13130 W LAKE ST 90066

Certificate Information: 13130 W LAKE ST 90066

Application / Permit
21010-20000-02400
Plan Check / Job No.
B21VN05938
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 53' X 43'-11" TWO STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 1/6/2022
Issuing Office
Current Status
CofO Issued on 10/28/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/13/2021 APPLICANT
Assigned to Plan Check Engineer 6/17/2021 SELLA BENYAMIN
Corrections Issued 6/24/2021 SELLA BENYAMIN
Quality Review Completed 7/2/2021 STEVEN KIM
Building Plans Picked Up 7/29/2021 APPLICANT
Plan Check Approved 12/7/2021 SELLA BENYAMIN
Issued 1/6/2022 APPLICANT
CofO in Progress 10/25/2022 JESUS RODRIGUEZ
Permit Finaled 10/28/2022 DANIEL ORRANTE
CofO Issued 10/28/2022 DANIEL ORRANTE
Permit Finaled 10/28/2022 DANIEL ORRANTE

Permit Application Clearance Information

Permit Cleared 8/10/2021 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 8/11/2021 ANTHONY MAINEZ
Sewer availability Cleared 8/11/2021 ANTHONY MAINEZ
ZI Cleared 8/16/2021 PABLO ESTRADA
Hydrant and Access approval Cleared 10/2/2021 RUEL COLE
Low Impact Development Cleared 10/5/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 10/7/2021 ANTHONY MAINEZ
Trees in Parkway Cleared 10/30/2021 ADALBERTO VERA

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/9/2022 Approved ENRIQUE MIRELES
Underground Mechanical 2/9/2022 Approved ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 2/16/2022 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 3/9/2022 Partial Approval ANDREW NAVE
BUILDING-Rough-Frame 3/24/2022 Corrections Issued PATRICK QUALEY
ELECTRICAL-Rough 3/24/2022 Approved PATRICK QUALEY
Green Building Rough 3/24/2022 Approved PATRICK QUALEY
HVAC-Rough 3/24/2022 Approved PATRICK QUALEY
PLUMBING-Rough 3/24/2022 Conditional Approval PATRICK QUALEY
Verify Sprinkler Sign Off 3/24/2022 Not Ready for Inspection PATRICK QUALEY
Insulation 4/5/2022 Approved PATRICK QUALEY
Interior/Exterior Lathing 4/5/2022 Approved PATRICK QUALEY
Shower Pan 4/5/2022 Approved PATRICK QUALEY
Drywall Nailing 4/11/2022 Approved PATRICK QUALEY
Gas Test 4/11/2022 Approved PATRICK QUALEY
ELECTRICAL-Final 9/20/2022 Partial Approval JESUS RODRIGUEZ
HVAC-Final 9/20/2022 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 9/23/2022 Approved JESUS RODRIGUEZ
Final 9/23/2022 Corrections Issued JESUS RODRIGUEZ
Green Building Final 9/23/2022 Approved JESUS RODRIGUEZ
PLUMBING-Final 9/23/2022 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 9/23/2022 SGSOV Not Ready JESUS RODRIGUEZ
Service/Power Release 9/23/2022 Not Ready for Inspection JESUS RODRIGUEZ
Smoke Detectors 9/23/2022 Approved JESUS RODRIGUEZ
Verify Sprinkler Sign Off 9/23/2022 Approved JESUS RODRIGUEZ
PLUMBING-Final 9/28/2022 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 9/28/2022 SGSOV Approved JESUS RODRIGUEZ
ELECTRICAL-Final 10/21/2022 Approved JESUS RODRIGUEZ
Final 10/21/2022 Conditional Approval JESUS RODRIGUEZ
Service/Power Release 10/21/2022 Approved JESUS RODRIGUEZ