14752 W HARTSOOK ST 91403
Certificate Information: 14752 W HARTSOOK ST 91403
- Application / Permit
- 21010-20000-02430
- Plan Check / Job No.
- B21VN06011
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW (98'-4"x 40'-0") IRR SHAPE ONE-STORY SINGLE FAMILY DWELLING W/ATT. 2- CAR GARAGE, NFPA-13D AUTO FIRE SPRINKLER THROUGHOUT. WORK PER ENGINEER.
- Permit Issued
- Issued on 12/1/2021
- Issuing Office
- Current Status
- CofO Issued on 7/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/17/2021 | TROY DEGUZMAN |
| Corrections Issued | 6/23/2021 | TROY DEGUZMAN |
| Quality Review Completed | 7/7/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 7/9/2021 | APPLICANT |
| Applicant returned to address corrections | 8/11/2021 | TROY DEGUZMAN |
| Applicant returned to address corrections | 11/23/2021 | TROY DEGUZMAN |
| Plan Check Approved | 12/1/2021 | TROY DEGUZMAN |
| Issued | 12/1/2021 | APPLICANT |
| CofO in Progress | 7/14/2022 | JACK KARGODORIAN |
| Permit Finaled | 7/22/2022 | MICHAEL SMITH |
| CofO Issued | 7/22/2022 | MICHAEL SMITH |
| Permit Finaled | 7/22/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 7/13/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 7/14/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 7/14/2021 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 9/12/2021 | ROBERT DUFF |
| Low Impact Development | Cleared | 11/22/2021 | ROGELIO CORTES |
| Green Code | Cleared | 11/23/2021 | TROY DEGUZMAN |
| Roof/Waste drainage to street | Cleared | 11/24/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Builder Hub Inc; Lic. No.: 976592-B | 12501 SHERMAN WAY NORTH HOLLYWOOD, CA 91605 |
| Engineer | Wassef,, Mena Maher Salama; Lic. No.: C84979 | 28131 VALERIO CT VALENCIA, CA 91354 |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/11/2022 | Partial Approval | JACK KARGODORIAN |
| Excavation/Setback/Form/Re-Bar | 1/24/2022 | Corrections Issued | JACK KARGODORIAN |
| Excavation/Setback/Form/Re-Bar | 1/26/2022 | Off-Hour Fees Due | |
| Excavation/Setback/Form/Re-Bar | 1/27/2022 | Approved | JACK KARGODORIAN |
| Footing/Foundation/Slab | 1/27/2022 | Approved | JACK KARGODORIAN |
| Deputy Wood Construction | 2/14/2022 | Partial Approval | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/18/2022 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Rough | 2/28/2022 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 2/28/2022 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 3/1/2022 | Approved | JACK KARGODORIAN |
| Sewer | 3/1/2022 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 3/3/2022 | Corrections Issued | JOHN KIDWELL |
| BUILDING-Rough-Frame | 3/9/2022 | Not Ready for Inspection | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 3/9/2022 | Not Ready for Inspection | ASHLEY THOMPSON |
| Shower Pan | 3/9/2022 | Not Ready for Inspection | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 3/10/2022 | Approved | JACK KARGODORIAN |
| Green Building Rough | 3/10/2022 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 3/10/2022 | Partial Approval | JACK KARGODORIAN |
| Sewer | 3/10/2022 | Approved | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 3/10/2022 | Approved | JACK KARGODORIAN |
| Insulation | 3/15/2022 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 3/15/2022 | Partial Approval | JACK KARGODORIAN |
| Drywall Nailing | 3/22/2022 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Final | 5/25/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Gas Test | 5/25/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| HVAC-Final | 5/26/2022 | Approved | JACK KARGODORIAN |
| PLUMBING-Final | 5/26/2022 | Partial Approval | JACK KARGODORIAN |
| ELECTRICAL-Final | 6/7/2022 | Approved | JACK KARGODORIAN |
| PLUMBING-Final | 6/8/2022 | Corrections Issued | JACK KARGODORIAN |
| PLUMBING-Final | 6/13/2022 | Approved | JACK KARGODORIAN |
| Final | 6/15/2022 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 6/15/2022 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 6/15/2022 | SGSOV Approved | JACK KARGODORIAN |
| Service/Power Release | 6/15/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Smoke Detectors | 6/15/2022 | Approved | JACK KARGODORIAN |
| Final | 7/14/2022 | OK to Issue CofO | JACK KARGODORIAN |
| Service/Power Release | 7/14/2022 | Approved | JACK KARGODORIAN |