12717 N NORRIS AVE 91342
Certificate Information: 12717 N NORRIS AVE 91342
- Application / Permit
- 21010-20000-02418
- Plan Check / Job No.
- B21VN05986
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 27'-9" X 24' ACCESSORY DWELLING UNIT PER CA GOV. STATE CODE 65852.2(e)(1)(B). WORK PER WFPP. “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
- Permit Issued
- Issued on 11/22/2021
- Issuing Office
- Current Status
- CofO Issued on 1/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/21/2021 | ROSENDO MEDINA |
| Corrections Issued | 5/22/2021 | ROSENDO MEDINA |
| Applicant returned to address corrections | 11/4/2021 | ROSENDO MEDINA |
| Issued | 11/22/2021 | APPLICANT |
| Building Plans Picked Up | 11/23/2021 | APPLICANT |
| CofO in Progress | 12/27/2022 | JENNIFER RABUCHIN |
| No Progress | 1/12/2023 | ROBERT GOLD |
| CofO in Progress | 1/12/2023 | ROBERT GOLD |
| Permit Finaled | 1/14/2023 | MICHAEL SMITH |
| CofO Issued | 1/14/2023 | MICHAEL SMITH |
| Permit Finaled | 1/14/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 8/16/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 8/17/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 8/17/2021 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 10/2/2021 | MATTHEW CRAIG |
| Roof/Waste drainage to street | Cleared | 11/9/2021 | AMIR KASHFI |
| Community Plan Implem. Overlay | Cleared | 11/19/2021 | KORA MCNAUGHTON |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/13/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 12/22/2021 | Approved | JENNIFER RABUCHIN |
| Gas Test | 12/22/2021 | Partial Approval | JENNIFER RABUCHIN |
| Underground Mechanical | 2/1/2022 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 2/15/2022 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 2/15/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 2/15/2022 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 2/15/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 2/15/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 2/15/2022 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 2/15/2022 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 2/22/2022 | Partial Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 2/22/2022 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 2/22/2022 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 2/22/2022 | Approved | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 2/22/2022 | Approved | JENNIFER RABUCHIN |
| Insulation | 2/24/2022 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 2/28/2022 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 2/28/2022 | Approved | JENNIFER RABUCHIN |
| Final | 5/10/2022 | Corrections Issued | MICHAEL TEMPLE |
| Green Building Final | 5/10/2022 | Approved | MICHAEL TEMPLE |
| SGSOV-Seismic Gas S/O Valve | 5/10/2022 | SGSOV Approved | MICHAEL TEMPLE |
| Service/Power Release | 5/10/2022 | Corrections Issued | MICHAEL TEMPLE |
| Smoke Detectors | 5/10/2022 | Approved | MICHAEL TEMPLE |
| ELECTRICAL-Final | 6/23/2022 | Approved | JENNIFER RABUCHIN |
| Final | 6/23/2022 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Final | 6/23/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 6/23/2022 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 6/23/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Final | 10/28/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Service/Power Release | 10/28/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Final | 12/27/2022 | OK to Issue CofO | JENNIFER RABUCHIN |
| Service/Power Release | 12/27/2022 | Approved | JENNIFER RABUCHIN |
| Special/Order Compliance | 1/5/2023 | Approved | JENNIFER RABUCHIN |
| Special/Order Compliance | 1/9/2023 | Corrections Issued | ROBERT GOLD |