17731 W BURTON ST 91335
Certificate Information: 17731 W BURTON ST 91335
- Application / Permit
- 21010-20000-02447
- Plan Check / Job No.
- B21VN06063
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (22) Storage Building
- Work Description
- PROPOSED NEW 10'X11" DETACHED STORAGE BUILDING. ALL WORK PER WFPP.
- Permit Issued
- Issued on 8/20/2021
- Issuing Office
- Current Status
- CofO Issued on 9/8/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/24/2021 | HAYATO TSUCHIYA |
| Corrections Issued | 5/25/2021 | HAYATO TSUCHIYA |
| Plan Check Approved | 8/20/2021 | HAYATO TSUCHIYA |
| Issued | 8/20/2021 | APPLICANT |
| Building Plans Picked Up | 8/25/2021 | APPLICANT |
| CofO in Progress | 7/26/2025 | ROBERT GOLD |
| Permit Finaled | 9/8/2025 | MICHAEL PELHAM |
| CofO Issued | 9/8/2025 | MICHAEL PELHAM |
| Permit Finaled | 9/8/2025 | MICHAEL PELHAM |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/3/2021 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 6/3/2021 | DAGOVERTO GUERRERO |
| Construction near power lines | Cleared | 8/5/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/23/2022 | Not Ready for Inspection | VINCENT HANLEY |
| BUILDING-Rough-Frame | 3/14/2022 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 3/14/2022 | Approved | VINCENT HANLEY |
| Green Building Rough | 3/14/2022 | Approved | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 3/14/2022 | Not Ready for Inspection | VINCENT HANLEY |
| BUILDING-Rough-Frame | 6/27/2022 | Approved | JEFFREY BULL |
| Drywall Nailing | 6/27/2022 | Approved | JEFFREY BULL |
| Final | 6/27/2022 | Corrections Issued | JEFFREY BULL |
| Footing/Foundation/Slab | 6/27/2022 | Approved | JEFFREY BULL |
| Green Building Final | 6/27/2022 | Approved | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 6/27/2022 | SGSOV Approved | JEFFREY BULL |
| Service/Power Release | 6/27/2022 | Approved | JEFFREY BULL |
| Smoke Detectors | 6/27/2022 | Approved | JEFFREY BULL |
| Final | 7/26/2025 | OK to Issue CofO | ROBERT GOLD |
| Special/Order Compliance | 8/12/2025 | Approved | ROBERT GOLD |