13130 W LAKE ST 90066
Certificate Information: 13130 W LAKE ST 90066
- Application / Permit
- 21010-20000-02401
- Plan Check / Job No.
- B21VN05938
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- NEW 12'-4" X 16'-7" REC ROOM
- Permit Issued
- Issued on 1/6/2022
- Issuing Office
- Current Status
- CofO Issued on 10/28/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/17/2021 | SELLA BENYAMIN |
| Corrections Issued | 6/24/2021 | SELLA BENYAMIN |
| Quality Review Completed | 7/2/2021 | STEVEN KIM |
| Building Plans Picked Up | 7/29/2021 | APPLICANT |
| Plan Check Approved | 12/7/2021 | SELLA BENYAMIN |
| Issued | 1/6/2022 | APPLICANT |
| CofO in Progress | 10/24/2022 | JESUS RODRIGUEZ |
| Permit Finaled | 10/28/2022 | DANIEL ORRANTE |
| CofO Issued | 10/28/2022 | DANIEL ORRANTE |
| Permit Finaled | 10/28/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 8/10/2021 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 8/10/2021 | ANTHONY MAINEZ |
| ZI | Cleared | 8/10/2021 | PABLO ESTRADA |
| Eng Process Fee Ord 176,300 | Cleared | 8/11/2021 | ANTHONY MAINEZ |
| Low Impact Development | Cleared | 10/5/2021 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 10/7/2021 | ANTHONY MAINEZ |
| Construction near power lines | Cleared | 10/19/2021 | TINA MIRANDA |
| Hydrant and Access approval | Cleared | 11/15/2021 | RUEL COLE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/9/2022 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 2/9/2022 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 2/16/2022 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 2/23/2022 | Partial Approval | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2022 | Partial Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 3/22/2022 | Approved | PATRICK QUALEY |
| BUILDING-Rough-Frame | 3/24/2022 | Conditional Approval | PATRICK QUALEY |
| ELECTRICAL-Rough | 3/24/2022 | Conditional Approval | PATRICK QUALEY |
| Verify Sprinkler Sign Off | 3/24/2022 | Not Ready for Inspection | PATRICK QUALEY |
| Insulation | 4/5/2022 | Approved | PATRICK QUALEY |
| Interior/Exterior Lathing | 4/5/2022 | Approved | PATRICK QUALEY |
| Drywall Nailing | 4/11/2022 | Approved | PATRICK QUALEY |
| ELECTRICAL-Final | 9/20/2022 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 9/20/2022 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 9/23/2022 | Approved | JESUS RODRIGUEZ |
| Final | 9/23/2022 | Corrections Issued | JESUS RODRIGUEZ |
| HVAC-Final | 9/23/2022 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 9/23/2022 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 9/23/2022 | SGSOV Not Ready | JESUS RODRIGUEZ |
| Service/Power Release | 9/23/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Smoke Detectors | 9/23/2022 | Approved | JESUS RODRIGUEZ |
| Verify Sprinkler Sign Off | 9/23/2022 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 9/28/2022 | Approved | JESUS RODRIGUEZ |
| Final | 10/24/2022 | OK to Issue CofO | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 10/24/2022 | SGSOV Approved | JESUS RODRIGUEZ |
| Service/Power Release | 10/24/2022 | Approved | JESUS RODRIGUEZ |