13136 W DESMOND ST 91331

Certificate Information: 13136 W DESMOND ST 91331

Application / Permit
21010-20000-02470
Plan Check / Job No.
B21VN06136
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 29'-0" X 31'-0" 1-STORY DETACHED ADU PER LAMC 12.22 A.33(c) and (d). ALL WORK PER WFPP
Permit Issued
Issued on 4/15/2022
Issuing Office
Current Status
CofO Issued on 8/2/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/20/2021 APPLICANT
Assigned to Plan Check Engineer 6/24/2021 MARVEL DELACRUZ
Corrections Issued 6/26/2021 MARVEL DELACRUZ
Quality Review Completed 7/2/2021 STEVEN KIM
Applicant returned to address corrections 2/18/2022 MARVEL DELACRUZ
Plan Check Approved 4/11/2022 RAPHAEL ROSAS
Issued 4/15/2022 APPLICANT
CofO in Progress 7/29/2022 MICHEL ABAJAN
Permit Finaled 8/2/2022 DANIEL ORRANTE
CofO Issued 8/2/2022 DANIEL ORRANTE
Permit Finaled 8/2/2022 DANIEL ORRANTE

Permit Application Clearance Information

ZI Cleared 7/20/2021 MIGUEL GAMBOA
Address approval Cleared 7/21/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 7/23/2021 CARLOS AGUILERA
Sewer availability Cleared 7/23/2021 CARLOS AGUILERA
Hydrant and Access approval Cleared 10/2/2021 RUEL COLE
Low Impact Development Cleared 3/4/2022 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 3/7/2022 CARLOS AGUILERA
Green Code Cleared 3/31/2022 MARVEL DELACRUZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/19/2022 Approved MICHEL ABAJAN
Footing/Foundation/Slab 4/19/2022 Approved MICHEL ABAJAN
PLUMBING-Rough 4/19/2022 Partial Approval MICHEL ABAJAN
Sewer 4/19/2022 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 5/5/2022 Partial Approval MICHEL ABAJAN
Deputy Drilled-In Anchors 5/6/2022 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 5/12/2022 Approved MICHEL ABAJAN
ELECTRICAL-Rough 5/12/2022 Approved MICHEL ABAJAN
Green Building Rough 5/12/2022 Approved MICHEL ABAJAN
HVAC-Rough 5/12/2022 Approved MICHEL ABAJAN
Interior/Exterior Lathing 5/12/2022 Partial Inspection MICHEL ABAJAN
MERV13>=Rough 5/12/2022 Approved MICHEL ABAJAN
PLUMBING-Rough 5/12/2022 Approved MICHEL ABAJAN
Underground Mechanical 5/12/2022 Partial Approval MICHEL ABAJAN
Verify Sprinkler Sign Off 5/12/2022 Approved MICHEL ABAJAN
Insulation 5/16/2022 Approved MICHEL ABAJAN
Interior/Exterior Lathing 5/16/2022 Approved MICHEL ABAJAN
Drywall Nailing 5/20/2022 Approved MICHEL ABAJAN
Final 7/6/2022 Corrections Issued OGANES TARAKHCHYAN
Green Building Final 7/6/2022 Approved OGANES TARAKHCHYAN
MERV13>=Final 7/6/2022 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 7/6/2022 SGSOV Approved OGANES TARAKHCHYAN
Service/Power Release 7/6/2022 Approved OGANES TARAKHCHYAN
Smoke Detectors 7/6/2022 Approved OGANES TARAKHCHYAN
Final 7/21/2022 Not Ready for Inspection MICHEL ABAJAN
ELECTRICAL-Final 7/29/2022 Approved MICHEL ABAJAN
Final 7/29/2022 OK to Issue CofO MICHEL ABAJAN
HVAC-Final 7/29/2022 Approved MICHEL ABAJAN
PLUMBING-Final 7/29/2022 Approved MICHEL ABAJAN