4150 N RHODES AVE 91604

Certificate Information: 4150 N RHODES AVE 91604

Application / Permit
21010-20000-02291
Plan Check / Job No.
B21VN05623
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 35'-6" X 64'-9" (2) STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 8/20/2021
Issuing Office
Current Status
CofO Issued on 8/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/7/2021 APPLICANT
Assigned to Plan Check Engineer 5/13/2021 SELLA BENYAMIN
Corrections Issued 5/17/2021 SELLA BENYAMIN
Quality Review Completed 5/20/2021 STEVEN KIM
Building Plans Picked Up 6/1/2021 APPLICANT
Issued 8/20/2021 APPLICANT
Plan Check Approved 8/21/2021 SELLA BENYAMIN
CofO in Progress 6/30/2022 CHRISTOPHE COCHRAN
CofO in Progress 7/14/2022 CHRISTOPHE COCHRAN
CofO Issued 8/1/2022 DANIEL ORRANTE
Permit Finaled 8/1/2022 DANIEL ORRANTE

Permit Application Clearance Information

Permit Cleared 6/10/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 6/11/2021 GABRIEL ROBLES
Sewer availability Cleared 6/11/2021 GABRIEL ROBLES
Hydrant and Access approval Cleared 7/16/2021 KURT CORRAL
Trees in Parkway Cleared 7/29/2021 JOHN KIM
Low Impact Development Cleared 7/30/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 7/31/2021 ABDULLAH SADOZAI

Contact Information

Contractor Owner-Builder       ,
Engineer Wang,, Hongyu; Lic. No.: C72679 8887 W FALMINGO RD STE 101      LAS VEGAS, NV 89147

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/1/2021 Not Ready for Inspection ARAM AVEDISIAN
Underground Mechanical 9/1/2021 Not Ready for Inspection ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 9/2/2021 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 9/2/2021 Partial Approval ARAM AVEDISIAN
Sewer 9/2/2021 Approved ARAM AVEDISIAN
Footing/Foundation/Slab 9/8/2021 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 9/17/2021 Corrections Issued ARAM AVEDISIAN
Special/Order Compliance 9/17/2021 Partial Inspection ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 9/20/2021 Partial Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 10/19/2021 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 10/19/2021 Not Ready for Inspection JENNIFER RABUCHIN
Verify Sprinkler Sign Off 10/19/2021 Not Ready for Inspection JENNIFER RABUCHIN
Wood Frame 10/19/2021 Not Ready for Inspection JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 10/22/2021 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 11/8/2021 Approved ARAM AVEDISIAN
HVAC-Rough 11/10/2021 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 11/16/2021 Approved ARAM AVEDISIAN
Shower Pan 11/16/2021 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 11/23/2021 Corrections Issued MICHAEL TEMPLE
Green Building Rough 11/23/2021 Not Ready for Inspection MICHAEL TEMPLE
Verify Sprinkler Sign Off 11/23/2021 Not Ready for Inspection MICHAEL TEMPLE
Wood Frame 11/23/2021 Partial Approval MICHAEL TEMPLE
Deputy Wood Construction 11/29/2021 Conditional Approval ARAM AVEDISIAN
Insulation 11/29/2021 Not Ready for Inspection ARAM AVEDISIAN
BUILDING-Rough-Frame 11/30/2021 Approved ARAM AVEDISIAN
Green Building Rough 11/30/2021 Approved ARAM AVEDISIAN
Verify Sprinkler Sign Off 11/30/2021 Approved ARAM AVEDISIAN
Insulation 12/6/2021 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 12/6/2021 Partial Approval ARAM AVEDISIAN
Drywall Nailing 12/13/2021 Approved ASHLEY THOMPSON
Gas Test 1/7/2022 Conditional Approval THOMAS FINNILA
Gas Test 3/4/2022 Approved ARAM AVEDISIAN
Final 5/24/2022 Corrections Issued ARAM AVEDISIAN
Green Building Final 5/24/2022 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 5/24/2022 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 5/24/2022 Approved ARAM AVEDISIAN
Final 6/21/2022 Corrections Issued CHRISTOPHE COCHRAN
Service/Power Release 6/21/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Final 6/30/2022 OK to Issue CofO CHRISTOPHE COCHRAN
Service/Power Release 6/30/2022 Approved CHRISTOPHE COCHRAN
Final 7/14/2022 OK to Issue CofO CHRISTOPHE COCHRAN
Gas Test 7/19/2022 Approved CHRISTOPHE COCHRAN