5550 N WOODLAKE AVE 91367

Certificate Information: 5550 N WOODLAKE AVE 91367

Application / Permit
21010-20000-02337
Plan Check / Job No.
B21VN05764
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ADU PER ORDINANCE ( 1-STORY)
Permit Issued
Issued on 11/10/2021
Issuing Office
Current Status
CofO Issued on 10/19/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/12/2021 APPLICANT
Assigned to Plan Check Engineer 6/17/2021 CARLOS MONTES
Corrections Issued 6/25/2021 CARLOS MONTES
Quality Review Completed 7/1/2021 WING SUEN
Plan Check Approved 11/2/2021 CARLOS MONTES
Issued 11/10/2021 APPLICANT
CofO in Progress 10/18/2022 TROY SANDERS
Permit Finaled 10/19/2022 JOHN JANSON
CofO Issued 10/19/2022 JOHN JANSON
Permit Finaled 10/19/2022 JOHN JANSON

Permit Application Clearance Information

Grading Pre-Inspection Cleared 7/26/2021 TIMOTHY POWELL
Address approval Cleared 8/10/2021 GABRIEL ROBLES
Watercourse Cleared 8/10/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 8/11/2021 GABRIEL ROBLES
Sewer availability Cleared 8/11/2021 GABRIEL ROBLES
Hydrant and Access approval Cleared 10/1/2021 KURT CORRAL
Low Impact Development Cleared 10/15/2021 KHAING AYE
Roof/Waste drainage to street Cleared 10/21/2021 GABRIEL ROBLES
GPI Written Notices Cleared 11/2/2021 CARLOS MONTES

Contact Information

Contractor Master Plan Construction Inc; Lic. No.: 1027598-B 17797 RIDGEWAY ROAD      GRANADA HILLS, CA 91344
Engineer Hernandez,, Gerardo; Lic. No.: C78115 1426 E STUART AVE      WEST COVINA, CA 91791
Engineer Hernandez,, Gerardo; Lic. No.: NA78115       ,

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/1/2021 Partial Approval TROY SANDERS
Excavation/Setback/Form/Re-Bar 12/9/2021 Approved TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 1/24/2022 Partial Approval STEVEN BACK
HVAC-Rough 1/24/2022 Corrections Issued STEVEN BACK
PLUMBING-Rough 2/3/2022 Approved TROY SANDERS
ELECTRICAL-Rough 2/15/2022 Approved TROY SANDERS
HVAC-Rough 2/15/2022 Approved TROY SANDERS
Shower Pan 2/28/2022 Approved TROY SANDERS
Interior/Exterior Lathing 4/26/2022 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 5/6/2022 Approved TROY SANDERS
Green Building Rough 5/6/2022 Approved TROY SANDERS
Interior/Exterior Lathing 5/6/2022 Approved TROY SANDERS
Verify Sprinkler Sign Off 5/6/2022 Approved TROY SANDERS
Insulation 5/16/2022 Approved JESUS PINEDA
Drywall Nailing 5/23/2022 Approved JESUS PINEDA
Gas Test 7/29/2022 No Access for Inspection PETER FOLLING
PLUMBING-Final 7/29/2022 No Access for Inspection PETER FOLLING
ELECTRICAL-Final 8/9/2022 Approved TROY SANDERS
Gas Test 8/9/2022 Approved TROY SANDERS
HVAC-Final 8/9/2022 Approved TROY SANDERS
PLUMBING-Final 8/9/2022 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 8/9/2022 SGSOV Approved TROY SANDERS
Service/Power Release 8/9/2022 Not Ready for Inspection TROY SANDERS
Smoke Detectors 8/9/2022 Approved TROY SANDERS
Service/Power Release 8/17/2022 Approved TROY SANDERS
Final 10/4/2022 Not Ready for Inspection TROY SANDERS
Footing/Foundation/Slab 10/4/2022 Approved TROY SANDERS
Gas Test 10/4/2022 Approved TROY SANDERS
Green Building Final 10/4/2022 Approved TROY SANDERS
Interior/Exterior Lathing 10/4/2022 Approved TROY SANDERS
PLUMBING-Final 10/4/2022 Approved TROY SANDERS
Verify Rec and Parks Fee Memo 10/4/2022 Approved TROY SANDERS
Final 10/17/2022 OK to Issue CofO TROY SANDERS