD
Special/Order Compliance 9/9/2024 Partial Approval LARRY ARNICK
Pre-Inspection 9/20/2024 Partial Inspection RAFAEL ESPINOZA
Drywall Nailing 9/25/2024 Partial Approval RAFAEL CORTES
Drywall Nailing 9/27/2024 Partial Approval RAFAEL CORTES
Insulation 9/27/2024 Partial Approval RAFAEL CORTES
Pre-Inspection 10/1/2024 Approved RAFAEL CORTES
Verify Sprinkler Sign Off 10/1/2024 Not Ready for Inspection RAFAEL CORTES
Wood Frame 10/1/2024 Not Ready for Inspection RAFAEL CORTES
Drywall Nailing 10/7/2024 Not Ready for Inspection RAFAEL CORTES
Special/Order Compliance 10/9/2024 Partial Inspection RAFAEL ESPINOZA
Drywall Nailing 10/10/2024 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 10/10/2024 Partial Approval RAFAEL ESPINOZA
Wood Frame 10/10/2024 Not Ready for Inspection RAFAEL ESPINOZA
Drywall Nailing 10/16/2024 Partial Approval RAFAEL ESPINOZA
Wood Frame 10/25/2024 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 10/30/2024 Corrections Issued RAFAEL ESPINOZA
Insulation 11/4/2024 Partial Approval RAFAEL ESPINOZA
Wood Frame 11/4/2024 Partial Approval RAFAEL ESPINOZA
Insulation 11/6/2024 Not Ready for Inspection RAFAEL CORTES
Insulation 11/8/2024 Partial Approval RAFAEL ESPINOZA
Wood Frame 11/8/2024 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 11/18/2024 Partial Approval RAFAEL ESPINOZA
Insulation 11/18/2024 Partial Approval RAFAEL ESPINOZA
Wood Frame 11/18/2024 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 11/25/2024 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 12/6/2024 Partial Approval RAFAEL ESPINOZA
Insulation 12/6/2024 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 12/12/2024 Partial Approval RAFAEL ESPINOZA
Wood Frame 12/12/2024 Partial Approval RAFAEL ESPINOZA
Insulation 12/17/2024 Partial Approval RAFAEL ESPINOZA
Insulation 12/20/2024 Partial Approval RAFAEL ESPINOZA
Wood Frame 12/20/2024 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 1/6/2025 Partial Approval LARRY ARNICK
Wood Frame 1/6/2025 Partial Approval LARRY ARNICK
Drywall Nailing 1/13/2025 Partial Approval RAFAEL CORTES
Insulation 1/13/2025 Partial Approval RAFAEL CORTES
Drywall Nailing 1/23/2025 Partial Approval RAFAEL ESPINOZA
Insulation 1/23/2025 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 2/7/2025 Not Ready for Inspection RAFAEL CORTES
Drywall Nailing 2/11/2025 Partial Approval RAFAEL ESPINOZA
Wood Frame 2/14/2025 Not Ready for Inspection RAFAEL CORTES
Wood Frame 2/21/2025 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 2/26/2025 Partial Approval RAFAEL CORTES
Drywall Nailing 3/4/2025 Not Ready for Inspection RAFAEL CORTES
Light Gage Steel Frame 3/4/2025 Partial Approval RAFAEL CORTES
Drywall Nailing 3/7/2025 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 3/7/2025 Partial Approval RAFAEL ESPINOZA
Wood Frame 3/7/2025 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 3/12/2025 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 3/14/2025 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 3/20/2025 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 3/20/2025 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 4/4/2025 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 4/4/2025 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 4/18/2025 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 4/18/2025 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 4/23/2025 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 4/23/2025 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 5/1/2025 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 6/3/2025 Partial Approval RAFAEL ESPINOZA
Pre-Inspection 6/25/2025 Partial Inspection RAFAEL ESPINOZA
Drywall Nailing 6/27/2025 Not Ready for Inspection RAFAEL CORTES
Special/Order Compliance 6/30/2025 Partial Approval JAMES POWERS
Drywall Nailing 10/6/2025 Approved RAFAEL ESPINOZA
Final 10/6/2025 Corrections Issued RAFAEL ESPINOZA
Footing/Foundation/Slab 10/6/2025 Approved RAFAEL ESPINOZA
Reinforced Masonry Frame 10/6/2025 Approved RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 10/6/2025 SGSOV Not Ready RAFAEL ESPINOZA
Smoke Detectors 10/6/2025 Approved RAFAEL ESPINOZA
Structural Steel Frame 10/6/2025 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 10/6/2025 Approved RAFAEL ESPINOZA
Wood Frame 10/6/2025 Approved RAFAEL ESPINOZA
Final 10/22/2025 Partial Inspection RAFAEL ESPINOZA
Green Building Final 10/22/2025 Approved RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 10/22/2025 SGSOV Approved RAFAEL ESPINOZA
Structural Steel Frame 10/22/2025 Approved RAFAEL ESPINOZA
Final 1/6/2026 Not Ready for Inspection RAFAEL ESPINOZA
Final 1/8/2026 OK to Issue CofO RAFAEL ESPINOZA