9676 N RINCON AVE 91331
Certificate Information: 9676 N RINCON AVE 91331
- Application / Permit
- 21010-20000-02293
- Plan Check / Job No.
- B21VN05624
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 20' X 30' (2) STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 10/22/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/29/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/10/2021 | SELLA BENYAMIN |
| Corrections Issued | 6/17/2021 | SELLA BENYAMIN |
| Quality Review Completed | 6/24/2021 | STEVEN KIM |
| Plan Check Approved | 10/15/2021 | SELLA BENYAMIN |
| Issued | 10/22/2021 | APPLICANT |
| CofO in Progress | 3/10/2023 | MICHEL ABAJAN |
| Permit Finaled | 3/29/2023 | MICHAEL SMITH |
| CofO Issued | 3/29/2023 | MICHAEL SMITH |
| Permit Finaled | 3/29/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 7/1/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 7/12/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 7/12/2021 | GABRIEL ROBLES |
| Low Impact Development | Cleared | 9/2/2021 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 9/7/2021 | GABRIEL ROBLES |
| Construction near power lines | Cleared | 9/22/2021 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 10/1/2021 | JOHN CONNEALLY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/6/2022 | Corrections Issued | MICHEL ABAJAN |
| PLUMBING-Rough | 5/13/2022 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 5/27/2022 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/8/2022 | Partial Approval | JENNIFER RABUCHIN |
| Wood Frame | 6/8/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2022 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 8/4/2022 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 8/4/2022 | Approved | MICHEL ABAJAN |
| Green Building Rough | 8/4/2022 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 8/4/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 8/4/2022 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 8/4/2022 | Approved | MICHEL ABAJAN |
| Wood Frame | 8/4/2022 | Partial Inspection | MICHEL ABAJAN |
| Insulation | 8/23/2022 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 8/23/2022 | Partial Approval | JENNIFER RABUCHIN |
| Drywall Nailing | 8/31/2022 | Approved | MICHEL ABAJAN |
| Shower Pan | 8/31/2022 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 1/12/2023 | Approved | MICHEL ABAJAN |
| Final | 1/12/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| Green Building Final | 1/12/2023 | Approved | MICHEL ABAJAN |
| HVAC-Final | 1/12/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 1/12/2023 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 1/12/2023 | SGSOV Not Ready | MICHEL ABAJAN |
| Service/Power Release | 1/12/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 1/12/2023 | Approved | MICHEL ABAJAN |
| Final | 3/10/2023 | OK to Issue CofO | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 3/10/2023 | SGSOV Approved | MICHEL ABAJAN |
| Service/Power Release | 3/10/2023 | Approved | MICHEL ABAJAN |