21206 W DE LA OSA ST 91364
Certificate Information: 21206 W DE LA OSA ST 91364
- Application / Permit
- 21010-20000-02336
- Plan Check / Job No.
- B21VN05763
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan new ADU. Proposed 24 ft x 25 ft detached 2-story Accessory Dwelling Unit per ordinance.
- Permit Issued
- Issued on 11/26/2021
- Issuing Office
- Current Status
- CofO Issued on 11/2/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/17/2021 | MICHAEL LOPEZ |
| Corrections Issued | 6/28/2021 | MICHAEL LOPEZ |
| Quality Review Completed | 7/7/2021 | WING SUEN |
| Applicant returned to address corrections | 11/10/2021 | MICHAEL LOPEZ |
| Plan Check Approved | 11/10/2021 | MICHAEL LOPEZ |
| Issued | 11/26/2021 | APPLICANT |
| CofO in Progress | 10/6/2022 | DAVID SANDOVAL |
| Permit Finaled | 11/2/2022 | JOHN JANSON |
| CofO Issued | 11/2/2022 | JOHN JANSON |
| Permit Finaled | 11/2/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 7/16/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 7/16/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 7/16/2021 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 9/9/2021 | RUEL COLE |
| Low Impact Development | Cleared | 10/8/2021 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 10/12/2021 | ABDULLAH SADOZAI |
| GPI Written Notices | Cleared | 11/10/2021 | ALEXANDER ANDREWS |
| Grading Pre-Inspection | Cleared | 11/10/2021 | ALEXANDER ANDREWS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/13/2022 | Partial Approval | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 1/18/2022 | Approved | PETER FOLLING |
| Footing/Foundation/Slab | 1/18/2022 | Approved | PETER FOLLING |
| BUILDING-Rough-Frame | 1/27/2022 | Partial Approval | PETER FOLLING |
| Green Building Rough | 1/27/2022 | Not Ready for Inspection | PETER FOLLING |
| Verify Sprinkler Sign Off | 1/27/2022 | Not Ready for Inspection | PETER FOLLING |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2022 | Approved | PETER FOLLING |
| Deputy Drilled-In Anchors | 2/14/2022 | No Access for Inspection | PETER FOLLING |
| ELECTRICAL-Rough | 2/28/2022 | Approved | PETER FOLLING |
| HVAC-Rough | 2/28/2022 | Approved | PETER FOLLING |
| PLUMBING-Rough | 2/28/2022 | Approved | PETER FOLLING |
| Underground Mechanical | 2/28/2022 | Approved | PETER FOLLING |
| BUILDING-Rough-Frame | 3/25/2022 | Approved | PETER FOLLING |
| Green Building Rough | 3/25/2022 | Approved | PETER FOLLING |
| Interior/Exterior Lathing | 3/25/2022 | Approved | PETER FOLLING |
| Shower Pan | 3/25/2022 | Approved | PETER FOLLING |
| Verify Sprinkler Sign Off | 3/25/2022 | Approved | PETER FOLLING |
| Insulation | 3/31/2022 | Approved | PETER FOLLING |
| Drywall Nailing | 4/6/2022 | Approved | MORRIS JACKSON |
| Sewer | 5/13/2022 | Approved | PETER FOLLING |
| ELECTRICAL-Final | 8/3/2022 | Corrections Issued | DAVID SANDOVAL |
| HVAC-Final | 8/3/2022 | Corrections Issued | DAVID SANDOVAL |
| PLUMBING-Final | 8/3/2022 | Approved | DAVID SANDOVAL |
| ELECTRICAL-Final | 8/17/2022 | Not Ready for Inspection | PETER FOLLING |
| Final | 8/17/2022 | Corrections Issued | PETER FOLLING |
| Green Building Final | 8/17/2022 | Approved | PETER FOLLING |
| HVAC-Final | 8/17/2022 | Not Ready for Inspection | PETER FOLLING |
| PLUMBING-Final | 8/17/2022 | Approved | PETER FOLLING |
| SGSOV-Seismic Gas S/O Valve | 8/17/2022 | SGSOV Approved | PETER FOLLING |
| Service/Power Release | 8/17/2022 | Not Ready for Inspection | PETER FOLLING |
| Smoke Detectors | 8/17/2022 | Approved | PETER FOLLING |
| ELECTRICAL-Final | 9/7/2022 | Approved | PETER FOLLING |
| Final | 9/7/2022 | Not Ready for Inspection | PETER FOLLING |
| HVAC-Final | 9/7/2022 | Approved | PETER FOLLING |
| PLUMBING-Final | 9/7/2022 | Approved | PETER FOLLING |
| Service/Power Release | 9/7/2022 | Not Ready for Inspection | PETER FOLLING |
| Final | 10/5/2022 | OK to Issue CofO | DAVID SANDOVAL |
| Service/Power Release | 10/5/2022 | Approved | DAVID SANDOVAL |