550 N HANLEY AVE 90049

Certificate Information: 550 N HANLEY AVE 90049

Application / Permit
21010-20000-02343
Plan Check / Job No.
B21VN05789
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 90'2" X 67'7" TWO STORY SFD WITH HABITABLE BASEMENT AND ATTACHED THREE CAR GARAGE, NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT, ALL WORK PER ENGINEERING
Permit Issued
Issued on 8/18/2021
Issuing Office
Current Status
CofO Issued on 4/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/11/2021 APPLICANT
Assigned to Plan Check Engineer 5/26/2021 RARES BODEA
Corrections Issued 5/29/2021 RARES BODEA
Quality Review Completed 6/8/2021 STEVEN KIM
Building Plans Picked Up 6/11/2021 APPLICANT
Applicant returned to address corrections 7/14/2021 RARES BODEA
Applicant returned to address corrections 8/10/2021 RARES BODEA
Plan Check Approved 8/11/2021 RARES BODEA
Issued 8/18/2021 APPLICANT
CofO in Progress 4/14/2023 KEVIN SARGSYAN
Permit Finaled 4/14/2023 DANIEL ORRANTE
CofO Issued 4/14/2023 DANIEL ORRANTE
Permit Finaled 4/14/2023 DANIEL ORRANTE

Permit Application Clearance Information

Trees in Parkway Cleared 6/10/2021 JOHN KIM
Address approval Cleared 6/15/2021 HISASHI KOBAYAKAWA
BHO/Hillside ordinance Cleared 6/15/2021 HISASHI KOBAYAKAWA
BHO/Hillside ordinance Cleared 6/15/2021 HISASHI KOBAYAKAWA
BHO/Hillside ordinance Cleared 6/15/2021 HISASHI KOBAYAKAWA
BHO/Hillside ordinance Cleared 6/15/2021 HISASHI KOBAYAKAWA
BHO/Hillside ordinance Cleared 6/15/2021 HISASHI KOBAYAKAWA
Permit Cleared 6/15/2021 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 6/16/2021 HISASHI KOBAYAKAWA
Sewer availability Cleared 6/16/2021 HISASHI KOBAYAKAWA
Excavation more than 5-ft deep Cleared 7/14/2021 CALOSHA APPROVED
GPI Written Notices Cleared 7/14/2021 RARES BODEA
Grading Pre-Inspection Cleared 7/14/2021 RARES BODEA
Low Impact Development Cleared 7/22/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 7/22/2021 HISASHI KOBAYAKAWA
Distance to fire station Cleared 7/27/2021 MATTHEW CRAIG
Hydrant and Access approval Cleared 7/27/2021 MATTHEW CRAIG

Contact Information

Architect Ungar,, Kenneth Joel; Lic. No.: C21777 1173 WESTBEND ROAD      WESTLAKE VILLAGE, CA 91362
Contractor Owner-Builder       ,
Engineer Lin,, Chi Hsin; Lic. No.: GE2921 1722 CEDAR STREET APT G      ALHAMBRA, CA 91801
Geologist Kruger,, Mark Otto; Lic. No.: EG2345 10120 NATIONAL BLVD      LOS ANGELES, CA 90034

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/19/2021 Approved JUAN VALENZUELA
Footing/Foundation/Slab 10/18/2021 Partial Approval JUAN VALENZUELA
Underground Mechanical 10/19/2021 Partial Approval JUAN VALENZUELA
Footing/Foundation/Slab 11/10/2021 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 12/2/2021 Partial Approval JUAN VALENZUELA
Deputy Steel/Welding 1/5/2022 No Result Entered DANNY TOLENTINO
Floor/Roof Diaphrgm/Shear Wall 1/10/2022 Partial Approval JUAN VALENZUELA
Footing/Foundation/Slab 1/11/2022 Partial Approval JUAN VALENZUELA
Footing/Foundation/Slab 1/26/2022 Partial Approval JUAN VALENZUELA
Footing/Foundation/Slab 2/2/2022 Approved JUAN VALENZUELA
Deputy Reinf. Concrete 2/3/2022 No Result Entered DANNY TOLENTINO
Floor/Roof Diaphrgm/Shear Wall 2/9/2022 Partial Approval JUAN VALENZUELA
Deputy Wood Construction 3/18/2022 Approved JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 3/18/2022 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 4/27/2022 Corrections Issued JUAN VALENZUELA
Pre-Inspection 4/29/2022 Partial Inspection JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 5/9/2022 Partial Approval JUAN VALENZUELA
PLUMBING-Rough 5/9/2022 Approved JUAN VALENZUELA
HVAC-Rough 5/25/2022 Corrections Issued JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 5/26/2022 Corrections Issued CARLOS MATAMOROS
ELECTRICAL-Rough 5/31/2022 Approved JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 5/31/2022 Partial Approval JUAN VALENZUELA
Deputy Wood Construction 6/1/2022 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 6/2/2022 Approved JUAN VALENZUELA
HVAC-Rough 6/2/2022 Approved JUAN VALENZUELA
BUILDING-Rough-Frame 6/8/2022 Approved JUAN VALENZUELA
Green Building Rough 6/8/2022 Not Ready for Inspection JUAN VALENZUELA
Verify Sprinkler Sign Off 6/8/2022 Approved JUAN VALENZUELA
Interior/Exterior Lathing 6/16/2022 Partial Approval JUAN VALENZUELA
Green Building Rough 6/22/2022 Approved JUAN VALENZUELA
Insulation 6/22/2022 Approved JUAN VALENZUELA
Drywall Nailing 7/1/2022 Approved JUAN VALENZUELA
Shower Pan 7/28/2022 Approved ANDREW NAVE
Underground Mechanical 10/7/2022 Partial Approval JUAN VALENZUELA
Underground Mechanical 11/4/2022 Corrections Issued CLAYTON GRAHAM
Underground Mechanical 11/9/2022 Partial Approval JUAN VALENZUELA
Gas Test 3/24/2023 Approved KEVIN SARGSYAN
PLUMBING-Final 3/24/2023 Approved KEVIN SARGSYAN
HVAC-Final 3/28/2023 Not Ready for Inspection KEVIN SARGSYAN
ELECTRICAL-Final 3/29/2023 Not Ready for Inspection KEVIN SARGSYAN
HVAC-Final 4/3/2023 Approved KEVIN SARGSYAN
ELECTRICAL-Final 4/5/2023 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Final 4/11/2023 Approved KEVIN SARGSYAN
Final 4/13/2023 OK to Issue CofO KEVIN SARGSYAN
Green Building Final 4/13/2023 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 4/13/2023 SGSOV Approved KEVIN SARGSYAN
Service/Power Release 4/13/2023 Approved KEVIN SARGSYAN
Smoke Detectors 4/13/2023 Approved KEVIN SARGSYAN