22653 N BURBANK BLVD 91367

Certificate Information: 22653 N BURBANK BLVD 91367

Application / Permit
21010-20000-02364
Plan Check / Job No.
B21VN05866
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED (24'-0"x 50'-0"), 964 SQFT ADU PER LAMC 12.22 A.33 (c)(d) WORK DONE PER WFPP (TYPE V) SHEETS
Permit Issued
Issued on 5/19/2022
Issuing Office
Current Status
CofO Issued on 1/20/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/13/2021 APPLICANT
Assigned to Plan Check Engineer 6/17/2021 PETER MOSESIAN
Corrections Issued 6/22/2021 PETER MOSESIAN
Quality Review Completed 7/7/2021 OMID HEDAYAT
Building Plans Picked Up 7/9/2021 APPLICANT
Plan Check Approved 4/26/2022 PETER MOSESIAN
Issued 5/19/2022 APPLICANT
CofO in Progress 12/27/2022 TROY SANDERS
Permit Finaled 1/20/2023 JOHN JANSON
CofO Issued 1/20/2023 JOHN JANSON
Permit Finaled 1/20/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 7/15/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 7/31/2021 CARLOS AGUILERA
Sewer availability Cleared 7/31/2021 CARLOS AGUILERA
Grading Pre-Inspection Cleared 8/9/2021 TIMOTHY POWELL
Construction near power lines Cleared 10/20/2021 RIDWAN HARDY
Hydrant and Access approval Cleared 11/29/2021 MATTHEW CRAIG
Low Impact Development Cleared 4/18/2022 TA ANH
Roof/Waste drainage to street Cleared 4/25/2022 CARLOS AGUILERA

Contact Information

Contractor Prime Built Construction; Lic. No.: 948373-B 24942 VISTA VERENDA      WOODLAND HILLS, CA 91367

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/5/2022 Partial Approval TROY SANDERS
Footing/Foundation/Slab 7/13/2022 Approved TROY SANDERS
ELECTRICAL-Rough 8/17/2022 Approved TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 8/17/2022 Partial Approval TROY SANDERS
PLUMBING-Rough 8/17/2022 Approved TROY SANDERS
Shower Pan 8/24/2022 Corrections Issued JESUS PINEDA
BUILDING-Rough-Frame 9/8/2022 Approved TROY SANDERS
Green Building Rough 9/8/2022 Approved TROY SANDERS
Interior/Exterior Lathing 9/8/2022 Partial Approval TROY SANDERS
Shower Pan 9/8/2022 Approved TROY SANDERS
Underground Mechanical 9/8/2022 Approved TROY SANDERS
Verify Sprinkler Sign Off 9/8/2022 Approved TROY SANDERS
Insulation 9/13/2022 Conditional Approval JESUS PINEDA
Interior/Exterior Lathing 9/13/2022 Approved JESUS PINEDA
Drywall Nailing 9/19/2022 Approved JESUS PINEDA
Gas Test 11/14/2022 Approved TROY SANDERS
Service/Power Release 11/14/2022 Not Ready for Inspection TROY SANDERS
Final 12/23/2022 OK to Issue CofO TROY SANDERS
Green Building Final 12/23/2022 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 12/23/2022 SGSOV Approved TROY SANDERS
Service/Power Release 12/23/2022 Approved TROY SANDERS
Smoke Detectors 12/23/2022 Approved TROY SANDERS