9318 N ENCINO AVE 91325

Certificate Information: 9318 N ENCINO AVE 91325

Application / Permit
21010-20000-02308
Plan Check / Job No.
B21VN05685
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 24' X 22'11" TWO STORY DETACHED ACCESSORY DWELLING UNIT AS PER LAMC 12.22.A.33 (C) AND (D), ALL WORK PER ENGINEERING The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy. - SEE COMMENTS
Permit Issued
Issued on 12/29/2021
Issuing Office
Current Status
CofO Issued on 4/18/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/7/2021 APPLICANT
Assigned to Plan Check Engineer 6/10/2021 RARES BODEA
Corrections Issued 6/17/2021 RARES BODEA
Quality Review Completed 6/24/2021 STEVEN KIM
Building Plans Picked Up 6/25/2021 APPLICANT
Applicant returned to address corrections 12/7/2021 RARES BODEA
Plan Check Approved 12/13/2021 RARES BODEA
Issued 12/29/2021 APPLICANT
CofO in Progress 4/15/2024 JAVIER RAMOS JR
Permit Finaled 4/18/2024 RUBEN SALAS
CofO Issued 4/18/2024 RUBEN SALAS
Permit Finaled 4/18/2024 RUBEN SALAS

Permit Application Clearance Information

Hold Cleared 6/15/2021 JASON SHEETS
Address approval Cleared 7/14/2021 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 7/19/2021 MARKOS PEREZ-BRAN
Sewer availability Cleared 7/19/2021 MARKOS PEREZ-BRAN
Hydrant and Access approval Cleared 10/12/2021 MATTHEW CRAIG
Roof/Waste drainage to street Cleared 12/9/2021 MARKOS PEREZ-BRAN

Contact Information

Contractor Owner-Builder       ,
Engineer Adams,, Robert Charles; Lic. No.: C21234 22129 BRYANT STREET      CANOGA PARK, CA 91304

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/18/2022 Approved JAVIER RAMOS JR
Footing/Foundation/Slab 10/27/2022 Approved JAVIER RAMOS JR
Insulation 10/27/2022 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 10/27/2022 Partial Approval JAVIER RAMOS JR
Wood Frame 10/27/2022 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 11/3/2022 Not Ready for Inspection JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 11/3/2022 Partial Approval JAVIER RAMOS JR
Green Building Rough 11/3/2022 Not Ready for Inspection JAVIER RAMOS JR
Verify Sprinkler Sign Off 11/3/2022 Approved JAVIER RAMOS JR
Wood Frame 11/3/2022 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 12/8/2022 Not Ready for Inspection JAVIER RAMOS JR
ELECTRICAL-Rough 12/8/2022 Corrections Issued JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 12/8/2022 Corrections Issued JAVIER RAMOS JR
Green Building Rough 12/8/2022 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Rough 12/8/2022 Approved JAVIER RAMOS JR
PLUMBING-Rough 12/8/2022 Approved JAVIER RAMOS JR
Wood Frame 12/8/2022 Corrections Issued JAVIER RAMOS JR
ELECTRICAL-Rough 12/15/2022 Approved JAVIER RAMOS JR
Insulation 12/15/2022 Corrections Issued JAVIER RAMOS JR
Interior/Exterior Lathing 12/15/2022 Partial Approval JAVIER RAMOS JR
Drywall Nailing 12/30/2022 Not Ready for Inspection JAVIER RAMOS JR
Green Building Rough 12/30/2022 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 2/7/2023 Partial Approval JAVIER RAMOS JR
Sewer 2/7/2023 Approved JAVIER RAMOS JR
Shower Pan 2/7/2023 Approved JAVIER RAMOS JR
Underground Mechanical 2/7/2023 Partial Approval JAVIER RAMOS JR
Special/Order Compliance 5/15/2023 Corrections Issued ARAM AVEDISIAN
Underground Mechanical 5/15/2023 Partial Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 6/14/2023 Not Ready for Inspection JAVIER RAMOS JR
Drywall Nailing 6/14/2023 Not Ready for Inspection JAVIER RAMOS JR
ELECTRICAL-Final 6/14/2023 Approved JAVIER RAMOS JR
Final 6/14/2023 Corrections Issued JAVIER RAMOS JR
Green Building Final 6/14/2023 Approved JAVIER RAMOS JR
HVAC-Final 6/14/2023 Approved JAVIER RAMOS JR
PLUMBING-Final 6/14/2023 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 6/14/2023 SGSOV Approved JAVIER RAMOS JR
Service/Power Release 6/14/2023 Not Ready for Inspection JAVIER RAMOS JR
Smoke Detectors 6/14/2023 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 8/1/2023 Approved JAVIER RAMOS JR
Drywall Nailing 8/1/2023 Approved JAVIER RAMOS JR
ELECTRICAL-Final 8/1/2023 Approved JAVIER RAMOS JR
Final 8/1/2023 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Final 8/1/2023 Approved JAVIER RAMOS JR
PLUMBING-Final 8/1/2023 Approved JAVIER RAMOS JR
Service/Power Release 8/1/2023 Not Ready for Inspection JAVIER RAMOS JR
Final 11/29/2023 Corrections Issued JAVIER RAMOS JR
Service/Power Release 11/29/2023 Not Ready for Inspection JAVIER RAMOS JR
Final 1/11/2024 OK to Issue CofO JAVIER RAMOS JR