8142 1/2 W 4TH ST 90048

Certificate Information: 8142 1/2 W 4TH ST 90048

Application / Permit
21010-20000-02304
Plan Check / Job No.
B21VN05662
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW IRR. SHAPED 28'-0" x 34'-6" ONE-STORY DET. ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d); ALL WORK PER ENGINEERING DESIGN
Permit Issued
Issued on 1/7/2022
Issuing Office
Current Status
CofO Issued on 1/20/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/7/2021 APPLICANT
Assigned to Plan Check Engineer 5/20/2021 SEAN SHAHMIRI
Corrections Issued 5/22/2021 SEAN SHAHMIRI
Quality Review Completed 5/25/2021 OMID HEDAYAT
Building Plans Picked Up 6/1/2021 APPLICANT
Plan Check Approved 9/21/2021 SEAN SHAHMIRI
Issued 1/7/2022 APPLICANT
CofO in Progress 1/5/2023 MICHAEL PELHAM
Permit Finaled 1/20/2023 DANIEL ORRANTE
CofO Issued 1/20/2023 DANIEL ORRANTE
Permit Finaled 1/20/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 6/9/2021 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 6/10/2021 THOMAS LANG
Sewer availability Cleared 6/10/2021 THOMAS LANG
Construction near power lines Cleared 6/29/2021 RIDWAN HARDY
Construction within easement Cleared 6/29/2021 RIDWAN HARDY
Low Impact Development Cleared 8/5/2021 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 8/11/2021 RENZ SORIANO
Hydrant and Access approval Cleared 9/11/2021 MATTHEW CRAIG

Contact Information

Contractor Af Construction Inc; Lic. No.: 942352-B 4231 JUBILO DRIVE      TARZANA, CA 91356
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/26/2022 Partial Approval EVAN COOPER
Footing/Foundation/Slab 5/6/2022 Partial Approval EVAN COOPER
METHANE-Barrier 5/6/2022 Not Ready for Inspection EVAN COOPER
METHANE-Subgrade 5/6/2022 Approved EVAN COOPER
Footing/Foundation/Slab 5/26/2022 Approved EVAN COOPER
METHANE-Barrier 5/26/2022 Approved EVAN COOPER
Deputy Wood Construction 6/24/2022 No Access for Inspection KENNETH NAGLE
Wood Frame 6/27/2022 Corrections Issued EVAN COOPER
PLUMBING-Rough 7/7/2022 Not Ready for Inspection EVAN COOPER
Gas Test 7/12/2022 Partial Approval EVAN COOPER
PLUMBING-Rough 7/12/2022 Approved EVAN COOPER
HVAC-Rough 7/13/2022 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Rough 7/14/2022 Approved OGANES TARAKHCHYAN
HVAC-Rough 7/14/2022 Approved OGANES TARAKHCHYAN
Insulation 7/20/2022 Corrections Issued EVAN COOPER
Wood Frame 7/20/2022 Not Ready for Inspection EVAN COOPER
Shower Pan 7/21/2022 Approved GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 7/25/2022 Approved EVAN COOPER
Green Building Rough 7/25/2022 Approved EVAN COOPER
Insulation 7/25/2022 Approved EVAN COOPER
Interior/Exterior Lathing 7/25/2022 Partial Approval EVAN COOPER
METHANE-Rough 7/25/2022 Approved EVAN COOPER
Verify Sprinkler Sign Off 7/25/2022 Approved EVAN COOPER
Interior/Exterior Lathing 7/29/2022 Approved EVAN COOPER
Drywall Nailing 8/2/2022 Approved EVAN COOPER
Underground Mechanical 9/26/2022 Partial Approval EVAN COOPER
Final 11/28/2022 Corrections Issued EVAN COOPER
Gas Test 11/28/2022 Not Ready for Inspection EVAN COOPER
Green Building Final 11/28/2022 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 11/28/2022 SGSOV Not Ready EVAN COOPER
Service/Power Release 11/28/2022 Not Ready for Inspection EVAN COOPER
Smoke Detectors 11/28/2022 Approved EVAN COOPER
Gas Test 11/29/2022 Not Ready for Inspection EVAN COOPER
Special/Order Compliance 11/29/2022 Partial Inspection JEREMY TODD
Gas Test 12/7/2022 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 12/7/2022 SGSOV Not Ready OGANES TARAKHCHYAN
Final 1/3/2023 OK to Issue CofO JEREMY TODD
SGSOV-Seismic Gas S/O Valve 1/3/2023 SGSOV Approved JEREMY TODD
Service/Power Release 1/3/2023 Approved JEREMY TODD