Pre-Inspection
|
10/6/2022
|
No Access for Inspection
|
JOHN KITCKO
|
|
Pre-Inspection
|
10/12/2022
|
Approved
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
11/17/2022
|
Partial Inspection
|
JOHN KITCKO
|
|
Piling/Pier/Caisson
|
12/1/2022
|
Partial Inspection
|
JOHN KITCKO
|
|
Footing/Foundation/Slab
|
1/13/2023
|
Partial Inspection
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
1/26/2023
|
No Access for Inspection
|
JOHN KITCKO
|
|
Footing/Foundation/Slab
|
2/17/2023
|
Partial Inspection
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
2/22/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
3/9/2023
|
Partial Approval
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
3/16/2023
|
Partial Approval
|
JOHN KITCKO
|
|
Pre-Inspection
|
3/16/2023
|
Partial Inspection
|
JOHN KITCKO
|
|
Special/Order Compliance
|
3/16/2023
|
Partial Approval
|
STEVEN LEVITT
|
|
Excavation/Setback/Form/Re-Bar
|
4/14/2023
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
4/18/2023
|
Conditional Approval
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
4/25/2023
|
Partial Approval
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
5/9/2023
|
Partial Approval
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
6/12/2023
|
Partial Approval
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
6/22/2023
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
6/23/2023
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
6/27/2023
|
Partial Approval
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
7/24/2023
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
7/25/2023
|
Partial Approval
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
7/27/2023
|
Conditional Approval
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
7/28/2023
|
Conditional Approval
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
9/11/2023
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
9/12/2023
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Footing/Foundation/Slab
|
9/19/2023
|
Corrections Issued
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
9/20/2023
|
Partial Approval
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
9/21/2023
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Deputy Reinf. Concrete
|
9/22/2023
|
Conditional Approval
|
JOHN KITCKO
|
|
Footing/Foundation/Slab
|
9/22/2023
|
Partial Approval
|
JOHN KITCKO
|
|
Green Building Rough
|
9/22/2023
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Reinforced Concrete Frame
|
9/22/2023
|
Partial Approval
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
9/22/2023
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
10/5/2023
|
Partial Approval
|
JOHN KITCKO
|
|
Green Building Rough
|
10/18/2023
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
10/18/2023
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
10/18/2023
|
Corrections Issued
|
JOHN KITCKO
|
|
Green Building Rough
|
10/20/2023
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
10/20/2023
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
10/20/2023
|
Conditional Approval
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
11/7/2023
|
Partial Approval
|
JOHN KITCKO
|
|
Deputy Wood Construction
|
11/13/2023
|
Approved
|
JOHN KITCKO
|
|
Green Building Rough
|
11/13/2023
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
11/13/2023
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
11/13/2023
|
Partial Approval
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
11/20/2023
|
Partial Approval
|
JOHN KITCKO
|
|
Green Building Rough
|
12/4/2023
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
12/4/2023
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
12/4/2023
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Green Building Rough
|
12/6/2023
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
12/6/2023
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
12/6/2023
|
Partial Approval
|
JOHN KITCKO
|
|
Green Building Rough
|
12/11/2023
|
Partial Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
12/11/2023
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
12/11/2023
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
12/14/2023
|
Partial Approval
|
JOHN KITCKO
|
|
Green Building Rough
|
12/19/2023
|
Partial Approval
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
12/19/2023
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
12/19/2023
|
Partial Approval
|
JOHN KITCKO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/22/2024
|
No Access for Inspection
