9917 W COVELLO ST 91504

Certificate Information: 9917 W COVELLO ST 91504

Application / Permit
21010-20000-02440
Plan Check / Job No.
B21VN06047
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan new ADU. New detached one-story ADU (1200 sq.ft.).
Permit Issued
Issued on 12/4/2021
Issuing Office
Current Status
CofO Issued on 9/7/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/17/2021 APPLICANT
Assigned to Plan Check Engineer 6/24/2021 ARSALAN SHABESTARI
Corrections Issued 7/1/2021 ARSALAN SHABESTARI
Quality Review Completed 7/15/2021 MICHAEL PEREZ
Plan Check Approved 11/29/2021 ARSALAN SHABESTARI
Issued 12/4/2021 APPLICANT
CofO in Progress 9/7/2022 DAVID ANDERSON
Permit Finaled 9/7/2022 MICHAEL SMITH
CofO Issued 9/7/2022 MICHAEL SMITH
Permit Finaled 9/7/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 7/21/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 7/21/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 7/21/2021 DAGOVERTO GUERRERO
Construction near power lines Cleared 10/7/2021 RIDWAN HARDY
Construction within easement Cleared 10/7/2021 RIDWAN HARDY
Hydrant and Access approval Cleared 10/11/2021 GILBERT URREA
Low Impact Development Cleared 10/28/2021 ROGELIO CORTES
Roof/Waste drainage to street Cleared 11/9/2021 DAGOVERTO GUERRERO
Hold Cleared 2/22/2022 JAZELLE A TRINIDAD

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MATTHEW NELSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/25/2022 Approved JENNIFER RABUCHIN
PLUMBING-Rough 3/16/2022 Partial Approval KRISTEN CAUSEY
Sewer 3/16/2022 Approved KRISTEN CAUSEY
ELECTRICAL-Rough 3/21/2022 Partial Approval CHRISTOPHER DELLEFIELD
Insulation 3/21/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 3/23/2022 Partial Approval GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 3/29/2022 Partial Approval CHRISTOPHER DELLEFIELD
Deputy Wood Construction 4/18/2022 Conditional Approval WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 4/20/2022 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 5/6/2022 Approved MATTHEW NELSON
HVAC-Rough 5/6/2022 Approved MATTHEW NELSON
Interior/Exterior Lathing 5/6/2022 Approved MATTHEW NELSON
PLUMBING-Rough 5/6/2022 Approved MATTHEW NELSON
Wood Frame 5/6/2022 Approved MATTHEW NELSON
BUILDING-Rough-Frame 5/11/2022 Corrections Issued WILLIAM WREN
Insulation 5/11/2022 Approved WILLIAM WREN
Drywall Nailing 5/16/2022 Conditional Approval CHRISTOPHER DELLEFIELD
Green Building Rough 5/25/2022 Approved WILLIAM WREN
Interior/Exterior Lathing 5/25/2022 Approved WILLIAM WREN
Shower Pan 5/25/2022 Approved WILLIAM WREN
BUILDING-Rough-Frame 8/26/2022 Approved DAVID ANDERSON
Final 8/26/2022 Corrections Issued DAVID ANDERSON
Green Building Final 8/26/2022 Approved DAVID ANDERSON
MERV13>=Final 8/26/2022 Approved DAVID ANDERSON
MERV13>=Rough 8/26/2022 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 8/26/2022 SGSOV Approved DAVID ANDERSON
Service/Power Release 8/26/2022 Not Ready for Inspection DAVID ANDERSON
Smoke Detectors 8/26/2022 Approved DAVID ANDERSON
Verify Sprinkler Sign Off 8/26/2022 Approved DAVID ANDERSON
Final 9/6/2022 OK to Issue CofO DAVID ANDERSON
Service/Power Release 9/6/2022 Approved DAVID ANDERSON