14638 W NURMI ST 91342
Certificate Information: 14638 W NURMI ST 91342
- Application / Permit
- 21010-20000-02433
- Plan Check / Job No.
- B21VN06035
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 38' X 51'-9" ONE STORY SINGLE FAMILY DWELLING WITH ATTACHED CARPORT; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 12/8/2021
- Issuing Office
- Current Status
- CofO Issued on 9/13/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2021 | SELLA BENYAMIN |
| Corrections Issued | 7/1/2021 | SELLA BENYAMIN |
| Quality Review Completed | 7/2/2021 | STEVEN KIM |
| Applicant returned to address corrections | 11/15/2021 | SELLA BENYAMIN |
| Plan Check Approved | 11/30/2021 | SELLA BENYAMIN |
| Issued | 12/8/2021 | APPLICANT |
| CofO in Progress | 9/6/2022 | ARAM AVEDISIAN |
| CofO Issued | 9/13/2022 | MICHAEL SMITH |
| Permit Finaled | 9/13/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 7/14/2021 | CARLOS AGUILERA |
| Permit | Cleared | 7/14/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/15/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/15/2021 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 9/1/2021 | ROBERT DUFF |
| Trees in Parkway | Cleared | 10/21/2021 | ADALBERTO VERA |
| Low Impact Development | Cleared | 10/22/2021 | LONDY ALVARADO |
| Low Impact Development | Cleared | 10/27/2021 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 11/4/2021 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/13/2021 | Corrections Issued | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 12/28/2021 | Not Ready for Inspection | JOHN HAYES |
| Special/Order Compliance | 12/28/2021 | Not Ready for Inspection | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 1/6/2022 | Approved | JOHN HAYES |
| Underground Mechanical | 1/6/2022 | Approved | JOHN HAYES |
| ELECTRICAL-Rough | 3/29/2022 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 3/29/2022 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 3/29/2022 | Not Ready for Inspection | JOHN HAYES |
| Wood Frame | 3/29/2022 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 4/11/2022 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 4/11/2022 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 4/11/2022 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 4/11/2022 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 4/19/2022 | Corrections Issued | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 4/19/2022 | Not Ready for Inspection | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 4/19/2022 | Not Ready for Inspection | JOHN HAYES |
| Special/Order Compliance | 4/19/2022 | Not Ready for Inspection | JOHN HAYES |
| Deputy Wood Construction | 4/25/2022 | Conditional Approval | JOHN HAYES |
| ELECTRICAL-Rough | 4/27/2022 | Approved | JOHN HAYES |
| HVAC-Rough | 4/27/2022 | Approved | JOHN HAYES |
| PLUMBING-Rough | 4/27/2022 | Approved | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2022 | Approved | JOHN HAYES |
| Insulation | 5/2/2022 | Corrections Issued | JOHN HAYES |
| Interior/Exterior Lathing | 5/2/2022 | Partial Approval | JOHN HAYES |
| Insulation | 5/4/2022 | Approved | JOHN HAYES |
| Drywall Nailing | 5/9/2022 | Partial Approval | JOHN HAYES |
| Interior/Exterior Lathing | 6/7/2022 | Approved | JOHN HAYES |
| Underground Mechanical | 6/7/2022 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 8/24/2022 | Approved | ARAM AVEDISIAN |
| Final | 8/24/2022 | Corrections Issued | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 8/24/2022 | Approved | ARAM AVEDISIAN |
| Green Building Final | 8/24/2022 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 8/24/2022 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 8/24/2022 | SGSOV Approved | ARAM AVEDISIAN |
| Smoke Detectors | 8/24/2022 | Approved | ARAM AVEDISIAN |
| Verify Sprinkler Sign Off | 8/24/2022 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 9/6/2022 | Approved | ARAM AVEDISIAN |
| Final | 9/6/2022 | OK to Issue CofO | ARAM AVEDISIAN |
| HVAC-Final | 9/6/2022 | Approved | ARAM AVEDISIAN |
| PLUMBING-Final | 9/6/2022 | Approved | ARAM AVEDISIAN |
| Service/Power Release | 9/6/2022 | Approved | ARAM AVEDISIAN |