|
JOHN KITCKO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/24/2024
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/25/2024
|
Conditional Approval
|
JOHN KITCKO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/9/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Green Building Rough
|
2/14/2024
|
No Access for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
2/14/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
2/14/2024
|
No Access for Inspection
|
JOHN KITCKO
|
|
Green Building Rough
|
2/23/2024
|
No Access for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
2/23/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
2/23/2024
|
No Access for Inspection
|
JOHN KITCKO
|
|
Green Building Rough
|
2/27/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
2/27/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
2/27/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Green Building Rough
|
3/6/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
3/6/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
3/6/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Special/Order Compliance
|
3/7/2024
|
Corrections Issued
|
JOHN KITCKO
|
|
Green Building Rough
|
3/11/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
3/11/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
3/11/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Special/Order Compliance
|
3/13/2024
|
Partial Inspection
|
JOHN KITCKO
|
|
Green Building Rough
|
3/15/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
3/15/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
3/15/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Green Building Rough
|
3/26/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
3/26/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
3/26/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Green Building Rough
|
3/28/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
3/28/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
3/28/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Green Building Rough
|
4/8/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
4/8/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
4/8/2024
|
Partial Inspection
|
JOHN KITCKO
|
|
Green Building Rough
|
4/11/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
4/11/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
4/11/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Green Building Rough
|
4/19/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
4/19/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
4/19/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Green Building Rough
|
4/25/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
4/25/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
4/25/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Green Building Rough
|
4/30/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
4/30/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
4/30/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Green Building Rough
|
5/3/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
5/3/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
5/3/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Green Building Rough
|
5/8/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
5/8/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
5/8/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Green Building Rough
|
5/28/2024
|
No Access for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
5/28/2024
|
No Access for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
5/28/2024
|
No Access for Inspection
|
JOHN KITCKO
|
|
Green Building Rough
|
6/3/2024
|
Approved
|
ROBERT DAVIS
|
|
Verify Sprinkler Sign Off
|
6/3/2024
|
Approved
|
ROBERT DAVIS
|
|
Wood Frame
|
6/3/2024
|
No Access for Inspection
|
ROBERT DAVIS
|
|
Wood Frame
|
6/6/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
6/12/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Wood Frame
|
7/11/2024
|
Partial Inspection
|
JOHN KITCKO
|
|
Deputy Wood Construction
|
7/17/2024
|
Conditional Approval
|
JOHN KITCKO
|
|
Wood Frame
|
7/17/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Interior/Exterior Lathing
|
7/22/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Deputy Wood Construction
|
7/23/2024
|
Approved
|
JOHN KITCKO
|
|
Wood Frame
|
7/24/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Wood Frame
|
7/31/2024
|
Partial Inspection
|
ANDREW DORSO
|
|
Wood Frame
|
8/6/2024
