4150 N RHODES AVE 91604
Certificate Information: 4150 N RHODES AVE 91604
- Application / Permit
- 21010-20000-02292
- Plan Check / Job No.
- B21VN05623
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- NEW 12' x 18' REC. ROOM WITH 7' X 18' ATTACHED TRELLIS
- Permit Issued
- Issued on 8/20/2021
- Issuing Office
- Current Status
- CofO Issued on 8/1/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/13/2021 | SELLA BENYAMIN |
| Corrections Issued | 5/17/2021 | SELLA BENYAMIN |
| Quality Review Completed | 5/20/2021 | STEVEN KIM |
| Building Plans Picked Up | 6/1/2021 | APPLICANT |
| Issued | 8/20/2021 | APPLICANT |
| Plan Check Approved | 8/21/2021 | SELLA BENYAMIN |
| CofO in Progress | 6/30/2022 | CHRISTOPHE COCHRAN |
| Permit Finaled | 8/1/2022 | DANIEL ORRANTE |
| CofO Issued | 8/1/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/1/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/15/2021 | GABRIEL ROBLES |
| Low Impact Development | Cleared | 7/30/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 7/31/2021 | ABDULLAH SADOZAI |
| Construction near power lines | Cleared | 8/6/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Wang,, Hongyu; Lic. No.: C72679 | 8887 W FALMINGO RD STE 101 LAS VEGAS, NV 89147 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/1/2021 | Not Ready for Inspection | ARAM AVEDISIAN |
| Underground Mechanical | 9/1/2021 | Not Ready for Inspection | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 9/2/2021 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 9/2/2021 | Partial Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 9/8/2021 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/17/2021 | Not Ready for Inspection | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2021 | Not Ready for Inspection | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/19/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 10/19/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 10/19/2021 | Approved | JENNIFER RABUCHIN |
| Wood Frame | 10/19/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 10/22/2021 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 11/8/2021 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 11/16/2021 | Approved | ARAM AVEDISIAN |
| Shower Pan | 11/16/2021 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 11/23/2021 | Partial Approval | MICHAEL TEMPLE |
| Green Building Rough | 11/23/2021 | Not Ready for Inspection | MICHAEL TEMPLE |
| Wood Frame | 11/23/2021 | Partial Approval | MICHAEL TEMPLE |
| Insulation | 11/29/2021 | Not Ready for Inspection | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 11/30/2021 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 11/30/2021 | Approved | ARAM AVEDISIAN |
| Insulation | 12/6/2021 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 12/6/2021 | Partial Approval | ARAM AVEDISIAN |
| Drywall Nailing | 12/13/2021 | Approved | ASHLEY THOMPSON |
| Final | 5/24/2022 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 5/24/2022 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 5/24/2022 | SGSOV Approved | ARAM AVEDISIAN |
| Smoke Detectors | 5/24/2022 | Approved | ARAM AVEDISIAN |
| Final | 6/21/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| Service/Power Release | 6/21/2022 | Approved | CHRISTOPHE COCHRAN |
| Final | 6/30/2022 | OK to Issue CofO | CHRISTOPHE COCHRAN |