6369 N WYNNE AVE 91335

Certificate Information: 6369 N WYNNE AVE 91335

Application / Permit
21010-20000-02288
Plan Check / Job No.
B21VN05611
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 38'-2" X 22'-6" ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c), (d), and (g). ALL WORK DONE PER WFPP.
Permit Issued
Issued on 10/18/2021
Issuing Office
Current Status
CofO in Progress on 5/2/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/20/2021 APPLICANT
Assigned to Plan Check Engineer 5/26/2021 ARTIN ZARUKIAN
Corrections Issued 5/27/2021 ARTIN ZARUKIAN
Plan Check Approved 10/8/2021 ARTIN ZARUKIAN
Issued 10/18/2021 APPLICANT
Building Plans Picked Up 10/19/2021 APPLICANT
CofO in Progress 5/2/2025 MORRIS JACKSON
CofO in Progress 5/14/2025 MORRIS JACKSON

Permit Application Clearance Information

Address approval Cleared 6/14/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 6/14/2021 ADRIAN CASTRO
Sewer availability Cleared 6/14/2021 ADRIAN CASTRO
Hydrant and Access approval Cleared 8/27/2021 GILBERT URREA
ZA Case Cleared 9/15/2021 LAUREN PADICK
ZI Cleared 9/15/2021 LAUREN PADICK
ZI Cleared 9/15/2021 LAUREN PADICK
Low Impact Development Cleared 9/22/2021 TA ANH
Roof/Waste drainage to street Cleared 9/23/2021 ABDULLAH SADOZAI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/22/2024 Partial Approval JON MCHUGH
Excavation/Setback/Form/Re-Bar 7/25/2024 Approved MORRIS JACKSON
Footing/Foundation/Slab 7/29/2024 Approved MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 8/7/2024 Partial Approval TROY SANDERS
ELECTRICAL-Rough 8/13/2024 Corrections Issued MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 8/13/2024 Partial Approval MORRIS JACKSON
HVAC-Rough 8/13/2024 Not Ready for Inspection MORRIS JACKSON
PLUMBING-Rough 8/13/2024 Approved MORRIS JACKSON
BUILDING-Rough-Frame 8/22/2024 Corrections Issued JON MCHUGH
ELECTRICAL-Rough 8/22/2024 Approved JON MCHUGH
HVAC-Rough 8/22/2024 Not Ready for Inspection JON MCHUGH
Interior/Exterior Lathing 8/22/2024 Approved JON MCHUGH
BUILDING-Rough-Frame 8/27/2024 Approved JON MCHUGH
Green Building Rough 8/27/2024 Approved JON MCHUGH
HVAC-Rough 8/27/2024 Approved JON MCHUGH
Verify Sprinkler Sign Off 8/27/2024 Approved JON MCHUGH
Insulation 8/29/2024 Approved SCOTT SOBEL
Drywall Nailing 8/30/2024 Approved JON MCHUGH
Final 11/20/2024 Corrections Issued JON MCHUGH
Green Building Final 11/20/2024 Not Ready for Inspection JON MCHUGH
SGSOV-Seismic Gas S/O Valve 11/20/2024 SGSOV Not Ready JON MCHUGH
Service/Power Release 11/20/2024 Not Ready for Inspection JON MCHUGH
Smoke Detectors 11/20/2024 Approved JON MCHUGH
Final 12/23/2024 Corrections Issued JOHN COLEMAN
Final 12/23/2024 Partial Inspection MORRIS JACKSON
Green Building Final 12/23/2024 Approved JOHN COLEMAN
SGSOV-Seismic Gas S/O Valve 12/23/2024 SGSOV Approved JOHN COLEMAN
Service/Power Release 12/23/2024 Not Ready for Inspection JOHN COLEMAN
Final 4/1/2025 Corrections Issued MORRIS JACKSON
Service/Power Release 4/1/2025 Not Ready for Inspection MORRIS JACKSON
Final 5/2/2025 Partial Approval MORRIS JACKSON
Service/Power Release 5/2/2025 Approved MORRIS JACKSON
Final 5/14/2025 Corrections Issued MORRIS JACKSON