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Wood Frame
|
8/20/2024
|
Partial Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
9/16/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Wood Frame
|
9/19/2024
|
Conditional Approval
|
JOHN KITCKO
|
|
Special/Order Compliance
|
10/1/2024
|
Partial Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
12/6/2024
|
Partial Approval
|
GREGORY POMISH
|
|
Footing/Foundation/Slab
|
12/20/2024
|
Partial Inspection
|
JOHN KITCKO
|
|
Reinforced Masonry Frame
|
12/20/2024
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Masonry Wall/Backfill
|
12/24/2024
|
Partial Approval
|
GREGORY POMISH
|
|
Deputy Reinf. Masonry
|
12/27/2024
|
Conditional Approval
|
JOHN KITCKO
|
|
Wood Frame
|
2/6/2025
|
Corrections Issued
|
JOHN KITCKO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/12/2025
|
No Access for Inspection
|
JOHN KITCKO
|
|
Interior/Exterior Lathing
|
2/12/2025
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
2/12/2025
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/19/2025
|
Partial Approval
|
JOHN KITCKO
|
|
Wood Frame
|
2/19/2025
|
Partial Approval
|
JOHN KITCKO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/20/2025
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Order to Comply
|
2/20/2025
|
Not Required
|
JOHN KITCKO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/10/2025
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Interior/Exterior Lathing
|
3/10/2025
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
3/10/2025
|
Partial Approval
|
JOHN KITCKO
|
|
Interior/Exterior Lathing
|
4/14/2025
|
Partial Approval
|
ROBERT DAVIS
|
|
Wood Frame
|
4/17/2025
|
Corrections Issued
|
JOHN KITCKO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/9/2025
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Insulation
|
5/9/2025
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
5/9/2025
|
Partial Approval
|
JOHN KITCKO
|
|
Insulation
|
5/16/2025
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Drywall Nailing
|
5/21/2025
|
Partial Approval
|
JOHN KITCKO
|
|
Drywall Nailing
|
5/23/2025
|
Partial Approval
|
JOHN KITCKO
|
|
Insulation
|
5/23/2025
|
Partial Approval
|
JOHN KITCKO
|
|
Drywall Nailing
|
5/28/2025
|
Partial Approval
|
JOHN KITCKO
|
|
Drywall Nailing
|
6/4/2025
|
Partial Approval
|
JOHN KITCKO
|
|
Wood Frame
|
6/11/2025
|
Partial Approval
|
JOHN KITCKO
|
|
Wood Frame
|
6/24/2025
|
Partial Approval
|
JOHN KITCKO
|
|
Insulation
|
8/8/2025
|
Partial Approval
|
JOHN KITCKO
|
|
Insulation
|
8/11/2025
|
Partial Approval
|
JOHN KITCKO
|
|
Drywall Nailing
|
8/15/2025
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Drywall Nailing
|
8/19/2025
|
Partial Approval
|
JOHN KITCKO
|
|
Light Gage Steel Frame
|
9/25/2025
|
Partial Approval
|
JOHN KITCKO
|
|
Wood Frame
|
9/25/2025
|
Partial Approval
|
JOHN KITCKO
|
|
Insulation
|
9/29/2025
|
Partial Inspection
|
ANDREW DORSO
|
|
Drywall Nailing
|
10/8/2025
|
Partial Approval
|
JOHN KITCKO
|
|
Drywall Nailing
|
10/16/2025
|
Partial Approval
|
JOHN KITCKO
|
|
Drywall Nailing
|
10/21/2025
|
Partial Approval
|
JOHN KITCKO
|
|
Light Gage Steel Frame
|
11/17/2025
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Wood Frame
|
11/25/2025
|
Partial Inspection
|
JOHN KITCKO
|
|
Light Gage Steel Frame
|
12/2/2025
|
Partial Approval
|
GREGORY POMISH
|
|
Insulation
|
12/5/2025
|
Partial Approval
|
JOHN KITCKO
|
|
Drywall Nailing
|
12/16/2025
|
Partial Approval
|
JOHN KITCKO
|
|
Special/Order Compliance
|
12/16/2025
|
Partial Approval
|
SCOTT SOBEL
|
|
Drywall Nailing
|
1/2/2026
|
Partial Approval
|
GREGORY POMISH
|
|
Drywall Nailing
|
1/13/2026
|
Partial Approval
|
JOHN KITCKO
|
|
Structural Steel Frame
|
1/15/2026
|
No Access for Inspection
|
JOHN KITCKO
|
|
Special/Order Compliance
|
1/16/2026
|
Partial Inspection
|
JOHN KITCKO
|
|
Special/Order Compliance
|
2/6/2026
|
Partial Inspection
|
DEANDRE HOFFMAN
|
|
Special/Order Compliance
|
3/27/2026
|
Partial Inspection
|
DEANDRE HOFFMAN
|
|
Special/Order Compliance
|
3/31/2026
|
Partial Approval
|
DEANDRE HOFFMAN
|
|
Special/Order Compliance
|
4/22/2026
|
Partial Inspection
|
DEANDRE HOFFMAN
|
|
Special/Order Compliance
|
4/24/2026
|
Partial Inspection
|
DEANDRE HOFFMAN
|
|
Special/Order Compliance
|
4/29/2026
|
Partial Inspection
|
DEANDRE HOFFMAN
|
|
Special/Order Compliance
|
5/1/2026
|
Partial Inspection
|
DEANDRE HOFFMAN
|
|
Special/Order Compliance
|
5/12/2026
|
Partial Inspection
|
DEANDRE HOFFMAN
|
|
Special/Order Compliance
|
5/15/2026
|
Partial Inspection
|
DEANDRE HOFFMAN
|